Circle K Cashel Motorway Services Area, Junction 8 on the M8 Motorway Waller's-Lot, Cashel Co. Tipperary
Planning application 2460099
DecisionConditional grant
Decided09 April 2024
Application typePERMISSION
Source documents1
Site
What is on file
0refusal reasons0conditions8nearby records
Proposed development
Application description published by Tipperary County Council.Decision details
Core application dates and identifiers from the public planning record.Planning analysis
Refusal reasons and planning conditions extracted from the public decision file.Refusal reasons
No refusal reason on record
Documents are indexed. Reason extraction for Tipperary has not started yet.
Conditions
No conditions
No conditions are on record for this application yet.
Planning a project near Circle K Cashel Motorway Services Area, Junction 8 on the M8 Motorway Waller's-Lot, Cashel Co. Tipperary?
Get a site risk brief with the local decision pattern and up to 80 detailed nearby comparables (40 refusals and 40 grants), including extracted reasons and source links. €29 incl. VAT, PDF by email.Source documents
Original council portal records and source PDFs where available.- Application fileApplication file on www.eplanning.ieSource portal
Nearby precedent
Similar nearby applications linked to this planning decision.- 2360316A change of use from permitted retail use to retail use including the sale of alcohol for consumption off the premises (i.e., off licence use) within the overall permitted retail unit, where the floor area for the off licence use is 12.5sqm and is ancillary to the primary retail use / 0.0 km away / 30 June 2023Granted
- 18600320The construction of a compressed natural gas refuelling facility as part of the Motorway Services Area and 13 no new car parking spaces and Permission for Retention of modifications to the parking layout permitted under application register reference 15600414, including a reduction in parking and consequent revisions to the site levels, drainage, road markings and public lighting, and 2 no temporary storage structures at the Topaz Motorway Services Area, Junction 8 on the M8 Motorway / 0.0 km away / 20 August 2018Granted
- 19600597Development consisting of the (I) demolition of existing substation, and (ii) construction of a new substation (iii) all associated site and development works / 0.1 km away / 19 July 2019Granted
- 18601043A High Power Electric Vehicle Charging Station consisting of the: (i) Installation of 6 no. electric vehicle charging bays, each comprising a parking space and electric vehicle charging unit, (ii) Associated revisions to existing car parking area, (iii) Installation of electric vehicle power units, (iv) Construction of a new substation, (v) Erection of illuminated signage, (vi) All associated lighting, infrastructure, site and development works / 0.1 km away / 15 October 2018Granted
- 20790Development will consist of the replacement of an existing 24 metre lattice tower and existing 21 metre wooden pole for a 30 metre high free standing lattice communications structure carrying antennae and communication dishes, with associated equipment to form part of ESB's communication system and to share with other licensed operators within an existing compound / 0.1 km away / 10 September 2020Granted
- 2660207The construction/extension of the existing boundary wall to the site / 0.3 km away / 28 April 2026Granted
- 2660030Installation of 6 no. 21m galvanised steel poles with 500 lux floodlights for the purpose of illuminating the pitch and all associated site works / 0.3 km away / 12 March 2026Granted
- 22426The revisions to the site layout granted previously under planning register no. 20/1097 to accommodate revised wayleave and including the relocation of house numbers 10, 11, 12, 12, 14, & 15 to accommodate the revised wayleave and the change of house type for house numbers 14 & 15 from detached (Type A) to a pair of semi-detached (Type B). Permission for completion of all revisions / 0.6 km away / 16 August 2022Granted