25210: Dwelling, waste water treatment system to EPA standards, garage, entrance and associated works
Balymoyle, Arklow, Co. Wicklow
DecisionRefused
Decided16 September 2025
Application typePERMISSION
Source documents4
Site
What is on file
0refusal reasons0conditions8nearby records
Decision details
Core application dates and identifiers from the public planning record.Planning analysis
Refusal reasons and planning conditions extracted from the public decision file.Refusal reasons
Refusal reasons not machine-readable
Documents are indexed. Reason extraction for Wicklow has not started yet.
Conditions
No conditions
No conditions are on record for this application yet.
Source documents
Original council portal records and source PDFs where available.- Application fileApplication file on www.eplanning.ieSource portal
- Notification Of DecisionSource: wicklowcoco.eplanning.ie / Be636201-7813-4c75-ab44-0f85f59fc8af.pdf / Document 652613Source PDF
- Chief Executives OrderSource: wicklowcoco.eplanning.ie / Efc00dfe-ba4c-4b51-9833-ce671f2d6c4c.pdf / Document 652612Source PDF
- Planners ReportSource: wicklowcoco.eplanning.ie / 5b543627-73fb-4632-8727-b55cd34bdfb6.pdf / Document 652620Source PDF
Nearby precedent
Similar nearby applications linked to this planning decision.- 2460422The reclamation of land through the filling of material comprising of clay, silt, sand, gravel or stone on a site having an area of circa 3.5282 hectares for the purpose of improvement of land for agricultural use. Access will be taken from the existing L6674 local road via a previously approved vehicular entrance and infill site. The previously approved site infrastructure including a vehicular entrance, haul road, portable truck wheel-wash, office/ chemical toilet granted planning permission under Ref. 19/98 will be retained for a further period to serve the proposed infill development. The application is accompanied by a Natura Impact Statement (NIS). The proposed development relates to an activity which requires a Waste Licence / 0.7 km away / 10 September 2024Refused
- 21144110 portable camping areas, 2 portable toilet blocks, 1 portable kitchen block, upgrading existing entrance, temporary parking area, new well and associate works / 1.4 km away / 01 February 2022Refused
- 2511Erection of a single storey dwelling house, on-site waste water treatment system, vehicular entrance and all associated site works / 1.6 km away / 03 March 2025Refused
- 171473Single storey extension to side of existing dwelling together with the upgrade of existing effluent disposal system to current EPA guidelines and all ancillary site works / 2.2 km away / 08 February 2018Refused
- 23610To construct 2No. 340m² industrial storage sheds and all associated site works / 2.4 km away / 29 August 2023Refused
- 2560361Period of 10 years for a proposed solar farm and BESS (battery energy storage system) development which will consist of the construction of PV panels mounted on metal frames, inverters, battery storage infrastructure (BESS units, and MV Stations), new access tracks, underground cabling, perimeter fencing with CCTV cameras and access gates, a temporary construction compound, a substation and all ancillary grid infrastructure and associated works. It is proposed to use the consented Ballymoney Solar Farm access point (Pl Ref: 19/627 and ABP Ref: 305289-19). The solar farm and BESS would be operational for 40 years. A Natura Impact Statement (NIS) will be submitted with this application / 2.6 km away / 08 July 2025Refused
- 211539Proposed extension to dwelling / 2.8 km away / 18 February 2022Refused
- 23722Work completed to date and completion of same for outbuilding / 2.8 km away / 13 November 2023Refused