Applications tied to the site
Partial coverage10 register records are within the point-match tolerance; a parcel boundary is needed to treat this as exact.
10 matchedSite planning risk brief
One-off house / within 5 km where a location match is available
Executive snapshot
22% of nearby decided applications were refused. The site check found 512 decisions within 5 km, 10 exact-site or onsite candidate records, and 30 structured appeals.
Evidence maturity
Each section reports its own coverage. “Not yet covered” means no conclusion is drawn while source datasets or policy extraction are still being loaded.
10 register records are within the point-match tolerance; a parcel boundary is needed to treat this as exact.
10 matchedCurrent indexed zoning and settlement layers are intersected with the selected site where coverage exists.
Current section-and-page citations have not yet been loaded for this authority.
Each layer reports its own coverage; missing coverage never appears as a clean result.
0 prompts are backed by extracted nearby decision evidence; all prompts remain checks, not predictions.
30 structured nearby appeal records.
30 matchedHistoric extracted references are not presented as current policy; verified citations are still being loaded.
Open preview
Open preview
Permission for 1. Demolition of 2 existing sheds; 2. Construction of new workshop associated with kitchen manufacturing business; 3. Construction of new workshop/general storage shed; 4. Alterations to existing façades of existing storage shed with offices to be provided at first floor level; 5. Alterations and upgrading of existing entrance to site and boundary treatments; 6. Upgrading of existing septic tank system to new waste water treatment plant and percolation area; and all associated site development works.
Permission for development that consists of the following: 1. Extension to rear of proposed workshop/general storage shed, 2. Construction of boundary wall to rear of property to match existing wall, 3. Reduction in size of building previously granted under application Ref no. 19/588 and all associated site development works. These amendments are to previously granted planning permission Ref No 19/588 which consisted of the following:1. Demolition of 2 existing sheds, 2. Construction of new workshop associated with kitchen manufacturing business, 3. Construction of new workshop/general storage shed, 4. Alterations to existing façades of existing storage shed with offices to be provided at first floor level 5. Alterations and upgrading of existing entrance to site and boundary treatments 6. Upgrading of existing septic tank system to new waste water treatment plant and all associated site development works
Permission for development to consist of the following: 1. Change of use of existing workshop to offices, 2. Removal of condition 2 of planning ref. no. 20 943 in relation to existing building to allow for leasing and all associated site development works.
The development consists of the following: 1. Change of use from voluntary community workshop to showrooms to existing kitchen manufacturing business, 2. First floor extension to provide office accommodation and all Associated site development works. *Significant Further Information Received on 28/01/2026*
Permission for extension to front of existing workshop, elevational changes and all associated site development works.
Permission for development to consist of (a) partial demolition of existing school including detached external store, permanent teaching structure and temporary teaching structures (b) construction of new two storey extension which will include Home Economics, Science, Art and general classrooms along with Special Needs Unit, offices, and ancillary stores (c) extension to include roof mounted photovoltaic panels (d) provision of new onsite ESB substation structure (e) provision of new on site proprietary wastewater treatment system with 24 hour storage (15.2m3) and sand polishing filter (400m2), (f) modifications to existing school elevation forming new general classroom space (g) modifications to existing front boundary including width increase of both existing site entrances (h) adjustment to existing bus set down to front of school (i) reconfiguration of existing onsite parking and provision of new staff parking areas with onsite visitor set down and parking facilities (j) the site is the subject of a hydrological assessment (k) and all ancillary site works.
The brief summarizes the pattern across all 512 matched decisions within 5 km and includes up to 80 detailed comparables (40 nearest refusals and 40 nearest grants), with extracted reasons, quotes, and available source links. €29 incl. VAT.
Source match
Matched from public planning record 19588The site brief adds up to 80 nearest detailed grants and refusals, extracted source evidence, document links, and a shareable risk summary.
Included in site brief
Included in site brief
Included in site brief
Included in site brief