Application description published by Meath County Council.
The application is for a 10 year permission. The development will consist of: a solar farm with an export capacity of approximately 3MW comprising photovoltaic panels on ground mounted frames, a single-storey ESB MV Sub-Station / switch room building, installation of 3 No. transformers, ducting & underground electrical cabling, perimeter fencing, pole mounted CCTV cameras, upgrading of existing vehicle entrance, provision of internal access track and all associated ancillary works and services
Application and appeal history
Structured appeal stages, outcomes and source documents currently tied to this application.
ABP-302368-18Submitted 17 August 2018 / decided 14 March 2019
No appeal document has been bound to this case yet; the timeline will enrich as indexing continues.
Decision details
Core application dates and identifiers from the public planning record.
Application ref
LB180570
Received
01 June 2018
Decided
24 July 2018
FI requested
No
Authority
Meath County Council
Application type
PERMISSION
Outcome
Refused
Source status
Documents indexed. Reason extraction for Meath has not started yet.
Planning analysis
Refusal reasons and planning conditions extracted from the public decision file.
Refusal reasons
Refusal reasons not machine-readable
Documents are indexed. Reason extraction for Meath has not started yet.
Conditions
No conditions
No conditions are on record for this application yet.