Applications tied to the site
Partial coverage1 register record is within the point-match tolerance; a parcel boundary is needed to treat this as exact.
1 matchedSite planning risk brief
One-off house / within 5 km where a location match is available
Executive snapshot
8% of nearby decided applications were refused. The site check found 1,212 decisions within 5 km, 1 exact-site or onsite candidate record, and 65 structured appeals.
Evidence maturity
Each section reports its own coverage. “Not yet covered” means no conclusion is drawn while source datasets or policy extraction are still being loaded.
1 register record is within the point-match tolerance; a parcel boundary is needed to treat this as exact.
1 matchedCurrent indexed zoning and settlement layers are intersected with the selected site where coverage exists.
Current section-and-page citations have not yet been loaded for this authority.
Each layer reports its own coverage; missing coverage never appears as a clean result.
0 prompts are backed by extracted nearby decision evidence; all prompts remain checks, not predictions.
65 structured nearby appeal records.
65 matchedHistoric extracted references are not presented as current policy; verified citations are still being loaded.
Open preview
Open preview
CONSTRUCTION OF A NEW ADVANCED BUILDING SOLUTION CONSISTING OF OFFICE AND LIGHT INDUSTRIAL/PRODUCTION SPACES AND VEHICULAR/PEDESTRIAN ENTRANCE, SIGNAGE, CAR PARKING, CYCLE SHELTERS, LANDSCAPING, GAS SKID, UNDERGOUND WATER STORAGE TANK, INDEPENDENT ESB SUBSTATION AND SWITCH ROOM BUILDING, ACCESS ROAD AND ALL ASSOCIATED SITE WORKS. A NATURA IMPACT STATEMENT (NIS) ACCOMPANIES THIS APPLICATION
(A) DEVELOPMENT OF NEW OFFICE FACILITY COMPRISING 1 NO. OFFICE BUILDING CONTAINING 4 NO. THREE STOREY LINKED OFFICE BLOCKS, CENTRAL ENTRANCE/RECEPTION WITH CENTRAL DINING ROOM, COMMERCIAL KITCHEN AND EXTERNAL REFUSE STORAGE AREA. (B) SECURITY GATE HOUSE, BARRIERS AND SECURITY GATES TO EXISTING SITE ACCESS ROAD, EXTEND EXISTING ROAD FROM SITE ENTRANCE INTO NEW CAR PARKING TO FRONT AND REAR OF BUILDING WITH EXTERNAL CIRCULATION AROUND THE BUILDING ACCESSING THE CAR PARKING INCLUDING RAMP TO REAR SERVICE AREA. (C) FORMATION OF NEW VEHICULAR ENTRANCE FOR EMERGENCY VEHICLES WITH SECURITY GATES FROM EXISTING IDA LINK ROAD. (D) 2 NO. SERVICE BUILDINGS EACH CONTAINING A GENERATOR, UPS AND BOILER HOUSE. (E) PROVISION OF PUMP HOUSE AT THE ATTENUATION LAKE. (F) 2 NO. LPG TANKS AND COMPOUND FENCING. (G) CONNECTION TO EXISTING FOUL SEWERAGE SYSTEM AND STORM WATER DRAINAGE SYSTEM VIA AN ATTENUATION LAKE LOCATED TO THE SOUTH OF THE PROPOSED BUILDING WITH FINAL DISCHARGE INTO EXISTING STORM DRAINAGE SYSTEM. (H) VARIOUS FREE STANDING SITE SIGNAGE & FIXED BUILDING SIGNAGE. (I) PROVISION OF 150 NO. BICYCLE RACKS, HARD STANDING, PAVING, LANDSCAPING AND ALL ASSOCIATED SITE WORKS INCLUDING 2 NO. PEDESTRIAN ACCESS STAIRS TO THE REAR ENTRANCE POINTS OF THE BUILDING. (J) GABION WALLS AND OTHER RETAINING STRUCTURES AT CHANGES IN LEVEL WITHIN SITE AND AT SITE BOUNDARIES. (K) PROVISION OF PV / SOLAR PANELS ON THE BUILDING ROOFS. (L) ALTERATIONS TO 2 NO. EXISTING IDA LINK ROAD JUNCTIONS WITH THE N56 INCLUDING ROAD MARKINGS, SIGNAGE ETC. (M) ADDITIONAL STREET LIGHTING TO THE EXISTING IDA LINK ROAD
828 SQUARE METRES OF SOLAR PV (PHOTO VOLTAIC) AND ANCILLARY DEVELOPMENT WORKS
REMOVAL OF THE EXISTING 'PRAMERICA' SIGN WITH LOGO EXTERNALLY MOUNTED ON THE SOUTH FACING ELEVATION OF EXISTING BLOCK 1
(1) RELOCATION OF SECONDARY BUILDING ENTRANCE WITH NEW ENTRANCE CANOPY ON THE NORTHERN ELEVATION, (2) RECONFIGURATION AND EXTENSION TO EXISTING MEZZANINE LEVEL, (3) RECONFIGURATION OF EXTERNAL FENESTRATIONS ON ALL THREE FACADES INCLUDING AMENDING/FORMATION OF EXISTING/NEW WINDOWS AND DOORS, (4) REMOVAL OF COVERED SMOKING AREA IN EXISTING CARPARK, (5) RECONFIGURATION OF THE EXTERNAL LANDSCAPING AND CAR PARKING LAYOUTS, (6) NEW BUILDING SIGNAGE AND (7) ALL ASSOCIATED WORKS AND SITE WORKS
(1) RELOCATION OF MAIN BUILDING ENTRANCE WITH NEW ENTRANCE CANOPY AT THE NEW ENTRANCE ON THE SOUTHERN ELEVATION (2) RECONFIGURATION OF EXTERNAL FENESTRATIONS ON ALL THREE FACADES INCLUDING AMENDING/FORMATION OF EXISTING/NEW WINDOWS AND DOORS (3) REMOVAL OF GLAZING TO THE SIDES OF THE SOUTH FACING PROJECTION AND REPLACE WITH NEW CLADDING INTEGRATED INTO THE ROOF OF THE PROJECTING SECTION OF THE BUILDING. (4) NEW CANOPY TO EXTERNAL STEPS FROM UPPER CAR PARK (5) REMOVAL OF GAS TANK AND INSTALLATION OF SMOKING SHELTER WITHIN THE SAME COMPOUND (6) RECONFIGURATION OF THE EXTERNAL LANDSCAPING AND CAR PARKING LAYOUTS (7) NEW BUILDING SIGNAGE AND ALL ASSOCIATED WORKS AND SITE WORKS
The brief summarizes the pattern across all 1,212 matched decisions within 5 km and includes up to 80 detailed comparables (40 nearest refusals and 40 nearest grants), with extracted reasons, quotes, and available source links. €29 incl. VAT.
Source match
Matched from public planning record 2350663The site brief adds up to 80 nearest detailed grants and refusals, extracted source evidence, document links, and a shareable risk summary.
Included in site brief
Included in site brief
Included in site brief
Included in site brief