Conditional grantDecided 18 January 2024Carlow County Council

23137: To construct a boiler housing unit and Wood Chip Silo and all associated site works

Downings, Tullow, Co. Carlow
DecisionConditional grant
Decided18 January 2024
Application typePERMISSION
Source documents5

Site

What is on file

0refusal reasons10conditions8nearby records

Decision details

Core application dates and identifiers from the public planning record.

Planning analysis

Refusal reasons and planning conditions extracted from the public decision file.

Refusal reasons

No refusal reason

No refusal reason is on record for this application yet.

Conditions

  • , Development must follow approved plans received 14/08/2023 and FI received 15/12/2023.Compliance
  • , Operate silo and boiler per FI (15/12/2023), install multi-cyclone filter, use fuel compliant with Irish Bioenergy Association standard.Environment Ecology
  • , Submit revised plans/elevations prior to commencement showing external finishes (colour) and external flue height.Design Materials
  • , Permission covers only the authorised development; does not extend to other exempted development on site.Compliance
  • , Do not impair existing drainage; no surface water to public road/properties; dispose to on-site soakways/system per B.S. 8301:1985 and BRE Digest 365 with inspection covers.Wastewater Drainage
  • , Consult Municipal Engineer before interfering with road/footpath; obtain Road Opening Licence for any openings; no materials stored on public road/footpath during construction.Traffic Access
  • , Provide off-carriageway parking for all construction traffic; keep vehicles clean; maintain litter-free site; confine noise/dust/debris to site; restrict works to approved layout.Construction Management
  • , Construction hours restricted to Mon-Fri 08:00-18:00 and Sat 08:00-13:00. No work on Sundays/Bank Holidays without prior written approval.Construction Management
  • , Consult Chief Fire Officer prior to commencement and comply with all fire safety requirements.Compliance
  • , Pay €541.04 development contribution prior to commencement (Silo 19.63m² @ €8/m² = €157.04; Boiler House 48m² @ €8/m² = €384). 5% p.a. interest applies from grant date after 90-day discount.Development Contribution