Applications tied to the site
Partial coverage3 register records are within the point-match tolerance; a parcel boundary is needed to treat this as exact.
3 matchedSite planning risk brief
One-off house / within 5 km where a location match is available
Executive snapshot
10% of nearby decided applications were refused. The site check found 478 decisions within 5 km, 3 exact-site or onsite candidate records, and 0 structured appeals.
Evidence maturity
Each section reports its own coverage. “Not yet covered” means no conclusion is drawn while source datasets or policy extraction are still being loaded.
3 register records are within the point-match tolerance; a parcel boundary is needed to treat this as exact.
3 matchedCurrent indexed zoning and settlement layers are intersected with the selected site where coverage exists.
Current section-and-page citations have not yet been loaded for this authority.
Each layer reports its own coverage; missing coverage never appears as a clean result.
0 prompts are backed by extracted nearby decision evidence; all prompts remain checks, not predictions.
No structured appeal row is currently tied to the matched decision set.
Historic extracted references are not presented as current policy; verified citations are still being loaded.
Open preview
Open preview
The importation of soil & stone for the raising of an agricultural field in order to improve the agricultural output of the field and the construction of a temporary new haul road. A Natura Impact Statement (NIS) has been prepared and will be submitted to the authority with this application.
Permission the importation of soil & stone for the raising of an agricultural field in order to improve the agricultural output of the field and the construction of a temporary haul road. An Environmental Impact Assessment Report (EIAR) has been prepared and is submitted with the application. A Natura Impact Statement (NIS) has been prepared and is submitted with the application
Site development works for mobilehome park consisting of serviced sites for 26 mobile homes, 1 No. reception building, 26 sites for freestanding prefabricated composite decking for access to mobile homes and ancillary use. 2 sites for bin enclosures, roads, services, connections to existing water main and existing electrical system, existing surface water stream and to existing waste water treatment plant, landscaping, and related works, all works within the existing boundaries of Trabolgan Holiday Centre.
Permission for the importation of clean inert soil & stone for the restoration of a former quarry in order to improve the agricultural output and the construction of a new temporary haul road. There will be a temporary wheelwash on site for the duration of the project and the entrance gate will be widened.
The development will consist of a new 24 metres lattice telecommunications support structure with headframe, carrying antennas, dishes, associated equipment, ground-based equipment cabinets, fencing and all associated site development works for high-speed wireless data and broadband services
Construction of a machinery/straw storage shed and associated site works.
The brief summarizes the pattern across all 478 matched decisions within 5 km and includes up to 80 detailed comparables (40 nearest refusals and 40 nearest grants), with extracted reasons, quotes, and available source links. €29 incl. VAT.
Source match
Matched from public planning record 19/6189The site brief adds up to 80 nearest detailed grants and refusals, extracted source evidence, document links, and a shareable risk summary.
Included in site brief
Included in site brief
Included in site brief
Included in site brief