GrantedDecided 18 December 2023Kerry County Council

TULLAMORE, LISTOWEL, CO KERRY

Planning application 23431
DecisionConditional grant
Decided18 December 2023
Application typePERMISSION
Source documents1

Site

What is on file

0refusal reasons0conditions8nearby records

Proposed development

Application description published by Kerry County Council.
CONSTRUCT A 38KV SUBSTATION, INCLUDING ALL CONTROL BUILDING, AND ALL ASSOCIATED ELECTRICAL PLANT AND APPARATUS, FENCING, TEMPORARY ACCESS TRACK, AND ALL ASSOCIATED AND ANCILLARY WORKS NECESSARY TO FACILITATE THE DEVELOPMENT. THE PROPOSED SUBSTATION WILL ADJOIN THE CONSENTED 110KV DROMBEG SUBSTATION APPROVED THROUGH THE STRATEGIC INFRASTRUCTURE DEVELOPMENT PROCESS UNDER AN BORD PLEANÁLA REF: VA08.305106. THE PROPOSED DEVELOPMENT WILL REDUCE THE QUANTUM OF PROPOSED SOLAR PANELS BY C.902SQM OR 0.25% OF THE PREVIOUSLY PERMITTED SOLAR FARM UNDER KERRY COUNTY COUNCIL PLANNING REF: 18720 (AN BORD PLEANÁLA REF: PL08.302681). A NATURA IMPACT STATEMENT HAS BEEN PREPARED IN RESPECT OF THE PROPOSED DEVELOPMENT AND ACCOMPANIES THIS APPLCIATION

Decision details

Core application dates and identifiers from the public planning record.

Planning analysis

Refusal reasons and planning conditions extracted from the public decision file.

Refusal reasons

No refusal reason on record

Documents are indexed. Reason extraction for Kerry has not started yet.

Conditions

No conditions

No conditions are on record for this application yet.

Planning a project near TULLAMORE, LISTOWEL, CO KERRY?

Get a site risk brief with the local decision pattern and up to 80 detailed nearby comparables (40 refusals and 40 grants), including extracted reasons and source links. €29 incl. VAT, PDF by email.

Source documents

Original council portal records and source PDFs where available.

Nearby precedent

Similar nearby applications linked to this planning decision.
Get up to 80 detailed nearby comparables in a site risk brief →