Main Street, Kilcullen, Co. Kildare.
Planning application 211572
DecisionRefused
Decided21 December 2021
Application typePERMISSION
Source documents1
Site
What is on file
0refusal reasons0conditions8nearby records
Proposed development
Application description published by Kildare County Council.Decision details
Core application dates and identifiers from the public planning record.Planning analysis
Refusal reasons and planning conditions extracted from the public decision file.Refusal reasons
Refusal reasons not machine-readable
Documents are indexed. Reason extraction for Kildare has not started yet.
Conditions
No conditions
No conditions are on record for this application yet.
Planning a project near Main Street, Kilcullen, Co. Kildare.?
Get a site risk brief with the local decision pattern and up to 80 detailed nearby comparables (40 refusals and 40 grants), including extracted reasons and source links. €49 incl. VAT, PDF by email.Source documents
Original council portal records and source PDFs where available.- Application fileApplication file on www.eplanning.ieSource portal
Nearby precedent
Similar nearby applications linked to this planning decision.- 2561066For the unauthortised demolition of existing two storey house / 0.1 km away / 12 November 2025Refused
- 18260Extension of Duration Planning Ref:07/1201 &13/64 mixed use development scheme comprising retail, residential, commercial, cafe/restaurant, associated facilities and publicly accessible landscaped areas etc / 0.1 km away / 02 May 2018Refused
- 2561097For 1. Construction of a residential development comprising of 74 no. units in total, consisting of 16 no. three storey duplex units (8 no. two bed units and 8 no. three bed units), 16 no. four storey duplex units (8 no. three bed units and 8 no. three bed units), 29 no. three bed two storey houses and 13 no. four bed units in a mix of two and three storey houses; 2. Individual vehicular, pedestrian and cyclist access from a number of points from existing estate road at Riverside Crescent to the east of the application site. 3. Provision of public open spaces totalling 2,347 sq.m. 4. The inclusion of a total of 115 no. car parking spaces to serve the development, in addition to 126 no. bicycle spaces, and bin store areas located at various points around the development. 5. Infrastructure works to serve the proposed development to include the internal road and footpath network, ESB substations/switchrooms, lighting, site drainage works, hard and soft landscaping, boundary treatment, and all ancillary site services and development works above and below ground / 0.1 km away / 17 November 2025Refused
- 171123 No. terraced townhouse type dwellings in a single three storey block consisting of (a) 2 No. four bedroom three storey townhouses; (b) 1 No. two bedroom three storey townhouse; (c) New entrance, car parking, earth retaining boundary structures, bin storage area along with all associated site development and facilitating works / 0.2 km away / 31 March 2017Refused
- 1714543 no. terraced townhouse type dwellings in a single two storey block consisting of (a) 2 no. three bedroom, two storey townhouses, (b) 1 no. two bedroom, two storey townhouse, (c) new upgraded entrance, (d) earth retaining boundary structure to eastern boundary, (e) car parking and bin storage area along with all associated site development and facilitating works / 0.3 km away / 22 February 2018Refused
- 201561To erect an 18m high monopole telecommunications support structure together with antennas, dishes and associated equipment at the eir Exchange / 0.3 km away / 02 September 2021Refused
- 2560657For the proposed erection of 2 no. 3-bedroom dwelling houses, to include provision of a raised table pedestrian crossing, boundary walls, soft & hard landscaping, connection to privately owned infrastructure including mains water, wastewater, and stormwater systems, along with all associated and ancillary site works and services to facilitate the development / 0.4 km away / 31 July 2025Refused