SD20A/0017: Renovation and modifications to the original building including a change of use to office, training and distribution centre; proposed changes to the existing internal layout; internal fire stair location moved; extended mezzanine area, additional new toilets; external windows and modifications to the roller door on the rear elevation; new signage to the front elevation and all ancillary works.
Unit 2, The Square Industrial Complex, Belgard Square East, Tallaght, Dublin 24
DecisionGrant permission
Decided26 March 2020
Application typePermission
Source documents1
Site
What is on file
0refusal reasons0conditions8nearby records
Decision details
Core application dates and identifiers from the public planning record.Planning analysis
Refusal reasons and planning conditions extracted from the public decision file.Refusal reasons
No refusal reason on record
Documents are indexed. Reason extraction for South Dublin has not started yet.
Conditions
No conditions
No conditions are on record for this application yet.
Source documents
Original council portal records and source PDFs where available.Nearby precedent
Similar nearby applications linked to this planning decision.- SD21A/0134Amendments to previously granted permission (SD20A/0017) comprising of alterations to façade; installation of roof lights and PV panels. / 0.0 km away / 19 July 2021Granted
- SD16A/0052Change of use from existing warehouse with associated offices to recreational facility. Works will include reorganisation of internal office spaces, installation of coffee space, climbing wall facilities and the installation of 2 internally illuminated box signs to front elevation. / 0.0 km away / 13 April 2016Granted
- SD04A/0076Retention for internal alterations to existing premises comprising ancillary accommodation including offices and canteen at ground floor level and offices and boardroom at first floor level. / 0.0 km away / 26 March 2004Granted
- SD15A/0049Removal of existing corporate signage on the south and east elevations and the erection of new illuminated corporate signage on the south elevation, east elevation and eastern boundary wall; new visitor information signage also to be erected on the south and east elevations. / 0.1 km away / 28 April 2015Granted
- SD20A/0083Works to the existing roof including installation of 173sq.m of solar pv panels; the erection of a new guardrail on the existing parapet to the perimeter of the roof; alteration to a portion of the existing roof from a pitched roof to a flat roof, installation of roof access hatches and all associated site development works. / 0.1 km away / 13 July 2020Granted
- SD24A/0278WThe development consists the installation of 2no. new water tanks and an associated enclosure to the north of the existing office building, the relocation of a previously granted bicycle shelter under planning reference SD21A/0123, from the east of the site to the south-west, and all associated site works at PM Group, Kearney House, Belgard Square, Dublin, D24 XFW2. / 0.1 km away / 08 April 2025Granted
- SD03A/0179Change of use from retail use to estate agent, provision of new mezzanine structure to existing ground floor double height space, internal office fit-out to existing basement and ground floor levels and to proposed mezzanine level, provision of internally illuminated external signage (Overall 'Tuansgate' development previously granted planning permission under Reg. Ref. S01A/0435). / 0.1 km away / 22 May 2003Granted
- SD21A/0123Sliding steel entrance gate to the main entrance; partial demolition of a section of existing boundary wall; construction of new site entrance piers and the extension of the existing perimeter railings to meet the new piers; 2 new bicycle shelters and all associated site development works. / 0.1 km away / 17 January 2022Granted