GrantedDecided 02 April 2026Fingal County Council

F25A/0776E: The development will consist of amendments to the grid connection infrastructure between the approved solar photovoltaic (“PV”) energy development on lands at Mainscourt, Ballyboghill, Co. Dublin and the ESB Mountgory 38kV Substation, Swords Business Park, Swords, Co. Dublin permitted under Register Reference F22A/0365 comprising the laying of underground electricity cables in ducts and associated infrastructure within the margin of the R132 road and also beneath a portion of Balheary Park including under the Ward River by means of horizontal directional drilling. A Natura Impact Statement (NIS) will be submitted to the Planning Authority with the application. Additional Information Received 29/10/2025 Clarification of Additional Information Received 13/02/2026

South west corner of Balheary Park, Swords, Co. Dublin, and on the wes
DecisionGrant permission
Decided02 April 2026
Application typePermission
Source documents18

Site

What is on file

0refusal reasons0conditions8nearby records

Decision details

Core application dates and identifiers from the public planning record.

Planning analysis

Refusal reasons and planning conditions extracted from the public decision file.

Refusal reasons

No refusal reason on record

Documents are indexed. Reason extraction for Fingal is in progress.

Conditions

No conditions

No conditions are on record for this application yet.