GrantedDecided 21 August 2025Cork County Council

The Existing Cloyne 38kV Substation Demesne Cloyne Co Cork

Planning application 25/5257
DecisionConditional permission
Decided21 August 2025
Application typePermission
Source documents1

Site

What is on file

0refusal reasons0conditions8nearby records

Proposed development

Application description published by Cork County Council.
10 Year Planning Permission for a physical extension of c. 562 sq.m to the existing electricity substation compound and will include: 1) Site clearance works including removal of:- a) 1 no. MV poles and associated overhead lines. b) Existing MV busbar and associated electrical equipment. c) Existing 38 kV busbar and associated electrical equipment. d) Existing 2 no. 38 kV/MV transformers. e) All existing site fencing and gates. f) Existing lighting. g) Demolition of existing single storey control building (c. 12 sq.m), h) Existing vegetation along northern, eastern and southern site boundaries. 2) Provision of new electrical plant and equipment including:- a) 1 no. prefabricated control room, GIS and MV module and foundation (98.46 sqm). b) 1 no. prefabricated customer control room module and foundation (24.43 sq.m). c) 3 no. customer transformers and associated bunds. d) 1 no. relocated interface transformer and new bunds. e) 2 no. house transformers and associated bunds. f) Associated and ancillary electrical equipment and other apparatus, including installation of underground cables. g) Site development works including provision of lighting; resurfacing and internal access roads, new fencing and access gates (including new entrance gate onto public road). Provision of site services including drainage and all other ancillary works.

Application and appeal history

Structured appeal stages, outcomes and source documents currently tied to this application.

No indexed appeal history

No structured appeal case is tied to this application. This means no appeal is indexed, not that an appeal is impossible.

Decision details

Core application dates and identifiers from the public planning record.

Planning analysis

Refusal reasons and planning conditions extracted from the public decision file.

Refusal reasons

No refusal reason on record

Documents are indexed. Reason extraction for Cork has not started yet.

Conditions

No conditions

No conditions are on record for this application yet.

Planning a project near The Existing Cloyne 38kV Substation Demesne Cloyne Co Cork?

Get a site risk brief with the local decision pattern and up to 80 detailed nearby comparables (40 refusals and 40 grants), including extracted reasons and source links. €29 incl. VAT, PDF by email.

Source documents

Original council portal records and source PDFs where available.

Nearby precedent

Similar nearby applications linked to this planning decision.
Get up to 80 detailed nearby comparables in a site risk brief →