Applications tied to the site
Partial coverage11 register records are within the point-match tolerance; a parcel boundary is needed to treat this as exact.
11 matchedSite planning risk brief
One-off house / within 5 km where a location match is available
Executive snapshot
8% of nearby decided applications were refused. The site check found 883 decisions within 5 km, 11 exact-site or onsite candidate records, and 0 structured appeals.
Evidence maturity
Each section reports its own coverage. “Not yet covered” means no conclusion is drawn while source datasets or policy extraction are still being loaded.
11 register records are within the point-match tolerance; a parcel boundary is needed to treat this as exact.
11 matchedCurrent indexed zoning and settlement layers are intersected with the selected site where coverage exists.
Current section-and-page citations have not yet been loaded for this authority.
Each layer reports its own coverage; missing coverage never appears as a clean result.
0 prompts are backed by extracted nearby decision evidence; all prompts remain checks, not predictions.
No structured appeal row is currently tied to the matched decision set.
Historic extracted references are not presented as current policy; verified citations are still being loaded.
Open preview
Open preview
Construction of a distribution centre with ancillary offices, vehicular entrance and car parking, ESB substation, storm water attenuation system together with all other ancillary site works (Permission previously granted under Planning Ref. No. 07/5768) - Extension of Duration to Permission granted under Planning Ref. No. 17/4638
Permission for retention of development at the existing distribution centre (including ancillary internal offices) which consists of the retention of (1) increased internal office floor area (2) alterations to elevations of building to include windows at ground and first floor of south elevation to facilitate increased ancillary internal offices and an additional roller door, single door, and window on the east elevation (3) 32 no. car parking spaces.
Permission for retention of the constructed ESB sub-station in its current location in lieu of the location granted in Planning Register No. 17/4638.
Permission to construct an ESB substation building (21.8 sqm) and carry out all associated site works
The proposed development will consist of the construction of a transport depot comprising; 1)an administration and warehouse building incorporating a 2-storey administration block (495 sqm) and mezzanine store (163 sqm), truck maintenance garage (505 sqm). warehouse (511 sqm), dock leveller and rooftop photovoltaic solar panel arrays (150 sqm). 2)A service block building incorporating a boiler house (305 sqm), tank washing bays enclosure (605 sqm) truck wash enclosure (183 sqm), covered outdoor tank heating station, 2 storey administration block (148 sqm) and roof top photovoltaic solar panel arrays (75 sqm). 3)Proposed site and drainage works including a service yard, 2 no. vehicular accesses, new boundary treatments, landscape works, storage, circulation, staff parking areas with sixteen spaces including one disabled space, underground attenuation tank, underground fuel tank, 1 no. silt trap, 1 no. wash down separator, 1 no. forecourt separator, 2 no. compartment separators, 1 no. full retention separator, 1 no. 5 m high aeration tank. 1 no. 5m high balancing tank, weigh bridge, rainwater harvesting, underground pumping chamber and all other associated site development works
Permission for the development which will consist of a new two-storey office building, a maintenance warehouse, a crane wash ramp, a maintenance ramp, a single storey storage shed, car and crane parking, a concrete hardstanding and all associated site development, drainage and landscaping works.
The brief summarizes the pattern across all 883 matched decisions within 5 km and includes up to 80 detailed comparables (40 nearest refusals and 40 nearest grants), with extracted reasons, quotes, and available source links. €29 incl. VAT.
Source match
Matched from public planning record 22/6211The site brief adds up to 80 nearest detailed grants and refusals, extracted source evidence, document links, and a shareable risk summary.
Included in site brief
Included in site brief
Included in site brief
Included in site brief