FW23A/0016: The proposed development will consist of the construction of an industrial development facility for the processing and distribution of fresh and used cooking oils (UCO) including ancillary offices and staff amenities, roof-mounted photovoltaic array, delivery vehicle maintenance building, external covered storage area, weighbridge, lorry wash, tank farm, fuel tanks, signage, lighting, landscaping, car/lorry/trailer parking areas, and all associated site development works. Access to the proposed development will be from the existing industrial estate road abutting the site to the west that connects to the Ballycoolin Road to the north. A Local Authority permit (Recovery Code 13) is required for the used cooking oil process. AI received 09/05/23
Site B, Cappogue Industrial Park, Ballycoolin Road, Dublin 11
DecisionGrant permission
Decided31 May 2023
Application typePermission
Source documents22
Site
What is on file
0refusal reasons0conditions8nearby records
Decision details
Core application dates and identifiers from the public planning record.Planning analysis
Refusal reasons and planning conditions extracted from the public decision file.Refusal reasons
No refusal reason on record
Documents are indexed. Reason extraction for Fingal is in progress.
Conditions
No conditions
No conditions are on record for this application yet.
Planning a project near Site B, Cappogue Industrial Park, Ballycoolin Road, Dublin 11?
Get the precedent report for this site: every grant and refusal within 5 km, and the planners' reasons. €49 incl. VAT, PDF by email.Source documents
Original council portal records and source PDFs where available.- Application fileApplication file on planning.agileapplications.ieSource portal
- Notification Of DecisionSource: planningapi.agileapplications.ie / 29511FA6008A11EEB7D49C7BEFBB54FD.tif / Document 830100Source PDF
- Notification Of DecisionSource: planningapi.agileapplications.ie / 883B58A7C27F11EDB79F9C7BEFBB54FD.tif / Document 874244Source PDF
- Chief Executives OrderSource: planningapi.agileapplications.ie / 29511FA9008A11EEB7D49C7BEFBB54FD.tif / Document 830101Source PDF
- Chief Executives OrderSource: planningapi.agileapplications.ie / 883B58AAC27F11EDB79F9C7BEFBB54FD.tif / Document 874245Source PDF
- Final GrantSource: planningapi.agileapplications.ie / 6DE8634B209811EEB74AD81265959F30.tif / Document 871257Source PDF
- Planners ReportSource: planningapi.agileapplications.ie / 6901ECBD24A311EEA0A2D81265958418.pdf / Document 870640Source PDF
- ReportsSource: planningapi.agileapplications.ie / 3191477AB8DB11ED868600505692B757.doc / Document 830948Source PDF
- ReportsSource: planningapi.agileapplications.ie / 35F4538EB35911ED86860050569277E6.pdf / Document 831451Source PDF
- ReportsSource: planningapi.agileapplications.ie / 35F45390B35911ED86860050569277E6.docx / Document 831453Source PDF
- ReportsSource: planningapi.agileapplications.ie / 35F45398B35911ED86860050569277E6.pdf / Document 831461Source PDF
- ReportsSource: planningapi.agileapplications.ie / 41333806B6C311EDB90E84C5A60C64E0.pdf / Document 865728Source PDF
- ReportsSource: planningapi.agileapplications.ie / 5157C084F54E11ED8688005056926D4A.docx / Document 867530Source PDF
- ReportsSource: planningapi.agileapplications.ie / 83B0B5A8BE6011ED8686005056923C73.docx / Document 873753Source PDF
- ReportsSource: planningapi.agileapplications.ie / AE86C325A87F11EDB90684C5A60C64E3.pdf / Document 878613Source PDF
- ReportsSource: planningapi.agileapplications.ie / B06E222CF95011EDB710D03C1F93414D.pdf / Document 878795Source PDF
- ReportsSource: planningapi.agileapplications.ie / BE9AD0F1BCCC11EDB91184C5A60C64E3.docx / Document 880669Source PDF
- ReportsSource: planningapi.agileapplications.ie / C8022534F96C11EDB710D03C1F93414D.docx / Document 881822Source PDF
- ReportsSource: planningapi.agileapplications.ie / E7AF5500A3A211ED868100505692C209.docx / Document 885189Source PDF
- ReportsSource: planningapi.agileapplications.ie / E7AF5505A3A211ED868100505692C209.pdf / Document 885194Source PDF
- ReportsSource: planningapi.agileapplications.ie / EC3F5CF7D3A911EDB6EC4CEBBDB391AE.pdf / Document 885602Source PDF
- ReportsSource: planningapi.agileapplications.ie / F48E55A1C80211EDB91784C5A60C64E3.docx / Document 886541Source PDF
Nearby precedent
Similar nearby applications linked to this planning decision.- FW11A/0033The construction of a new waste recovery facility (total area 1393 sqm / 0.1 km away / 07 July 2011Granted
- FW20A/0122Permission for development an an existing C&D waste facility. The proposed development at the 0.75 ha site is for an increase in the rate of waste acceptance and processing at the facility up to 49,500 tonnes per annum, comprising mixed construction and demoliton (C&D) wastes. The planning application is accompanied by an Environmental Impact Assessment Report. / 0.2 km away / 21 September 2020Granted
- FW19A/0128Retention permission is being sought for 368.87m2 of floor space, including ground floor area (347.34m2) and first floor area (21.53m2) measuring a maximum height of 13.5m above ground level within the existing building permitted under previous Planning Permission FW13A/0053 and a 51 m long constructed boundary wall along the western boundary of the site consisting of a 2.7m high concrete wall with a 19m high palisade fence atop (total height 4.6m). Additional Information Lodged on 5th Dec 2019 Significant Additional Information Public Notices received on 19th Dec 2019 Clarification of Additional Information lodged on 25th March 2020 / 0.2 km away / 11 June 2020Granted
- FW13A/0053Retention permission for a 2 meter high earth mound along the new sout / 0.2 km away / 09 December 2013Granted
- FW25A/0296EPermission for development at a parcel of Land immediately south of Ballycoolin Road ( L3080) in the townland of Cappoge between Rosemount Business Park (north) and Premier Business Park (east) ( ITM X: 710273, y:739735) for the construction and establishment of an Electric Vehicle (EV) Bus Depot. The Proposed Development forms part of the NTA's Bus Connects programme. Spanning approximately 4 hectares within an urban industrial area south of Ballycoolin Road in Cappoge, Co. Dublin, the depot will accommodate around 176 buses. The Proposed Development will also accommodate administrative offices, maintenance facilities, electrical substation, and parking spaces. In all, the Proposed Development will consist of the following: • Administrative offices (including atrium entrance) (ground floor: 1,240m2, first floor: 1,280m2, total: 2,520m2); • Vehicle washing and cleaning building (1,120m2); • Major and minor repairs and maintenance bays/workshop/stores (ground floor: 2,250m2, first floor: 430m2, total: 2,680m2); • Gate, entrance, and security hut; • Vehicle inspection bays/hut (530m2); • Electrical substation compound (2,700m2); • Seven transformer buildings at 60m2 each; • Car parking (approximately 57 standard, three accessible bays, six for motorcycle, and six for EVs), catering to diverse transportation needed (1,700m2); • Bus parking bays (176 spaces); • Cycle parking (24m2); • Architecturally designed boundary fencing: 1.8m high fence along Ballycoolin Road and 4.5m high fencing around the remainder of the site's perimeter; • Two vehicle crossings on the eastern boundary for site access; • A separate vehicle crossing for direct ESB substation access; • Minor upgrades to the public road (eastern access road) including road grading, reshaping mounding refreshing line markings, new cycle ramps and removal of barriers; • Landscaping including native tree planning/shrubs and various amenity areas and SuDS features throughout the site; • Earthworks, construction activities and all ancillary site development works. Additional Information received 19/12/25 Clarification of Additional Information received 24/02/2026 / 0.2 km away / 23 March 2026Granted
- FW21A/0149Construction of 1) a new security hut at the site entrance, 2) a warehouse/light industrial unit of approx. 4,743 sq.m (Unit B), 3) a warehouse/light industrial unit of approx. 5,896 sq.m. (Unit C) and 4) a warehouse/logistics unit of approx. 6,736 sq.m (Unit D), along with all associated site works, car and bicycle parking and landscaping, all on a site are of 4.89 ha. Cappoge Castle, a recorded monument is located on the site. AI received 15/12/21 CAI received 24/3/2022 / 0.2 km away / 14 April 2022Granted
- FW15A/0078Permission for the change of use of Unit 31 (412 sq.m.) from dog train / 0.3 km away / 16 July 2015Granted
- FW23A/0399Proposed development that amends the warehouse development permitted under Fingal County Council Reg ref FW21A/0149 at this site. The proposed amendments are for design alterations to the Unit D warehouse and ancillary office building and to the associated site works within the Unit D curtilage to facilitate its use as a logistics enterprise/land terminal. The proposed amendments include: Reduction in height and volume of the warehouse building (c 4,195 sqm GFA), which also accommodates the ancillary office and driver welfare facilities (c. 725sqm GFA), inclusion of protective external canopies on northwest and southeast elevations, alteration of facade design and finishes and solar PV panels on the roof of the warehouse building; Associated signage on the northeast, southeast and northwest elevations. Also reconfiguration and alteration of associated site development works including: New HGV and vehicular site entrances along northern site boundary to Ballycoolin Road with separate access points for pedestrians, cars and HGVs; Relocation of the ancillary surface car park area (64 no. car parking spaces) to the east of the warehouse, 34 no. bicycle parking spaces (total), HGV parking bays, dock levellers, wash bay, trailer yard, fuel tank, fuel pump island, ESB substation; bin stores; landscaping and boundary treatment works, plant at roof level with associated screening. Site (c.2.42 ha) at Premier Business Park, Ballycoolin Road, Dublin 11. / 0.3 km away / 13 February 2024Granted