Application description published by Offaly County Council.
CONSTRUCTION OF ONE 4.2MW WIND TURBINE WITH AN OVERALL TIP HEIGHT OF UP TO 150M; CONSTRUCTION OF THE WIND TURBINE FOUNDATION, HARDSTANDING AND ASSEMBLY AREA; PROVISION OF A SITE ENTRANCE AND AN ACCESS TRACK WITHIN THE SITE; CONSTRUCTION OF AN ON-SITE 20KV SUBSTATION AND UNDERGROUND ELECTRICAL CABLE; AND, ALL ASSOCIATED SITE DEVELOPMENT AND ANCILLARY WORKS
Application and appeal history
Structured appeal stages, outcomes and source documents currently tied to this application.
Appeal linked to 21306Submitted 05 August 2021 / decided 09 May 2022
No appeal document has been bound to this case yet; the timeline will enrich as indexing continues.
Decision details
Core application dates and identifiers from the public planning record.
Application ref
21306
Received
17 May 2021
Decided
09 July 2021
FI requested
No
Authority
Offaly County Council
Application type
PERMISSION
Outcome
Refused
Source status
Documents indexed. Reason extraction for Offaly has not started yet.
Planning analysis
Refusal reasons and planning conditions extracted from the public decision file.
Refusal reasons
Refusal reasons not machine-readable
Documents are indexed. Reason extraction for Offaly has not started yet.
Conditions
No conditions
No conditions are on record for this application yet.