Applications tied to the site
Partial coverage2 register records are within the point-match tolerance; a parcel boundary is needed to treat this as exact.
2 matchedSite planning risk brief
One-off house / within 5 km where a location match is available
Executive snapshot
11% of nearby decided applications were refused. The site check found 117 decisions within 5 km, 2 exact-site or onsite candidate records, and 6 structured appeals.
Evidence maturity
Each section reports its own coverage. “Not yet covered” means no conclusion is drawn while source datasets or policy extraction are still being loaded.
2 register records are within the point-match tolerance; a parcel boundary is needed to treat this as exact.
2 matchedCurrent indexed zoning and settlement layers are intersected with the selected site where coverage exists.
Current section-and-page citations have not yet been loaded for this authority.
Each layer reports its own coverage; missing coverage never appears as a clean result.
0 prompts are backed by extracted nearby decision evidence; all prompts remain checks, not predictions.
6 structured nearby appeal records.
6 matchedHistoric extracted references are not presented as current policy; verified citations are still being loaded.
Open preview
Open preview
To retain additional windows to the side elevations to her house
RETAIN AN EXISTING TELECOMMUNICATIONS SUPPORT STRUCTURE (PREVIOUSLY GRANTED UNDER LOCAL AUTHORITY REF NO. 11/969) (AN BORD PLEANALA REFERENCE PL 08.240232) TOGETHER WITH ASSOCIATED GROUND EQUIPMENT, SECURITY FENCE, AND ACCESS TRACK
CLOSE UP THE EXISTING EASTERN VECHICULAR ENTRANCE, RETAIN AND COMPLETE THE EXISTING WESTERN VEHICULAR ENTRANCE AND ALL ASSOCIATED SITE WORKS TO HIS DWELLING HOUSE.
FOR A 10 YEAR PERMISSION TO CONSTRUCT A BATTERY ENERGY STORAGE SYSTEM (BESS) FACILITY ON A TOTAL SITE AREA OF UP TO 0.6HA THAT WILL PROVIDE GIRD BALANCING SERVICES TO THE IRISH ELECTRICAL GRID, TO INCLUDE UP TO 26 NO. SELF-CONTAINED BATTERY CONTAINER UNITS WITH ASSOCIATED HEATING VENTILATION AND AIR CONDITIONING SYSTEMS (HVAC), POWER CONVERSION SYSTEMS (PCS), STEP-UP TRANSFORMERS, CONTROL SYSTEMS AND ANCILLARY ELECTRICAL COMPONENTS, 1 NO. SINGLE – STOREY ELECTRICITY CONTROL BUILDING, 1 NO. 110KV ESB SUBSTATION, SINGLE STOREY SUBSTATION CONTROL BUILDING AND ASSOCIATED ELECTRICAL INFRASTRUCTURE, 1 NO. 110 KV GENERATOR TRANSFORMER, ALL NECESSARY GROUND AND FOUNDATION WORKS, ASSOCIATED COMPOUND CABLING AND DUCTING, PALISADE SECURITY FENCING AND LIGHTING, CCTV SECURITY CAMERAS, NEW SITE ACCESS FROM EXISTING PRIVATE ROAD, TEMPORARY CONSTRUCTION COMPOUND AND ALL ASSOCIATED ANCILLARY INFRASTRUCTURE AND SITE DEVELOPMENT WORKS. A NATURA IMPACT STATEMENT (NIS) IS NOW SUBMITTED IN SUPPORT OF THE APPLICATION
CONSTRUCT A DWELLINGHOUSE AND A DOMESTIC GARAGE SERVED BY AN EFFLUENT TREATMENT TANK AND POLISHING FILTER
(A) DEMOLISH EXISTING SINGLE STOREY KITCHEN TO THE REAR OF THE DWELLING HOUSE, (B) DEMOLISH THE EXISTING DETACHED DOMESTIC GARAGE, (C) CONSTRUCT A SINGLE STOREY FLAT ROOF EXTENSION TO THE REAR OF THE EXISTING DWELLING AND CARRY OUT ASSOCIATED INTERNAL ALTERATIONS COMPLETE WITH ALL ANCILLARY SITE WORKS, (D) RETAIN THE CHANGE OF USE OF ORIGINAL ATTACHED DOMESTIC GARAGE TO RESIDENTIAL USE AND ALL ASSOCIATED ELEVATIONAL CHANGES
The brief summarizes the pattern across all 117 matched decisions within 5 km and includes up to 80 detailed comparables (40 nearest refusals and 40 nearest grants), with extracted reasons, quotes, and available source links. €29 incl. VAT.
Source match
Matched from public planning record 2561176The site brief adds up to 80 nearest detailed grants and refusals, extracted source evidence, document links, and a shareable risk summary.
Included in site brief
Included in site brief
Included in site brief
Included in site brief