ESB Telecoms Ltd communication compound, ESB Griffinrath 110kV Substation Site, Townland of Oldtown
Planning application 171171
DecisionConditional grant
Decided30 April 2018
Application typePERMISSION
Source documents1
Site
What is on file
0refusal reasons0conditions8nearby records
Proposed development
Application description published by Kildare County Council.Application and appeal history
Structured appeal stages, outcomes and source documents currently tied to this application.No indexed appeal history
No structured appeal case is tied to this application. This means no appeal is indexed, not that an appeal is impossible.
Decision details
Core application dates and identifiers from the public planning record.Planning analysis
Refusal reasons and planning conditions extracted from the public decision file.Refusal reasons
No refusal reason on record
Documents are indexed. Reason extraction for Kildare has not started yet.
Conditions
No conditions
No conditions are on record for this application yet.
Planning a project near ESB Telecoms Ltd communication compound, ESB Griffinrath 110kV Substation Site, Townland of Oldtown?
Get a site risk brief with the local decision pattern and up to 80 detailed nearby comparables (40 refusals and 40 grants), including extracted reasons and source links. €29 incl. VAT, PDF by email.Source documents
Original council portal records and source PDFs where available.- Application fileApplication file on www.eplanning.ieSource portal
Nearby precedent
Similar nearby applications linked to this planning decision.- 2460371For the construction of 61 residential units, (comprising a mix of one-bedroom duplex/ apartment units, two-bedroom houses and three-bedroom houses), a crèche, and all associate ancillary site development works, including vehicular access, drainage, services, footpaths, cycle path, lighting, landscaping and amenity areas, bicycle and car parking. One existing entrance into the Oldtown Woods estate from Oldtown Road (as permitted under ABP -303295-18) is to be removed and a new entrance from Oldtown Road provided. Revised by Significant further Information which consists of: The amendment of the application boundary to include lands to the west of the site, which are to be reserved for the development of a school, with vehicle access from Oldtown Road. The proposed development also includes potential pedestrian connections to the future school site from within the proposed residential development. The Significant Further Information includes additional ancillary amendments to the previously submitted Site Layout Plan, which include the extension westwards of the proposed cyclepath/footpath along the Oldtown Road and the provision of a toucan crossing at Oldtown Road to connect to a future cyclepath / footpath on the eastern carriageway of Oldtown Road. / 0.5 km away / 01 July 2025Granted
- 171363EXTENSION OF DURATION of Planning Reference number 07/1363; previously extended under planning reference 13/498; fiche aitreabh ann (se arasan deag is ceithre arasan dha urlar) in dha cheap dha urlar le carrchlos faoi talamh is fo-oibreacha cui. Leagfar an teach inaitrithe ata ann mar chuid den fhorbairt molta / 0.5 km away / 01 February 2018Granted
- 2340For the construction of A three-storey building containing a 266m2 childcare facility and 4 No. three-bedroom apartments (change of plan from that granted under planning Reg. No. ABP-303295-18) / 0.6 km away / 14 March 2023Granted
- 221519The construction of a two-storey extension to the side with a new Velux roof window on the existing front roof slope and all associated site works / 0.6 km away / 16 February 2023Granted
- 18732The construction of a single storey extension to the side, internal alterations and associated site works and services / 0.6 km away / 13 August 2018Granted
- 2460177For a proposed sessional playschool, including outdoor play area, parking facilities, new access drive and use of existing vehicular entrance onto Oldtown Road, connection into public sewer and all associated site development works / 0.6 km away / 10 June 2024Granted
- 211256Application for a 10 year permission for development on lands in the townland of Griffinrath, Celbridge. The development will consist of the construction of a solar PV farm with an operational life of 35 years comprising approximately 75,984 No. photovoltaic panels on ground mounted frames within a site area of 44.21 hectares and associated ancillary development including 10 No. transformer stations, approximately 124 No. string-inverters, 1 No. onsite 38kV substation building, 1 No. 40ft storage container building, 7 No. CCTV security cameras mounted on 4 metre high poles and perimeter security fencing (2 metres high), the construction of an internal hardcore access road between the solar panels and the site access, localised improvements to an existing agricultural access from the adjoining L5065 road to facilitate construction and operational phase access and, the installation of a 38kV underground electricity cable from the onsite 38kV substation to the 110kV Griffinrath substation ca. 0.75km to the southeast. A Natura Impact Statement has been prepared in respect of the proposed development. Revised by Significant Further Information which consists of an Aviation Glint and Glare Assessment Report, an Archaeological Report; an amended Noise and Vibration Impact Assessment; a Traffic Report; drawings of cable locations and trench reinstatement and road closures and road diversion routes; a Stage 1/2 Road Safety Audit; updated drawings of the existing and proposed entrance and the proposed compound and temporary set down area; and a risk assessment of the hazards associated with a fire in or near the solar arrays. / 0.6 km away / 23 March 2022Granted
- 22974A) the construction of a two storey extension to the side of the existing dwelling to include a home office, WC and utility room on the ground floor, an extended bedroom area, laundry storage, bathroom and ensuite on the first floor and; b) extending the existing non-habitable attic room to include a new dormer window at the rear end and; c) a roof window to the front elevation to provide natural light into the landing below, all together with all associated site works / 0.6 km away / 22 September 2022Granted