Application description published by Tipperary County Council.
Construction and operation of solar PV arrays mounted on metal frames on a 38.3 ha site, inclusive of an electrical substation compound, up to 10 no indicative inverter units, a temporary construction area and ancillary facilities (inclusive of gross floor space of proposed works up to 248 sq m). The planning application is accompanied by an environmental report and Natura Impact Statement.
Application and appeal history
Structured appeal stages, outcomes and source documents currently tied to this application.
ABP-306933-20Submitted 18 March 2020 / decided 14 April 2021
Status not recordedCONDITIONAL
Appeal submittedAppeal reference ABP-306933-20
18 March 2020
Appeal decisionCONDITIONAL
14 April 2021
No appeal document has been bound to this case yet; the timeline will enrich as indexing continues.
Decision details
Core application dates and identifiers from the public planning record.
Application ref
19601012
Received
12 September 2019
Decided
20 February 2020
FI requested
Yes
Authority
Tipperary County Council
Application type
PERMISSION
Outcome
Conditional grant
Source status
Documents indexed. Reason extraction for Tipperary has not started yet.
Planning analysis
Refusal reasons and planning conditions extracted from the public decision file.
Refusal reasons
No refusal reason on record
Documents are indexed. Reason extraction for Tipperary has not started yet.
Conditions
No conditions
No conditions are on record for this application yet.
Planning a project near Rahelty and Shanballyduff, Thurles?
Get a site risk brief with the local decision pattern and up to 80 detailed nearby comparables (40 refusals and 40 grants), including extracted reasons and source links. €39 incl. VAT, PDF by email.
Searching the records is free. A one-off brief for this site is €39, and Pro at €19/month adds full document access and the planning AI for people tracking more than one site.
Source documents
Original council portal records and source PDFs where available.
Included in site brief
1 council document — in the €39 site risk brief
Refusal reasoning quoted verbatim from the council decision file
Policy citations and the planner's own wording