Applications tied to the site
Partial coverage3 register records are within the point-match tolerance; a parcel boundary is needed to treat this as exact.
3 matchedSite planning risk brief
One-off house / within 5 km where a location match is available
Executive snapshot
12% of nearby decided applications were refused. The site check found 283 decisions within 5 km, 3 exact-site or onsite candidate records, and 24 structured appeals.
Evidence maturity
Each section reports its own coverage. “Not yet covered” means no conclusion is drawn while source datasets or policy extraction are still being loaded.
3 register records are within the point-match tolerance; a parcel boundary is needed to treat this as exact.
3 matchedCurrent indexed zoning and settlement layers are intersected with the selected site where coverage exists.
Current section-and-page citations have not yet been loaded for this authority.
Each layer reports its own coverage; missing coverage never appears as a clean result.
0 prompts are backed by extracted nearby decision evidence; all prompts remain checks, not predictions.
24 structured nearby appeal records.
24 matchedHistoric extracted references are not presented as current policy; verified citations are still being loaded.
Open preview
Open preview
The proposed development comprises the construction of: A) a 1062m2 warehouse extension to the south of an existing light industrial warehouse building; B) demolition of an existing 92m2 light industrial unit; C) a 105m2 extension to the west of an existing light industrial warehouse building; D) hard and soft landscaping, boundary treatments, and all associated works and site works to facilitate the development
Retention permission for a new front boundary wall, vehicular entrance with off street parking and all associated site works
Development at a site at the entrance to the Tullow Wastewater Treatment Plant, Bunclody Road (N81), Tullow, Co. Carlow, R93 RY69 measuring approximately 0.14 hectares. The development will consist of [1] the retention of the existing ‘as built’ wall to the north and south of the site entrance to the Tullow Wastewater Treatment Plant; [2] the demolition of part of the ‘as built’ southern wall, fence and hardstanding; [3] the construction of a new realigned section of wall, concrete hand standing and fence to tie in with the remainder of the ‘as built’ wall, footpath and fence; and [4] hard and soft landscaping works and other associated site development works above & below ground necessary to deliver the development
Development at a site entrance to the Tullow Wastewater Treatment Plant, measuring approximately 0.0605 hectares. The development will consist of works to improve the visibility splay at the ertrance to Tullow Wastewater Treatment Plant, including; demolition of the existing boundary fencing; construction of new retaining boundary walls and new boundary fencing and the provision of a new grass verge along the N81. The development will also consist of the: relocation of existing road signage; relocation of utility and light standard poles; all hard and soft landscaping; and all other associated site excavation, infrastructural and site development works above and below ground including changes in level and boundary treatments
The construction of an extension to the northeastern end of an existing manufacturing unit and all associated site works
The construction of an industrial unit, connection to existing site services and all associated and ancillary development works
The brief summarizes the pattern across all 283 matched decisions within 5 km and includes up to 80 detailed comparables (40 nearest refusals and 40 nearest grants), with extracted reasons, quotes, and available source links. €29 incl. VAT.
Source match
Matched from public planning record 2460161The site brief adds up to 80 nearest detailed grants and refusals, extracted source evidence, document links, and a shareable risk summary.
Included in site brief
Included in site brief
Included in site brief
Included in site brief