201450: To demolish a shed and construct a dwellinghouse, wastewater treatment plant, vehicular access and ancillary site works. Gross floor space of proposed works: 220 sqm. Gross floor space of any demolition: 60 sqm
Castletown,
DecisionRefused
Decided27 November 2020
Application typeOUTLINE PERMISSION
Source documents1
Site
What is on file
0refusal reasons0conditions8nearby records
Decision details
Core application dates and identifiers from the public planning record.Planning analysis
Refusal reasons and planning conditions extracted from the public decision file.Refusal reasons
Refusal reasons not machine-readable
Documents are indexed. Reason extraction for Galway has not started yet.
Conditions
No conditions
No conditions are on record for this application yet.
Planning a project near Castletown,?
Get the precedent report for this site: every grant and refusal within 5 km, and the planners' reasons. €29 incl. VAT, PDF by email.Source documents
Original council portal records and source PDFs where available.- Application fileApplication file on www.eplanning.ieSource portal
Nearby precedent
Similar nearby applications linked to this planning decision.- 19538For construction of a dwelling house, garage, treatment unit and all associated services. Gross floor space of proposed works: 279.1 sqm (House), 31.85 sqm (Garage) / 0.9 km away / 31 May 2019Refused
- 1990For the construction of a dwelling house, garage, treatment unit and all associated services. Gross floor space of proposed works: 279.1 sqm (House), 31.85 sqm (Garage) / 0.9 km away / 15 March 2019Refused
- 21537For the construction of a dwellinghouse, domestic garage, proprietary treatment system and percolation area and for all ancillary services and site works. Gross floor space of proposed works: House: 279.75 sqm, Garage: 60 sqm / 1.5 km away / 31 May 2021Refused
- 2560302Of a dwelling house with attached garage, septic tank and associated works on revised site boundaries / 1.5 km away / 15 May 2025Refused
- 191812For development of a Biogas Plant on a 10.01 hectare (ha) site located in the townlands of Ballynamantan, Kinincha and Glenbrack. The Biogas plant will utilise anaerobic digestion technology to produce renewable energy and organic fertiliser. The plant will consist of; (i) Two storey office building (509 sq. m floor area) with connection to public sewer; (ii) single store electrical substation building (14.43 sq. m. floor area) and associated bunded transformer; (iii) 13.4m high feedstock reception building (3,806 sq. m floor area) incorporating; airlock lobby, feedstock reception area, processing and mixing areas, pasteurisation vessels and ancillary heating technology, wash down area, feedstock quarantine area, storage areas, workshop area, hygiene facilities, digestate separation area and process wastewater tanks; (iv) bunded tank farm (14,805 sq. m) containing; 2 no. pump house buildings (216 sq. m) and delivery pipework serving feedstock reception building, 8 no. digester vessels (each of c.15m in height and c.5, 120m3 in capacity) and 4 no. storage vessels (each of c.15m in height and c.5,120m3) fitted with gas collection roofs/domes, stairwell towers and gantries, bunded digestate dispatch bays; (v) biogas purification plant on raised concrete apron (vi) Carbon dioxide processing building (10.44m in height, 138 sq. m floor area) containing treatment plant and 4 no. outdoor storage tanks and dispatch area; (vii) Odour control system comprising air scrubber units, carbon adsorption bed and associated stack of up to 23m in height; (viii) energy centre, containing combined heat and power (CHP) plant and 2 no. standby boilers with exhaust stacks (16.4m in height); (ix) Biogas ground flare stack (c. 8m in height) and gas booster station; (x) weighbridge with secure lift barrier and all ancillary development. The development includes for construction of a new entrance to the site from N18/458 with associated signage and an access road (area of 1.734ha) from the new entrance to the Biogas plant. Permission is being sought for 10 years and is a development that is for the purpose of an activity requiring an Industrial Emissions Licence from the EPA. An EIAR and NIS has been prepared and accompanies this planning application. Gross floor space of proposed works: 4163.5 sqm / 1.9 km away / 02 December 2020Refused
- 2561073For the construction of two storage warehouses accessed via an existing entrance within the site of an existing commercial development, development to include a) associated road access including HGV access, b) provision of 32 parking spaces and bike storage c) provision of hard and soft landscaping including site lighting and all other associated and ancillary development and works above and below ground level. A Natura Impact Statement (NIS) has been prepared in respect of the proposed development / 2.3 km away / 26 September 2025Refused
- 211817For development consisting of construction of dwelling house, wastewater treatment system, percolation area along with any other site ancillary works attached. A Natura Impact Assessment (NIS) has been provided with the application. Gross floor space of proposed works 249.60 sqm. / 2.3 km away / 24 November 2021Refused