D22A/0810: The proposed development relates to the provision of 8 no. electric vehicle (EV) charging points and associated parking spaces, a substation to serve the EV charging points and signage which will be fixed to the southern facade of the Unit 235 to indicate the location of the charging points. The development includes associated hard and soft landscaping, provision of electrical and site services and all associated and ancillary works.
Site to South of Unit 235 (occupied by TK Maxx) and to North of Park Avenue, Carrickmines Park, Carrickmines Great and Jamestown, Dublin 18
DecisionGrant permission
Decided16 December 2022
Application typePermission
Source documents5
Site
What is on file
0refusal reasons0conditions8nearby records
Decision details
Core application dates and identifiers from the public planning record.Planning analysis
Refusal reasons and planning conditions extracted from the public decision file.Refusal reasons
No refusal reason on record
Documents are indexed. Reason extraction for Dún Laoghaire–Rathdown is in progress.
Conditions
No conditions
No conditions are on record for this application yet.
Planning a project near Site to South of Unit 235 (occupied by TK Maxx) and to North of Park Avenue, Carrickmines Park, Carrickmines Great and Jamestown, Dublin 18?
Get the precedent report for this site: every grant and refusal within 5 km, and the planners' reasons. €49 incl. VAT, PDF by email.Source documents
Original council portal records and source PDFs where available.- Planners ReportSource: planningapi.agileapplications.ie / Report_D22A0810.pdf / Document 4599538Source PDF
- ReportsSource: planningapi.agileapplications.ie / 221101090303-1016.pdf / Document 4591332Source PDF
- ReportsSource: planningapi.agileapplications.ie / D22A0810_Site_to_South_of_Unit_235_(occupied_by_TK_Maxx)__and_North_Avenue.docx / Document 4597304Source PDF
- ReportsSource: planningapi.agileapplications.ie / Public_Lighting_D22A-0810_December_2022.doc / Document 4597368Source PDF
- ReportsSource: planningapi.agileapplications.ie / 0810_Public_Lighting_Report_05Dec2022.doc / Document 4597409Source PDF
Nearby precedent
Similar nearby applications linked to this planning decision.- D07A/1543665 m2 net (895 m2 gross) comparison retail mezzanine / 0.0 km away / 11 January 2008Granted
- D20A/0654Full permission. The proposed development relates to the provision of a two-storey building comprising a café unit (135 sq.m) and public restrooms at ground floor level, with administration / office space (218 sq.m) provided at first floor level. The proposed building will provide a total gross floor area of 491 sq.m over two storeys, with a maximum height of c. 8 metres. The development includes the removal of three existing car parking spaces, hard and soft landscaping, plant, signage associated with the proposed café unit, waste management facilities, relocation of an existing pedestrian crossing, and all associated and ancillary works. / 0.0 km away / 08 January 2021Granted
- D05A/0922Permission for (a) additional means of escape doors to rear and (b) / 0.0 km away / 09 September 2005Granted
- D05A/0906Permission for the construction of an internal mezzanine floor level / 0.1 km away / 07 September 2005Granted
- D15A/0766Permission for modifications to the Block 90 office building as originally permi / 0.1 km away / 29 April 2016Granted
- D07A/1180(A) minor alterations to rear elevational treatment / 0.1 km away / 11 October 2007Granted
- D21A/0535Permission is sought for the construction of a 43 sqm / 0.1 km away / 30 July 2021Granted
- D05A/0428(A) Revised elevational treatment at the rear / 0.1 km away / 01 June 2005Granted