GrantedDecided 19 March 2026Clare County Council

Within the townlands of Woodpark TD and Leitrim TD, near Bridgetown, Co. Clare

Planning application 2560794
DecisionConditional grant
Decided19 March 2026
Application typePERMISSION
Source documents8

Site

What is on file

0refusal reasons0conditions8nearby records

Proposed development

Application description published by Clare County Council.
The proposed development, on an overall site of 3.58 hectares, will consist of: A co-located Battery Energy Storage System (BESS) Compound with associated internal access tracks; Access to the proposed BESS compound will be from the R466 local road and will consist of the use of an existing quarry entrance in the townland of Leitrim which will be upgraded as permitted as part of the Fahy Beg Wind Farm (under Clare County Council Ref: 23148 & ACP Ref 317227); Installation of grid code compliance equipment to facilitate an under-the-fence connection to the adjacent Fahy Beg 38kV substation. The grid code compliance equipment will include: Backup Generator, Neutral Earthing Resistor (NER), Auxiliary House Transformer, Marshalling Kiosks; 3 no. spare parts shipping containers (measuring 12.2 m (L) x 2.4 m (W) x 2.6 m (H)); and Associated ancillary development. Installation of 32 no. Battery Energy Storage Units comprising metal shipping containers housing batteries (measuring 6 m (L) x 2.4 m (W) and 2.9 m (H) each), and associated ancillary control and ventilation units; Installation of 8 no. Medium Voltage (MV) Inverter Stations comprising metal shipping containers housing the inverter, MV transformer, and an MV-LV room (measuring 6 m (L) x 2.4 m (W) and 2.9 m (H) each); Installation of 1 no. water storage tank (measuring 5.15 m (L) x 4.15 m(W) x 2.58 m (H)); Construction of 250m of new access tracks; Provision of a crane hardstanding area to facilitate lifting operations on site (280m2); Provision of 10 no. car parking spaces (8 no. standard parking spaces, and 2 no. accessible parking spaces); Reprofiling of the existing cut slope embankment with the erection of a gabion basket retaining wall measuring 75m in length and 2.5m in height, and construction of a reinforced fill slope embankment; Underground electrical and communications cabling; Security lighting, CCTV and communications mast; Provision of 150m of Sound reflective barriers; Security fencing and gates; Drainage system including on-site surface water attenuation ponds; Tree felling of 0.19 Ha (1,890m2) to facilitate required clearance for BESS compound, associated earthworks and drainage infrastructure; Removal of 109m of hedgerow to facilitate development of the BESS compound, and replanting of 109m at perimeter locations; and All associated ancillary site development and vegetation clearance works including landscaping and hedgerow reinstatement. The Applicant requests that the development be

Application and appeal history

Structured appeal stages, outcomes and source documents currently tied to this application.
PL-501167-CE-26Submitted 15 April 2026 / decided Not recorded
Status not recorded
No appeal document has been bound to this case yet; the timeline will enrich as indexing continues.

Decision details

Core application dates and identifiers from the public planning record.

Planning analysis

Refusal reasons and planning conditions extracted from the public decision file.

Refusal reasons

No refusal reason on record

No refusal reason is on record for this application yet.

Conditions

No conditions

No conditions are on record for this application yet.

Planning a project near Within the townlands of Woodpark TD and Leitrim TD, near Bridgetown, Co. Clare?

Get a site risk brief with the local decision pattern and up to 80 detailed nearby comparables (40 refusals and 40 grants), including extracted reasons and source links. €29 incl. VAT, PDF by email.

Inside the decision file

Extracts from the council's own decision documents for this application — 87 pages of searchable text on file.
Chief Executives Order2 pages indexed
CLARE COUNTY COUNCIL PLANNING AND DEVELOPMENT ACT 2000 (AS AMENDED) no: ¥XO\b p SUBJECT: ORDER: Application by RWE Renewables Ireland Ltd. for PERMISSION for proposed development, on an overall site of 3.58 hectares, will consist of: A co-located Battery Energy Storage System (BESS) Compound with associated internal...
Chief Executives Order6 pages indexed
CLARE COUNTY COUNCIL PLANNING AND DEVELOPMENT ACT 2000 (AS AMENDED) Order No: File Reference Number: Name of Applicant: Address: Application Received: Nature of Application: FALYS P25/60794 RWE Renewables Ireland Limited c/o Fehily Timoney & Company Core House Pouladuff Road Cork T12 D773 12/12/2025 Permission for the...
Notification Of Decision16 pages indexed
C la re Pl a nn ng Au th or ity -I ns pe ct io n Pu rp os es O nl y!
Read the full decision filePro members can search and read every indexed page of this file with the AI research assistant — planner's reasoning, conditions, and precedent across 7 documents.

Source documents

Original council portal records and source PDFs where available.

Nearby precedent

Similar nearby applications linked to this planning decision.
Get up to 80 detailed nearby comparables in a site risk brief →