SD22A/0349: Modifications to the existing main site entrance to comprise of minor realignment of the internal access road with adjusted road marking and roadside bollards; Removal of 3 existing security traffic arms; Installation of 3 new security traffic arms and installation of 3 underground lifting security road blockers together with associated communications and electrical services; Provision of 2 set-down only parking spaces and all associated site drainage and installation works.
Dublin Google Data Centre, Grange Castle Business Park South, 22, Baldonnel Road, Dublin 22
DecisionGrant permission
Decided28 October 2022
Application typePermission
Source documents1
Site
What is on file
0refusal reasons0conditions8nearby records
Decision details
Core application dates and identifiers from the public planning record.Planning analysis
Refusal reasons and planning conditions extracted from the public decision file.Refusal reasons
No refusal reason on record
Documents are indexed. Reason extraction for South Dublin has not started yet.
Conditions
No conditions
No conditions are on record for this application yet.
Source documents
Original council portal records and source PDFs where available.Nearby precedent
Similar nearby applications linked to this planning decision.- SD14A/0284Alterations to previously granted Reg. Ref. SD14A/0023 consisting of alterations to the position of the security gatehouse and security gates, internal roads layout, attenuation ponds, access road to the two storey substation; alterations to the double height warehouse elevations plus an additional internal mezzanine level (floor area 165sq.m); alterations to the single storey substation building (increase in additional floor area of 88sq.m and compound area; alterations to the height of the Load Bank Garage Building; additional 27 car parking spaces; removal of previously granted MV substation to north west of site; all associated site development works required as part of the above mentioned alterations. / 0.2 km away / 23 February 2015Granted
- SD14A/0023Construction of a two storey data storage facility (30,361sq.m.), a double height warehouse building (1,670 sq.m) and a HV Substation area with two buildings; 1 no. 2 storey building (968sq.m.) and 1 no. single storey building (190 sq.m) and associated site development works. Permission is also sought for a new site access and entrance gates, a security gatehouse, security gates, load bank garage, perimeter fencing, internal roadways, sprinkler tank, pump house, 10KV substation, water and fuel tanks, attenuation ponds, hard and soft landscaping, 83 no. new car parking spaces and bicycle shelter with ancillary site works. The highest point of any of the buildings is within 20m of the original ground level with the 25 no. stacks at 25m. Provision for a temporary construction entrance and haul road off the Baldonnel Road to the south of the site has been allowed for; an EIS (Environmental Impact Statement) will be submitted with this application, all on a 11.25 ha site. / 0.2 km away / 14 April 2014Granted
- SD09A/0267Retention of the existing 15-meter high telecommunications support structure carrying antennas & link dishes together with associated equipment container & security fence with access over existing access track. / 0.2 km away / 01 June 2010Granted
- SD04A/0489To retain the existing permitted GSM base station installation (See Reg. Ref. S98A/0585) comprising: 15m high triangular lattice mast carrying 6.No.GSM antennas and 2. No. 0.6m diameter link dish/drum antenna, together with associated telecommunications equipment container, security fencing and access track. / 0.2 km away / 30 November 2004Granted
- SD07A/0280Further Information - The proposed development now consists of: 43 Units in 7 blocks comprising 16 Industrial Units (Blocks 1, 2 and 7), 24 Warehouse Units (Blocks 4, 5 and 6) and 3 Science and Technology Units (Block 3) all with ancillary office space (total floor area approximately 12,558 sq. m.). Site development works including storm water attenuated works, water services, boundary fencing, temporary access haul road, estate roads and 2 no. E.S.B. sub-stations, 241 car parking spaces, all on a site of approx 3.314 hectares. (An increase in the overall floor area of the proposed development from 11,416 sq. m. to 12, 558 sq. m., increase in parking spaces from 168 to 241, a reduction in the number of units from 45 to 43, alterations to overall area and internal configuration of unit types A, B, C, D and D1, and reduction in floor area of ancillary office space, removal of 2 units onto internal access road (Block 4), relocation of unit from Block 5 to Block 3, relocation of waste collection area, cycle parking and 2 electricity sub-stations/switch rooms, and alterations to elevation onto internal access road, and alterations to internal access road layout). / 0.2 km away / 14 September 2007Granted
- SD11A/0121Change of use of an existing logistics/distribution warehouse facility (approved under planning ref. no. SD08A/0052) to an electronic technology facility, associated works including modifications to existing structure. The development will consist of the following works and modifications to the existing building: installation of external plant over two storeys along the east and west elevations of the building on a new steel support system clad with acoustic louvered screens to match existing cladding colours; installation of a new first floor to provide additional plant areas; extension to the administration area at ground floor level with new windows to the south elevation to match existing; installation of additional windows at upper level over the existing administration area and existing roof lights removed; removal of existing doors to north facade and replacement with new cladding to colour match existing; associated internal alterations. Extent of site works includes: a sprinkler tank and pump house to the north east corner; extension of existing single storey substation in the south east corner to include a customer switch room; provision of a new main entrance to the east of the existing entrance to Unit 502, a new road layout, entrance gates and new entrance gates south of the building to access the car park; block existing main entrance to Unit 502 to provide set down area to access the ESB substation; construct a single storey security building to the east of the site with new gates and new visitor car parking; remove one existing dock leveller and an on-grade roller shutter door from the north west corner of the building with the existing depressed loading dock filled in; installation of self contained emergency stand by generators and other plant to the north west corner of the site, including all supporting structures for flues, and a 1.8m high fence and gate to generator enclosure; construct roadway around the building to the west, north and east of the site; boundary fencing around site with site landscaping; existing site entrance to Unit 503 to be retained as an alternative access point; divert existing culvert along eastern side of the site to facilitate development; install a bicycle shelter to the south west of the site; increase in site area from 9131sq.m. to 13925sq.m. / 0.2 km away / 30 June 2011Granted
- SD16A/0148The painting of 5 murals max. 12.25m high totalling (1,192sq.m) on external walls of existing building, smaller images on 3 external flues (total 10sq.m) also mural painting on a 7.5m high external sprinkler tank (surface area 250sq.m). The installation of an external fence1.8m high x 18m long inside the existing perimter fence at external dining area with mural painted on the internal face (area 33sq.m) Total area of all murals is 1485sq.m. The murals will be lit with light fittings either on the building or nearby poles or ground. / 0.2 km away / 22 June 2016Granted
- SD10A/0063New 8m diameter sprinkler tank (8.5m in height) and pump house (floor area 30sq.m) to the rear of existing semi detached warehouse unit and associated site works on prviously approved development Reg. Ref. SD08A/0052 on a 0.45 Ha site. / 0.2 km away / 19 May 2010Granted