4152/19: The development consists of: Removal of three bitumen storage tanks of size 60 tonne, 80 tonne & 500 tonne and installation of four bitumen storage tanks of size 50 tonne, 235 tonne, 235 & 15 tonne. Also included is the modification of an existing electrical plant building, modifications include installation of a staircase and additional floor to the building. The new floor of the building will be used as an electrical plant room and will raise the height of the building from approximately 4 metres to 7.3 metres.
Irish Tar & Bitumen Suppliers, Alexandra Road, Dublin 1.
DecisionGrant permission
Decided28 November 2019
Application typePermission
Source documentsPending
Site
What is on file
0refusal reasons0conditions8nearby records
Decision details
Core application dates and identifiers from the public planning record.Planning analysis
Refusal reasons and planning conditions extracted from the public decision file.Refusal reasons
No refusal reason on record
Documents are indexed. Reason extraction for Dublin City has not started yet.
Conditions
No conditions
No conditions are on record for this application yet.
Source documents
Original council portal records and source PDFs where available.Source link pending
This application was published at source, but the document inventory has not been bound yet.
Nearby precedent
Similar nearby applications linked to this planning decision.- WEB2497/24Removal of the existing Tank 3 (378.5 tonnes bitumen) and installing Tank 4C (198.45 tonnes bitumen), also adding horizontal walkway from Tank 2 to portion of spiral stair on Tank 4C and another horizontal walkway linking Tank 4B to Tank 4C. / 0.0 km away / 09 January 2025Granted
- 2771/19The development will consist of: Demolition of an existing single storey building and construction of a new two storey building with a footprint of 14.9m by 5.6m. The building will consist of concrete foundations, blockwork walls, an external cladding and plaster finish, a trapezoidal roof, an internal concrete stairs and an external steel stairs. The building will be subdivided into a production area and store at ground floor level and an office and store rooms at first floor level. The building will be connected to the site's existing storm drainage and electrical services. / 0.0 km away / 10 June 2019Granted
- 4115/19The development will consist of the removal of a redundant fire water storage tank of 7.6m in diameter and 7.5m in height with a volume of approximately 340m3 and the installation of a new bitumen storage tank of 3.37m in diameter and 17.3m in height with a volume of approximately 100m3. / 0.2 km away / 25 November 2019Granted
- 3733/20The development will consist of the installation of a new bitumen storage tank of 30m in diameter and 19.2m in height with a volume of approximately 11,300m3 and the installation of an aromatic oil tank of 8m in diameter and 12.8m in height with a volume of approximately 600m3. A concrete containment area will also be installed around the perimeter of the proposed tanks. / 0.2 km away / 05 May 2021Granted
- 2697/20The development will consist of alterations to the existing North Wall Power Generating station, which include the replacement of existing indoor gas turbines with new and more efficient indoor gas turbines, the replacement of one of the two existing exhaust chimney stack’s (approx. 70m tall) and its re-construction at a reduced height of 65m to mirror the second existing exhaust stack, the installation of new gas compressors with associated fan coolers, the replacement of existing roof-mounted fan coolers, a fuel oil pumphouse, a demineralised water pumphouse, a new 1,000m3 demineralised water tank (approx. 10m tall), a new 1,000m3 gas oil storage tank (approx. 10m tall), the repurposing of an existing 4,000m3 fuel oil storage tank as a demineralised water storage tank of the same volume, a new fire water tank (approx. 10m tall), a new tanker unloading area comprising a concrete pad, emergency diesel generator, a new administration and welfare building, minor modifications to existing surface water drainage, a new entrance opening on to Alexandra Road and revised internal road layout and minor ancillary plant and equipment structures. The development will also comprise the removal of existing structures including; 70m tall stack and associated boiler, part of the administration building, canteen, stores building and water treatment buildings, gas compressor building as well as a water storage tanks, a bottle storage area and other minor redundant installations. The development will also include all other necessary associated works required to enable the construction and operation of the facility. An Environmental Impact Assessment Report (EIAR) has been prepared and is submitted as part of the planning application. It should be noted that this facility is identified as a Lower Tier site under the COMAH directive, furthermore the facility has an existing Industrial Emissions Licence which is regulated by the Environmental Protection Agency. All required licences and plans will be reviewed as required. / 0.2 km away / 17 July 2020Granted
- 3872/20The site is adjacent to Breakwater Road and Jetty Road. The development consists of removal of twelve bitumen & lubricant oil storage tanks with total capacity 3,105m3, removal of the associated equipment and removal of a control room building, followed by the installation of a new bitumen storage tank of 28m in diameter and 13.45m in height with a volume of approximately 8,275m3 and installation of a pump platform. / 0.3 km away / 08 April 2021Granted
- 2071/20Planning Permission for development at this site address: Circle K Yard 3, Alexandra Road, Dublin Port, Dublin 1. This site is regulated by the Major Accidents Directive. The development will consist of: Increasing the containment volume of the existing bund. Modifications will include raising the height of the existing bund wall by circa 0.5m, extending the bund to the east and lowering the ground level in the area of this bund extension from approximately 4.07m to 3.8m. The site's storm water, fresh water and foul sewer drainage will be modified to accommodate the bund extension. / 0.3 km away / 12 March 2020Granted
- WEB2823/24The replacement of approximately 52 m of existing 2.4 m high chainlink perimeter fencing and associated access / emergency gates with new 2.4 m high security fencing, gates, 2 no. 8 m CCTV poles and all associated site works. / 0.3 km away / 21 February 2025Granted