Applications tied to the site
Partial coverage6 register records are within the point-match tolerance; a parcel boundary is needed to treat this as exact.
6 matchedSite planning risk brief
One-off house / within 5 km where a location match is available
Executive snapshot
4% of nearby decided applications were refused. The site check found 157 decisions within 5 km, 6 exact-site or onsite candidate records, and 4 structured appeals.
Evidence maturity
Each section reports its own coverage. “Not yet covered” means no conclusion is drawn while source datasets or policy extraction are still being loaded.
6 register records are within the point-match tolerance; a parcel boundary is needed to treat this as exact.
6 matchedCurrent indexed zoning and settlement layers are intersected with the selected site where coverage exists.
Current section-and-page citations have not yet been loaded for this authority.
Each layer reports its own coverage; missing coverage never appears as a clean result.
0 prompts are backed by extracted nearby decision evidence; all prompts remain checks, not predictions.
4 structured nearby appeal records.
4 matchedHistoric extracted references are not presented as current policy; verified citations are still being loaded.
Open preview
Open preview
For development consisting of: o The construction of one Enercon 138 wind energy converter on an 99m tower with an electrical rating of 4.2MW and an overall tip height of 169m; o The construction of the wind energy converter foundation, hardstanding and assembly area; o Provision of a site entrance and an access track within the site; o Construction of an on-site 20kV substation and underground electrical cable; and o All associated site development and ancillary works
For: 1) The construction of one Enercon 115 wind turbine on a 92m tower with an electrical rating of 4.2MW and an overall tip height of 149.86m; 2) The construction of the wind turbine foundation, hardstanding and assembly area; 3) Provision of a site entrance and an access track within the site; 4) Construction of an on-site 20kV substation and underground electrical cable; and 5) All associated site development and ancillary works Significant further information and revised plans has been submitted.
For a minor amendment to planning application No. 2360009 to reposition the (A) site substation & (B) temporary site compound
For development consisting of; The construction of one 4.2MW wind turbine with an overall tip height of up to 125m; The construction of the wind turbine foundation, hard standing and assembly area; Provision of a site entrance and an access track within the site; Construction of an on-site 20kV substation and underground electrical cable; and all associated development and ancillary works
For the renovation & extension of existing two storey dwelling. Works to include 1) Demolition of existing two storey front porch and single storey side extension, 2) Erection of a new extension to the rear of the dwelling at first floor level and a new entrance canopy to the side/rear, 3) Alterations to internal layout and elevations and associated site works
For the erection of a dormer dwelling, attached domestic store, new entrance, effluent treatment system, percolation area & associated site works
The brief summarizes the pattern across all 157 matched decisions within 5 km and includes up to 80 detailed comparables (40 nearest refusals and 40 nearest grants), with extracted reasons, quotes, and available source links. €29 incl. VAT.
Source match
Matched from public planning record 22137The site brief adds up to 80 nearest detailed grants and refusals, extracted source evidence, document links, and a shareable risk summary.
Included in site brief
Included in site brief
Included in site brief
Included in site brief