8% of nearby decided applications were refused. The site check found 246 decisions within 5 km, 4 exact-site or onsite candidate records, and 0 structured appeals.
Evidence maturity
Each section reports its own coverage. “Not yet covered” means no conclusion is drawn while source datasets or policy extraction are still being loaded.
4 register records are within the point-match tolerance; a parcel boundary is needed to treat this as exact.
4 matchedCurrent indexed zoning and settlement layers are intersected with the selected site where coverage exists.
Current section-and-page citations have not yet been loaded for this authority.
Each layer reports its own coverage; missing coverage never appears as a clean result.
0 prompts are backed by extracted nearby decision evidence; all prompts remain checks, not predictions.
No structured appeal row is currently tied to the matched decision set.
Historic extracted references are not presented as current policy; verified citations are still being loaded.
Open preview
Open preview
Construction of a dwellinghouse, detached domestic garage, a new site entrance and all associated site works
Permission for the decommissioning of existing septic tank system, the installation of a new replacement wastewater system with percolation area and all ancillary site works.
Retain the existing domestic shed, the existing domestic garage and the existing domestic store, and to retain the amended site boundaries previously granted under planning register no. N/2336/87 and all associated site works.
Permission to construct a garage/storage shed and all other associated site works.
To construct a domestic garage adjacent to their home. The above to be carried out with all associated ancillary site works.
Site development works in three phases, for fifteen houses. Works include road and footpath construction entrance walls and piers, site boundries, service ducts, foul and surface water connections, electrical services and green area preparation with car parking. Extension of duration of permission granted under planning reference: 15/5325.
The brief summarizes the pattern across all 246 matched decisions within 5 km and includes up to 80 detailed comparables (40 nearest refusals and 40 nearest grants), with extracted reasons, quotes, and available source links. €29 incl. VAT.
Source match
Matched from public planning record 17/7058The site brief adds up to 80 nearest detailed grants and refusals, extracted source evidence, document links, and a shareable risk summary.