Applications tied to the site
Partial coverage1 register record is within the point-match tolerance; a parcel boundary is needed to treat this as exact.
1 matchedSite planning risk brief
One-off house / within 5 km where a location match is available
Executive snapshot
13% of nearby decided applications were refused. The site check found 149 decisions within 5 km, 1 exact-site or onsite candidate record, and 5 structured appeals.
Evidence maturity
Each section reports its own coverage. “Not yet covered” means no conclusion is drawn while source datasets or policy extraction are still being loaded.
1 register record is within the point-match tolerance; a parcel boundary is needed to treat this as exact.
1 matchedCurrent indexed zoning and settlement layers are intersected with the selected site where coverage exists.
Current section-and-page citations have not yet been loaded for this authority.
Each layer reports its own coverage; missing coverage never appears as a clean result.
0 prompts are backed by extracted nearby decision evidence; all prompts remain checks, not predictions.
5 structured nearby appeal records.
5 matchedHistoric extracted references are not presented as current policy; verified citations are still being loaded.
Open preview
Open preview
Development of a 22-hectare site. The proposed development comprises (i) two (2no.) air dome structures for the storage of carbon dioxide at atmospheric pressure (each 500m x 120m x 34m high) and associated cooling, compression, pumping and power generation equipment and machinery (ii) a single-storey storage and control building, (iii) internal site access roads and connection to existing and consented roads at Rhode Green Energy Park, (iv) underground electrical cable connection to Derryiron 110kV substation, (v) all civil engineering works, surface water and foul water drainage, landscaping, lighting and security fencing
AN ENERGY STORAGE FACILITY DESIGNED TO PROVIDE SYSTEM SUPPORT SERVICES TO THE ELECTRICITY GRID ON A 2.7-HECTARE SITE. THE DEVELOPMENT WILL COMPRISE: (i) AN OPEN AREA BATTERY ENERGY STORAGE SYSTEM (BESS) COMPOUND (AREA OF 3,407 SQM) CONTAINING 16 NO. BATTERY ENCLOSURES (13.716M LONG X 2.90M WIDE X 3.796M HIGH), 16 NO. MEDIUM VOLTAGE POWER STATION (MVPS) ENCLOSURES (12.192M LONG X 2.438M WIDE X 3.396M HIGH), (ii) SYNCHRONOUS CONDENSER COMPOUND (AREA OF 4,706SQM) CONTAINING SYNCHRONOUS CONDENSER BUILDING (30.0M LONG X 18.0M WIDE X 12.15M HIGH), CONTROLS BUILDING (12.486M LONG 12.192M WIDE X 4.865M HIGH), ASSOCIATED BUNDED TRANSFORMERS AND ELECTRICAL PLANT, (iii) ELECTRICAL SUBSTATION (AREA OF 2,325SQM) CONTAINING CUSTOMER BUILDING (10.032M LONG X 7.627M WIDE X 6.169M HIGH), EIRGRID BUILDING (13.507M LONG X 12.509M WIDE X 7.577M HIGH), AND ELECTRICAL PLANT AND BUNDED TRANSFORMER WHICH WILL ELECTRICALLY CONNECT THE DEVELOPMENT TO THE EXISITING DERRYION 110KV SUBSTATION LOCATED ON LANDS ADJOINING THE SITE TO THE SOUTH, (iv) CONTROL BUILDING (17.075M LONG X 5.830M WIDE X 5.960M HIGH), AND (v) ALL ANCILLARY DEVELOPMENT, INCLUDING; LIGHTING MAST PROTECTION, PERIMETER PALISADE FENCING WITH ACCESS GATE AT PRIMARY VEHICLE SITE ENTRANCE WHICH WILL CONNECT TO THE EXISTING ROADS OF THE ADJACENT RHODE BUSINESS PARK PROVIDING ACCESS TO THE R400, LANDSCAPING, LIGHTING,CAR PARKING, INTERNAL ACCESS ROADS AND ALL CIVIL ENGINEERING WORKS FOR THE DISPOSAL OF FOUL AND SURFACE WATER. A NATURA IMPACT STATEMENT (NIS) HAS BEEN PREPARED AND ACCOMPANIES THIS PLANNING APPLICATION
DEVELOPMENT OF AN ENERGY STORAGE FACILITY DESIGNED TO PROVIDE 20MW OF SYSTEM SUPPORT SERVICES TO THE ELECTRICITY GRID ON A 0.95 HECTARE SITE. THE DEVELOPMENT WILL COMPRISE: (I) AN OPEN AREA BATTERY ENERGY STORAGE SYSTEM (BESS) COMPOUND (AREA OF 563 SQM) CONTAINING 8 NO. BATTERY AND CONTROL SYSTEM ENCLOSURES (C. 12.2M LONG X 2.5M WIDE X 4M HIGH), (II) SINGLE STOREY SWITCHGEAR BUILDING (C. 18M LONG X 15M WIDE X 3M HIGH) CONTAINING ELECTRICIAL PLANT AND CONTROL ROOM, (III) BUNDED TRANSFORMER WHICH WILL ELECTRICALLY CONNECT THE DEVELOPMENT VIA OVERHEAD CABLE TO THE EXISTING 110KV DERRYIRON SUBSTATION LOCATED ON LANDS ADJOINING THE SITE TO THE SOUTH, AND (IV) ALL ANCILLARY DEVELOPMENT, INCLUDING; PERIMIETER PALISADE FENCING WITH ACCESS GATE AT PRIMARY VEHICLE SITE ENTRANCE WHICH WILL CONNECT TO THE EXISTING ROADS OF THE ADJACENT RHODE BUISINESS PARK PROVIDING ACCESS TO THE R400, LANDSCAPING, LIGHTING, CAR PARKING, INTERNAL ACCESS ROADS AND ALL CIVIL ENGINEERING WORKS FOR THE DISPOSAL OF FOUL AND SURFACE WATER
A 10-year planning permission for works to the existing Derryiron 110 kilovolt (kV) electricity substation comprising (i) an increase to the footprint of the substation compound by 190 square metres (m2) arising from the realignment of the existing palisade fence; (ii) the installation of electrical equipment including circuit breakers, cable sealing ends and voltage transformers; (iii) the installation of approximately 20m of 110kV underground electricity line; and, (iv) all associated ancillary site development works. This planning application is accompanied by an Appropriate Assessment Screening Report
EIRGRID PLC (WITH THE CONSENT AND APPROVAL OF THE ELECTRICITY SUPPLY BOARD (ESB)), INTENDS TO APPLY FOR PERMISSION FOR DEVELOPMENT AT SITE OF APPROXIMATELY 1 HECTARE AT DERRYIRON 110KV SUBSTATION, CLONIN, RHODE, CO. OFFALY. DEVELOPMENT CONSISTING OF WORKS TO UPGRADE THE EXISTING SUBSTATION INCLUDING: THE INSTALLATION OF ADDITIONAL AIR INSULATED SWITCHGEAR ELECTRICAL APPARATUS (APPROXIMATELY 7M IN HEIGHT) TO FACILITATE THE PROVISION OF A 110KV BUSBAR; INSTALLATION OF 3 NO. ADDITIONAL BAYS (EACH CONSISTING OF BUSBAR DISCONNECTS, SECTIONALISERS, CIRCUIT BREAKERS, CURRENT TRANSFORMERS, VOLTAGE TRANSFORMERS, LINE TRAPS, COUPLING CAPACITORS AND OTHER ELECTRICAL APPARATUS); AN EXTENSION TO THE NORTH OF THE EXISTING CONTROL BUILDING (APPROXIMATELY 73 SQUARE METERS) TO PROVIDE ACCOMMODATION FOR CABINETS, OTHER ELECTRICAL APPARATUS AND A BATTERY ROOM; INSTALLATION OF 2 NO. CIRCUIT BYPASS ARRANGEMENTS (APPROXIMATELY 14M AND APPROXIMATELY 4M IN HEIGHT, RESPECTIVELY) TO FACILITATE NORMAL OPERATION OF THE SUBSTATION DURING CONSTRUCTION; AND AN EXTENSION TO THE HARDSTAND COMPOUND (APPROXIMATELY 0.03 HECTARES). THE DEVELOPMENT WILL ALSO CONSIST OF: ALL ANCILLARY AND ASSOCIATED ELECTRICAL WORKS TO FACILITATE THE PROPOSED DEVELOPMENT; AND ALL OTHER ASSOCIATED SITE EXCAVATION, INFRASTRUCTURAL AND SITE DEVELOPMENT WORKS ABOVE AND BELOW GROUND, INCLUDING SITE PREPARATION WORKS, SITE CLEARANCE AND LEVELLING; HARDSTANDING, INTERNAL ACCESS TRACKS AND TEMPORARY CONSTRUCTION COMPOUND; EARTHGRID, SURFACE WATER DRAINAGE NETWORK; PALISADE FENCING (APPROXIMATELY 2.7M HIGH) AND GATES; AND LANDSCAPING.
DEVELOPMENT CONSISTING OF A SOLAR PV ENERGY DEVELOPMENT WITHIN A SITE AREA OF APPROXIMATELY 15HA. THIS AREA WAS REMOVED BY MEANS OF CONDITION NO. 2 IN PREVIOUS PLANNING REFERENCE PL2/16/246
The brief summarizes the pattern across all 149 matched decisions within 5 km and includes up to 80 detailed comparables (40 nearest refusals and 40 nearest grants), with extracted reasons, quotes, and available source links. €29 incl. VAT.
Source match
Matched from public planning record 2460289The site brief adds up to 80 nearest detailed grants and refusals, extracted source evidence, document links, and a shareable risk summary.
Included in site brief
Included in site brief
Included in site brief
Included in site brief