GrantedDecided 28 August 2025Dublin City Council

WEB2226/25: The proposed development will consist of a battery energy storage system (BESS) located within a fenced compound and will (subject to detailed design, commercial and technical considerations) comprise of 1. Up to 60 no. battery energy storage enclosures, split across 6 no. bays, each bay contains 2 no. rows of 5 no. enclosures. Each bay is on a concrete plinth of width c. 6.5 m and a maximum length of c. 47 m. Each battery enclosure will incorporate battery packs as well as power electronics, battery management systems, cooling units and fire suppression systems. 2. 6 No. Medium Voltage (MV) Skids, twin Inverter Skids (c. 12.8m x 6m x 2.4m) and associated bunds and fire walls. 3. Control building (c. 222 sq.m). 4. Ancillary plant and equipment comprising of a) A firefighting water tank (c. 9.75m high) and pumphouse (c. 17 sq.m) b) 2 no. Auxiliary Transformers (c. 2m x 2m x 2m) and associated bunds and fire walls c) 3 no. spare parts stores (20ft containers) (c. 15 sq.m each) d) 2 no. backup diesel generator plinths (c. 28.7 sq.m each) e) HV compound including 2 no. Grid step-up transformers (c. 5.7m x 3.3m x 2.8m and c. 6.6m x 5.5m x 5.1m), associated bunds and fire walls, and all other associated equipment including prefabricated electrical control room (c. 51 sq.m), linking with an underground cable and f) An underground fire water retention tank and underground attenuation tank. 5. Operation and Maintenance site offices including welfare facilities (c. 27.9 sq.m) 6. All service connections including electrical, potable water and connections to surface water drains 7. 1 no. lightning monopole (c. 18m high) and 8. All other ancillary site clearance and development works including provision of areas of hardstanding, internal access roads lighting and CCTV, laydown area, fencing and access gates (c. 3.5m in height), car parking; and connections to site services and networks. Planning permission is being sought for a duration of 10-years.

A c. 1.7 ha site located within the ESB Inchicore substation site, specifically lands south of Kylemore Way and northwest of the existing ESB Substation, Kylemore Way, Dublin 8, D08 E398 and to the immediate west of the Kylemore BESS, Kylemore Road, Dubli
DecisionGrant permission
Decided28 August 2025
Application typePermission
Source documentsPending

Site

What is on file

0refusal reasons0conditions8nearby records

Decision details

Core application dates and identifiers from the public planning record.

Planning analysis

Refusal reasons and planning conditions extracted from the public decision file.

Refusal reasons

No refusal reason on record

Documents are indexed. Reason extraction for Dublin City has not started yet.

Conditions

No conditions

No conditions are on record for this application yet.

Planning a project near A c. 1.7 ha site located within the ESB Inchicore substation site, specifically lands south of Kylemore Way and northwest of the existing ESB Substation, Kylemore Way, Dublin 8, D08 E398 and to the immediate west of the Kylemore BESS, Kylemore Road, Dubli?

Get the precedent report for this site: every grant and refusal within 5 km, and the planners' reasons. €49 incl. VAT, PDF by email.

Source documents

Original council portal records and source PDFs where available.

Source link pending

This application was published at source, but the document inventory has not been bound yet.

Nearby precedent

Similar nearby applications linked to this planning decision.
Full reasons for every nearby decision are in the site report →