Application description published by Waterford City and County Council.
For development consisting of a 10 year permission for the construction of a Solar PV Energy development within a total site are of up to 62.8hA, to include one single-storey electrical substation building and associated compound electrical transformer/inverter station modules, solar PV panels ground mounted on steel support structures,access roads, fencing and associated electrical cabling, ducting and ancillary infrastructure
Application and appeal history
Structured appeal stages, outcomes and source documents currently tied to this application.
ABP-300004-17Submitted 23 October 2017 / decided 19 February 2019
No appeal document has been bound to this case yet; the timeline will enrich as indexing continues.
Decision details
Core application dates and identifiers from the public planning record.
Application ref
17564
Received
04 August 2017
Decided
26 September 2017
FI requested
No
Authority
Waterford City and County Council
Application type
PERMISSION
Outcome
Refused
Source status
Documents indexed. Reason extraction for Waterford has not started yet.
Planning analysis
Refusal reasons and planning conditions extracted from the public decision file.
Refusal reasons
Refusal reasons not machine-readable
Documents are indexed. Reason extraction for Waterford has not started yet.
Conditions
No conditions
No conditions are on record for this application yet.