19643: For development which will consist of: 1) The construction of a new wastewater treatment plant adjacent to the existing wastewater tidal outfall tank at Skagh Point, Kilrush comprising of inlet screening works, 2 No. primary settlement tanks, stormwater and sludge holding tanks, administration building, site lighting. 2.4m high boundary fencing and a scheme identification sign with access provided via a new entrance onto the public road network. All associated site development and site excavation works above and below ground for the wastewater treatment plant; and 2) the construction of a new storage tank in greenfield lands adjacent to Frances Street Pumping Station at Cappagh Road, Kilrush comprising of an underground concrete storm storage tank, landscaping, site lighting, 2.4m high boundary fencing with access provided via a new entrance onto Cappagh Road. All associated site development and site excavation works above and below ground for storage tank. A Natura Impact Statement has been prepared in respect of this planning application
Skagh Point, Kilrush, Co. Clare
DecisionConditional grant
Decided01 October 2019
Application typePERMISSION
Source documents7
Site
What is on file
0refusal reasons0conditions8nearby records
Decision details
Core application dates and identifiers from the public planning record.Planning analysis
Refusal reasons and planning conditions extracted from the public decision file.Refusal reasons
No refusal reason on record
Documents are indexed. Reason extraction for Clare has not started yet.
Conditions
No conditions
No conditions are on record for this application yet.
Source documents
Original council portal records and source PDFs where available.- Application fileApplication file on www.eplanning.ieSource portal
- Chief Executives OrderSource: clarecoco.eplanning.ie / 5a53fd5d-0f99-4bcf-9d87-9bbaf4283b89.PDF / Document 461492Source PDF
- Final Grant / file 1 of 2Source: clarecoco.eplanning.ie / 672921.PDF / Document 468579Source PDF
- Final Grant / file 2 of 2Source: clarecoco.eplanning.ie / 672922.PDF / Document 468579Source PDF
- Planners ReportSource: clarecoco.eplanning.ie / 32540aeb-209d-43a8-a255-3422ad0ae19e.PDF / Document 461498Source PDF
- Planners ReportSource: clarecoco.eplanning.ie / 82a14929-a326-4c3b-8ca8-0a076db38bd0.PDF / Document 461499Source PDF
- Planners ReportSource: clarecoco.eplanning.ie / B6055ee1-d66c-44dd-bf3d-744c03771912.PDF / Document 462587Source PDF
Nearby precedent
Similar nearby applications linked to this planning decision.- 2560061For development which will consist of (1) the demolition of existing extensions to front, LHS, RHS and rear of original cottage, (2) the retrofit of original cottage, (3) the provision of a new extension to LHS of original cottage, (4) the provision of a garage, carport and externally covered areas to front and rear, (5) driveway entrance at position of existing agricultural entrance, and (6) all related site works / 0.3 km away / 11 February 2026Granted
- 17157To extend existing graveyard consisting of proposed plots, concrete plinth bases for headstones, gravel pathways, extension to existing service / access road within graveyard, upgrade existing land drainage within site, and ancillary site works / 0.3 km away / 01 June 2017Granted
- 2360280To construct 10 no. housing units consisting of 6 no. 3 bedroom semi-detached units and 4 no. 2 bedroom semi-detached units together with all associated ancillary site works and services / 0.4 km away / 20 September 2023Granted
- 2360094To construct 18 no. social housing units together with all associated ancillary site works and services / 0.4 km away / 28 July 2023Granted
- 17147To carry out refurbishment and reconfiguration works including alterations to the elevations and the construction of a private garage with all associated ancillary works / 0.4 km away / 25 April 2017Granted
- 25172Of the following works: a) retention of the light engineering workshop in the old seaweed factory building. b) retention of the new side cladding and access doors to old sea-weed factory building. c) retention of the existing palisade fencing and entrance gates. d) retention of the existing storage area. e) retention of the existing carparking. Please note that these works will be carried out within the curtilage of an existing protected structure / 0.4 km away / 25 February 2026Granted
- 23628To change of use of property from holiday home to permanent residence / 0.4 km away / 06 February 2024Granted
- 248003Proposes to carry out the following development: 1. Public realm enhancement works to include upgrades to and creation of new continuous footpaths, provision of a pedestrian friendly raised table with new courtesy crossings, road realignment, formalising of on street car parking and provision of age friendly parking, relocation of existing and provision of new street lighting and street furniture. 2. Creation of new pedestrian footpath to the playground and beach and a new civic space adjacent to the existing playground, including alterations to the existing stone wall to facilitate the new access and viewing points. 3. All associated services, site development and landscaping works. In accordance with the Habitats Directive, Appropriate Assessment Screening has been carried out on the project. An Environmental Impact Assessment (EIA) screening determination has been made and concludes that there is no real likelihood of significant effects on the environment arising from the proposed development. The subject works are partially located within the Cappa Architectural Conservation Area and would materially effect the character of the area concerned. / 0.5 km away / 08 July 2024Granted