20218: For the erection of a single storey extension, comprising a single classroom with en-suite toilets, accessible shower/WC, SET room and store room (gross floor area 134.4 m2), connection to existing on-site services and all associated site works
Carrigduff National School, Carrigduff, Bunclody
DecisionConditional grant
Decided17 August 2020
Application typePERMISSION
Source documents3
Site
What is on file
0refusal reasons8conditions8nearby records
Decision details
Core application dates and identifiers from the public planning record.Planning analysis
Refusal reasons and planning conditions extracted from the public decision file.Refusal reasons
No refusal reason
No refusal reason is on record for this application yet.
Conditions
- 1Development must be carried out in accordance with plans received 01/07/2020, except where amended by conditions.Compliance
- 2External finishes, including roof tiles/slates, must match the existing school building in colour and texture unless agreed in writing.Design Materials
- 3Onsite retaining walls must be built as retaining walls. A structural engineer's certification of adequacy must be submitted within one month of construction.Compliance
- 4Applicant must sign an Irish Water connection agreement prior to commencement, comply with CDS Technical Documentation, and accept constraints of the Irish Water Capital Investment Programme.Water Services
- 5Construction traffic must park off-carriageway, keep public roads clean, maintain a litter-free site, and ensure noise/dust emissions do not impair amenities beyond the site boundary.Construction Management
- 6Construction hours restricted to Mon-Fri 08.00-18.00 and Sat 08.00-13.00. No work on Sundays or Bank Holidays without prior written approval.Construction Management
- 7Service poles requiring relocation must be moved prior to construction. All ESB, telephone, and other cables must be placed underground at the applicant's expense unless otherwise agreed.Other
- 8Prior to commencement, the applicant must consult the Chief Fire Officer and strictly comply with any fire safety requirements made thereafter.Compliance
Source documents
Original council portal records and source PDFs where available.- Application fileApplication file on www.eplanning.ieSource portal
- Notification Of DecisionSource: carlowcoco.eplanning.ie / B7a068ff-7cf5-4e7b-855e-5e24f4fab225.pdf / Document 111161Source PDF
- Final GrantSource: carlowcoco.eplanning.ie / 4506b5b1-c101-4bd2-8413-6bfa9c6c3c5d.pdf / Document 111162Source PDF
Nearby precedent
Similar nearby applications linked to this planning decision.- 19407For the erection of a single storey prefabricated temporary unit, comprising of 1 No. 80m2 classroom, and associated site works. / 0.0 km away / 21 January 2020Conditional grant
- 22212To consist of refurbishment and enlargement of existing playground, new bicycle track for children and all associated site works / 0.2 km away / 11 November 2022Conditional grant
- 20474Permission for the construction of two no. single storey dwellings, a single storey domestic garage, an independent wastewater treatment system for each dwelling and all associated site works. A Natura Impact Statement (NIS) will be submitted to the Planning Authority with the application. / 0.3 km away / 15 July 2021Conditional grant
- 22271Of a detached domestic garage to the rear of the dwelling / 0.3 km away / 26 January 2023Conditional grant
- 22278A single storey extension to the rear of dwelling / 0.3 km away / 07 October 2022Conditional grant
- 1993Unauthorised works to include the construction of extension to the rear and side of existing dwelling, the construction of a detached building used as a store and office as part of my existing dwelling, the construction of a shed / garage and all associated site works / 0.3 km away / 09 July 2019Conditional grant
- 2165Permission to construct an extension to the rear of dwelling house and planning permission for elevational changes to existing dwelling house with all associated site works / 0.3 km away / 21 April 2021Conditional grant
- 2368The construction of 27 no. dwellings to be constructed in 3 phases of nine dwellings in each phase, to include 2 no. single storey and seven no. two storey dwellings in each phase and all associated site works / 0.3 km away / 01 February 2024Conditional grant