Applications tied to the site
Partial coverage1 register record is within the point-match tolerance; a parcel boundary is needed to treat this as exact.
1 matchedSite planning risk brief
One-off house / within 5 km where a location match is available
Executive snapshot
16% of nearby decided applications were refused. The site check found 413 decisions within 5 km, 1 exact-site or onsite candidate record, and 44 structured appeals.
Evidence maturity
Each section reports its own coverage. “Not yet covered” means no conclusion is drawn while source datasets or policy extraction are still being loaded.
1 register record is within the point-match tolerance; a parcel boundary is needed to treat this as exact.
1 matchedCurrent indexed zoning and settlement layers are intersected with the selected site where coverage exists.
Current section-and-page citations have not yet been loaded for this authority.
Each layer reports its own coverage; missing coverage never appears as a clean result.
0 prompts are backed by extracted nearby decision evidence; all prompts remain checks, not predictions.
44 structured nearby appeal records.
44 matchedHistoric extracted references are not presented as current policy; verified citations are still being loaded.
Open preview
Open preview
A solar farm to be installed over restored landfill with an export capacity of approximately 3MW comprising photovoltaic panels on ground mounted frames, connection to existing single-storey ESB Sub- Station / switch room building, installation of 3 No. transformers, ducting and underground electrical cabling and all associated ancillary works and services. Revised by significant further information consisting of; construction management plan detailing construction techniques
For a solar farm to be installed over restored landfill with an export capacity of approximately 4.5MW comprising photovoltaic panels on concrete ballast supported frames, construction of and connection to a new single-storey ESB Sub-Station / Switch Room building, installation of 3 No. transformers, ducting & electrical cabling and all associated ancillary works and services
Alterations to previously granted application PL 19/1085, (single storey extension to existing dormer style dwelling currently under construction) alterations include the relocation of the front door, reduction of floor area, external alterations to window sizes and locations and all associated site works
A single storey extension to side and rear of existing dormer style dwelling, internal renovations and alterations, use of existing onsite services and all ancillary site works
(a) Proposed new two storey dwelling; (b) New vehicle entrance; (c) Domestic double garage; (d) Treatment system and percolation area along with all associated site development facilitating works
The retention of the following a) Change of use of previously granted outhouse building under planning ref. 02/66 to cookery demonstration school. b) Extension to cookery demonstration school to include demonstration area and storeroom. c) Amendments to existing site layout including all associated site development and facilitating works. d) Planning permission for proposed new covered seating area. e) Proposed upgrading of existing vehicle entrance. f) Proposed installation of new treatment system & percolation area & decommissioning of existing septic tank along with all associated site development and facilitating works
The brief summarizes the pattern across all 413 matched decisions within 5 km and includes up to 80 detailed comparables (40 nearest refusals and 40 nearest grants), with extracted reasons, quotes, and available source links. €29 incl. VAT.
Source match
Matched from public planning record 18969The site brief adds up to 80 nearest detailed grants and refusals, extracted source evidence, document links, and a shareable risk summary.
Included in site brief
Included in site brief
Included in site brief
Included in site brief