Conditional grantDecided 20 February 2024Carlow County Council

2360309: The erection of an extension and alterations to existing dwelling and all associated site works

29 The Ring, Tinnahinch, Graiguenamanagh
DecisionConditional grant
Decided20 February 2024
Application typePERMISSION
Source documents5

Site

What is on file

0refusal reasons10conditions8nearby records

Decision details

Core application dates and identifiers from the public planning record.

Planning analysis

Refusal reasons and planning conditions extracted from the public decision file.

Refusal reasons

No refusal reason

No refusal reason is on record for this application yet.

Conditions

  • , Development to be carried out in accordance with plans received by the Planning Authority on 20/12/2023.Compliance
  • ,Permission authorises only the development described in public notices and plans received by the PA.Compliance
  • ,Prior to commencement, submit revised elevation drawings specifying external wall finish. Roof finish colour must match existing house.Design Materials
  • ,Do not impair existing land/roadside drainage. No surface water to public road or adjoining properties. All surface water to soakaways/system on site per B.S. 8301:1985 and BRE Digest 365. Only clean surface water to soakpits; foul waste to public sewer.Wastewater Drainage
  • ,Sign Uisce Éireann connection agreement prior to commencement. Comply with Uisce Éireann CDS Technical Documentation. Submit diversion/build-over proposals for written approval. Adhere to separation distances and Capital Investment Programme constraints.Water Services
  • ,Do not interfere with public road/footpath without consulting Municipal District Engineer. Road opening works require a Road Opening Licence per Guidelines 2017, submitted for written agreement prior to commencement.Traffic Access
  • ,Provide adequate off-carriageway parking for construction traffic; no parking on public road. Prevent muck/debris on public road. Maintain site neat/litter-free with skips on site. Control noise/dust emissions. No materials on public road without Municipal Engineer consent.Construction Management
  • ,Construction hours restricted to Mon-Fri 08.00-18.00 and Sat 08.00-13.00. No work on Sundays or Bank Holidays.Construction Management
  • ,Consult Chief Fire Officer prior to commencement and strictly comply with recommendations.Compliance
  • ,Pay development contribution of €156.00 prior to commencement. Interest at 5% p.a. applies after first 90 days.Development Contribution