Conditional grantDecided 07 April 2021Carlow County Council

20392: Construction of a rock ramp fish pass in front of the existing Ballinacarrig Weir. The fish pass will require the lowering of a section of the weir. A Natura Impact Statement (NIS) will be submitted with this Planning Application.

On the River Burren on the, boundary of the townlands of Carlow, and Ballinacarrig.
DecisionConditional grant
Decided07 April 2021
Application typePERMISSION
Source documents4

Site

What is on file

0refusal reasons14conditions8nearby records

Decision details

Core application dates and identifiers from the public planning record.

Planning analysis

Refusal reasons and planning conditions extracted from the public decision file.

Refusal reasons

No refusal reason

No refusal reason is on record for this application yet.

Conditions

  • 1Work must follow approved plans (6 Nov 2020) and amended FI response (12 Feb 2021).Compliance
  • 2Permission is strictly limited to the development detailed in the application.Compliance
  • 3Undertake a licensed Underwater Archaeological Impact Assessment (UAIA) by a qualified archaeologist, including metal detection and mitigation. No works until Planning Authority written agreement.Archaeology Heritage
  • 4Strictly implement all mitigation in the revised Natura Impact Statement and Construction Environmental Management Plan.Environment Ecology
  • 5Supervision by qualified environmental personnel/ecological clerk of works. Qualifications submitted before commencement.Environment Ecology
  • 6Vegetation cutting outside bird breeding season (1 Mar-31 Aug). In-river works confined to July-Sept. No works during flood conditions.Environment Ecology
  • 7Follow Hydrology Report. Suspend work during floods. Use existing sluice for flow control. Treat silted water via vegetated areas/sediment traps; no direct discharge to river.Environment Ecology
  • 8Noise and vibration limited to BS 5228-1:2009+A1:2014 and BS 5228-2:2009+A1:2014 standards.Construction Management
  • 9Dust at site boundary < 350 mm/m²/day over 30-day composite, complying with VDI 2119.Construction Management
  • 10Daily machinery fuel leak checks. No fuel storage. No surface water discharges to watercourses. Comply with CIRIA C532 and IFI guidelines. Prevent spread of Alien Invasive Species.Environment Ecology
  • 11Development shall not impair the operation of existing land drainage.Environment Ecology
  • 12Alterations to existing entrances or construction signage require prior written agreement of the Municipal District Engineer.Traffic Access

Source documents

Original council portal records and source PDFs where available.

Nearby precedent

Similar nearby applications linked to this planning decision.