Applications tied to the site
Partial coverage1 register record is within the point-match tolerance; a parcel boundary is needed to treat this as exact.
1 matchedSite planning risk brief
One-off house / within 5 km where a location match is available
Executive snapshot
13% of nearby decided applications were refused. The site check found 916 decisions within 5 km, 1 exact-site or onsite candidate record, and 79 structured appeals.
Evidence maturity
Each section reports its own coverage. “Not yet covered” means no conclusion is drawn while source datasets or policy extraction are still being loaded.
1 register record is within the point-match tolerance; a parcel boundary is needed to treat this as exact.
1 matchedCurrent indexed zoning and settlement layers are intersected with the selected site where coverage exists.
Current section-and-page citations have not yet been loaded for this authority.
Each layer reports its own coverage; missing coverage never appears as a clean result.
0 prompts are backed by extracted nearby decision evidence; all prompts remain checks, not predictions.
79 structured nearby appeal records.
79 matchedHistoric extracted references are not presented as current policy; verified citations are still being loaded.
Open preview
Open preview
We, McGarrell Reilly Homes intend to apply for a 10-year permission for development in the Townlands of Bennetstown, Pace, and Dunboyne. The subject site (2.79ha) encompasses an area of 0.87ha situated to the south-west of the M3 Parkway and south-east of the Dunboyne Bypass (R157) located in the Townland of Bennetstown, and the balance (1.92ha) located in the Townlands of Pace, Bennetstown and Dunboyne including the Dunboyne Bypass (R157) and M3 Parkway access, Kennedy Road and Navan Road for infrastructure works. The development will consist of: i. Construction of a single-storey commercial building with a cumulative gross floor space (GFS) of 2,160 sq.m comprising: a. A supermarket with delivery, store and service area (1,880 sq.m), including net retail floorspace of 1,510 sq.m, and b. 2 commercial units (combined 280 sq.m) to facilitate Class 1 (Shop), Class 2 (Financial, Professional and Other Services) or Café (food and beverage) uses. ii. Provision of a 4-arm signalised junction replacing the existing Pace roundabout to include a new northern arm with segregated cycleway and footpath; iii. Upgrade works to the existing R157 and M3 Parkway access road to facilitate junction improvements; iv. Access to the development is proposed via a new 3-arm priority-controlled junction from the upgraded southern arm of the proposed 4-arm signalised junction, with 6m wide internal access roads to serve the development; v. A total of 118 surface level car parking spaces including 6 disabled access bays and 4 electric car charging points; vi. 20 short-stay bicycle parking spaces; vii. 1 Electricity substation / switch room; viii. Foul sewer connection to existing public system including pumping station on site with rising mains along Kennedy Road and Navan Road; ix. Permission is also sought for hard and soft landscaping, lighting, attenuation and drainage and all ancillary site development works. Significant further information/revised plans submitted on this application
A Large-Scale Residential Development: permission for the following Large-Scale Residential Development consisting of: i) 309 no. residential units comprising 169 no. dwelling houses and 140 no. apartments/duplexes providing a mix of 1, 2, 3 and 4-bed units. The dwelling houses range in height from 2-3 storeys. The apartments/duplexes are in 8 no. blocks (i.e. Blocks A-H) ranging in height from 3 to 4 storeys; ii) a 2 storey creche; iii) modifications to the R157 regional road including changes to the existing carriageway/traffic lanes, the replacement of an existing roundabout with a new signalised junction and the provision of a northern arm off the new signalised junction; iii) a new signalised junction and link road (including new bridge over the River Tolka) connecting the R157 and the Old Navan Road; iv) the provision of footpaths, cycle lanes and 2 no. pedestrian crossings on the existing M3 Parkway access road, v) a foul pumping station and connection to the existing public sewerage system via the Old Navan Road; vi) a watermain connection to the north of the site at Pace (townland); vii) 3 no. ESB substation/kiosks; viii) temporary raised levels and soil storage to the south west of the site; ix) reprofiling of lands, construction of conveyance swales and a surface water runoff retention area as part of pluvial flood mitigation measures and x) all associated ancillary development works including footpaths, cycle lanes, car and bicycle parking, drainage, public lighting, bin storage, boundary treatments and landscaping/amenity areas at this site principally located in Bennetstown (townland) to the west of the R157, and also extending into Pace & Dunboyne (townlands), Dunboyne North, Co. Meath. Access will be via 2 no. new signalised junctions on to the R157 comprising 1 no. new vehicular access point to the southeast along the R157 and via 1 no. new vehicular access point to the north along a new northern arm off a new signalised junction which will replace the existing roundabout on the R157. The planning application red line boundary overlaps with planning ref. 23/60290, 23/60065 and 23/424. An Environmental Impact Assessment Report (EIAR) and Natura Impact Statement (NIS) has been submitted to the planning authority with the application
Permission for the following Large-Scale Residential Development consisting of: 1) the demolition of 2 no. existing agricultural farm sheds and associated structures, 2) the removal of the existing GAA pitch and associated structures; 3) the construction of 356 no. residential units comprising 252 no. dwelling houses and 104 no. maisonettes/apartments/duplexes providing a mix of 1, 2, 3 and 4-bed units. The dwelling houses range in height from 2-3 storeys. The maisonettes are 2 storey in height and the apartments/duplexes are in 4 no. blocks (i.e. Blocks A-D) ranging in height from 3 to 4 storeys; 4) a 2 storey creche; 5) modifications to the R157 regional road including changes to the existing carriageway/traffic lanes, the replacement of an existing roundabout with a new signalised junction and the provision of a northern arm off the new signalised junction; 6) a new signalised junction and link road (including new bridge over the River Tolka) connecting the R157 and the Old Navan Road; 7) the provision of footpaths, cycle lanes and 2 no. pedestrian crossings on the existing M3 Parkway access road, 8) foul pumping stations and connection to the existing public sewerage system via the Old Navan Road; 9) a watermain connection to the north of the site at Pace (townland); 10) 4 no. ESB substation/kiosks; 11) construction of conveyance swales and filter drains as part of pluvial flood mitigation measures and 12) all ancillary development works including footpaths, cycle lanes, car and bicycle parking, drainage, public lighting, bin/bike storage, boundary treatments and landscaping/amenity areas at this site principally located in Bennetstown (townland) to the west of the R157 and north of Kennedy Road, and also extending into Pace & Dunboyne (townlands), Dunboyne North, Co. Meath. Access will be via 2 no. new signalised junctions on to the R157 comprising 1 no. new vehicular access point to the southeast along the R157 and via 1 no. new vehicular access point to the north along a new northern arm off a new signalised junction which will replace the existing roundabout on the R157. The planning application red line boundary overlaps with planning ref. 23/60290 (ABP Ref: 320049-24), 23/60065, 23/424, 24/60805 and 25/61001. An Environmental Impact Assessment Report (EIAR) and Natura Impact Statement (NIS) has been submitted to the planning authority with the application. Significant further information/revised plans submitted on this application
The development will consist of: i. Construction of 3 no. office buildings with a cumulative gross floor area (GFA) of 13,729 sq.m ranging in height from 3 to 4- storeys and shall comprise the following: a. Building 1 (3,597 sq.m GFA) 3-storeys in height (12.35 metres to top of parapet), with a set back louvred screen 2m above parapet level. b. Building 2 (5,336 sq.m GFA) 4-storeys in height (16.125 metres to top of parapet), with a set back louvred screen 2m above parapet level. c. Building 3 (4,796 sq.m GFA) 4-storeys in height (16.125 metres to top of parapet), with a set back louvred screen 2m above parapet level. ii. Roof mounted solar PV panels (c. 180 sq.m combined area); iii. Provision of a 4-arm signalised junction replacing the existing Pace roundabout to include a new northern arm with segregated cycleway and footpath; iv. Access to the development is proposed from the new northern arm, with 6m wide internal access roads to serve the development; v. Upgrade works to the R157 and M3 Parkway access road to facilitate junction improvements; vi. A total of 275 surface car parking spaces including 14 disabled access bays and 55 electric car charging points; vii. 280 bicycle parking spaces in 3 secure cycle storage areas adjacent to the buildings; viii. Site signage is to be erected, all spot-lit and back-lit illuminated, including 2 no. type 1 entrance signs (6.15m x 2.4m) and 3 no. type 2 building signs (1.35m x 2.4m); ix. 3 standalone electricity substations; x. Foul sewer connection to existing public system including pumping station on site with rising mains along Kennedy Road and Navan Road; xi. Watermain connection to the north east of site at Pace for connection to Irish Water Infrastructure; xii. Permission is also sought for associated landscaping, boundary treatments, public lighting, plant, waste storage and all ancillary site and development works. A Natura Impact Statement (NIS) has been prepared in respect of the proposed development. Signficant further information/revised plans submitted on this application
Permission for the following Large-Scale Residential Development consisting of: i) 267 no. residential units comprising 145 no. dwelling houses and 122 no. apartments/duplexes providing a mix of 1, 2, 3 and 4-bed units. The dwelling houses range in height from 2-3 storeys. The apartments/duplexes are in 8 no. blocks (i.e. Blocks A-H, with Blocks B and C joined) ranging in height from 3 to 5 storeys; ii) a single storey creche; iii) modifications to the R157 regional road including changes to the existing carriageway/traffic lanes and the replacement of an existing roundabout with a new signalised junction; iv) a new signalised junction and link road (including new bridge over the River Tolka) connecting the R157 and the Old Navan Road; v) the provision of footpaths, cycle lanes and 2 no. pedestrian crossings on the existing M3 Parkway access road, vi) a foul pumping station and connection to the existing public sewerage system via the Old Navan Road; vii) a watermain connection to the north of the site at Pace (townland); viii) 3 no. ESB substation/kiosks and the undergrounding/re-routing of existing electricity lines; ix) reprofiling of land and relocation of existing berm adjoining the River Tolka as part of flood mitigation measures; and x) all associated ancillary development works including footpaths, cycle lanes, car and bicycle parking, drainage, public lighting, bin storage, boundary treatments and landscaping/amenity areas at this site measuring 14.17 hectares principally located in Bennetstown (townland) to the south of the M3 Parkway park and ride and rail station, and also extending into Pace & Dunboyne (townlands), Dunboyne North, Co. Meath. Access will be via 2 no. new vehicular access points along the new link road between the R157 and the Old Navan Road. Pedestrian access will also be provided on to the existing M3 Parkway access road. An Environmental Impact Assessment Report (EIAR) and Natura Impact Statement (NIS) has been submitted to the planning authority with the application. Significant further information/revised plans submitted with this application
The conversion of the existing station building to use as staff accommodation for Iarnród Eireann. The buildings interior will be subdivided to provide offices, canteen, toilet and shower facility, locker rooms and storage. Construction of a new open-plan workshop and storage facility complete with loading bay, workstations and external company logo. External storage facility. Parking for company vehicles. The total works involved cover an area of approx. 512m2 of plan area, and approx 75 linear metres of street frontage.
The brief summarizes the pattern across all 916 matched decisions within 5 km and includes up to 80 detailed comparables (40 nearest refusals and 40 nearest grants), with extracted reasons, quotes, and available source links. €29 incl. VAT.
Source match
Matched from public planning record 2360065The site brief adds up to 80 nearest detailed grants and refusals, extracted source evidence, document links, and a shareable risk summary.
Included in site brief
Included in site brief
Included in site brief
Included in site brief