Executive snapshot
3% of nearby decided applications were refused. The site check found 460 decisions within 5 km, 2 exact-site or onsite candidate records, and 17 structured appeals.
Evidence maturity
Each section reports its own coverage. “Not yet covered” means no conclusion is drawn while source datasets or policy extraction are still being loaded.
2 register records are within the point-match tolerance; a parcel boundary is needed to treat this as exact.
2 matchedCurrent indexed zoning and settlement layers are intersected with the selected site where coverage exists.
Current section-and-page citations have not yet been loaded for this authority.
Each layer reports its own coverage; missing coverage never appears as a clean result.
0 prompts are backed by extracted nearby decision evidence; all prompts remain checks, not predictions.
17 structured nearby appeal records.
17 matchedHistoric extracted references are not presented as current policy; verified citations are still being loaded.
Open preview
Open preview
The construction and operation of solar PV arrays mounted on metal frames on a 37.6ha site, inclusive of an electrical substation compound, up to 10 inverter units, a temporary construction area and ancillary facilities, (inclusive of gross floor space of proposed works up to 248 sq.m). The planning application is accompanied by an environmental report and Natura Impact Statement
A) a single storey material recovery and transfer facility building (of floor area 1031 m sq), b) a single storage detached prefabricated office building (floor area 60 m sq) with signage on both buildings, c) vehicular access to the site is via the as constructed existing entrance, d) a service yard with vehicle weighbridge and vehicle washing area with the site, e) on-site staff and visitor car parking and truck parking areas, f) all necessary ancillary site development works to facilitate this development with boundary treatment and landscaping, g) all associated site works consisting of petrol interceptor and silt traps and connection to existing septic tank and upgraded percolation area with all associated site works (the application relates to an activity requiring a waste facility permit from Tipperary County Council, the waste tonnage for acceptance and handling at the facility will not exceed 24,500 tonnes per annum)
The relocation of a single storey detached prefabricated office building with commercial vehicle weighbridge, the relocation of a public civic amenity recycling facility, signage and planting. This development is subject to a waste licence
An extension to the side of existing warehouse premises for storage use with all associated sitework and ancillary works
A 3 no dock levellers constructed to the North East side of our premises and permission to fit new cladding to the all elevations to the same building with all associated sitework and ancillary works.
(a) a single storey extension to side of dwelling house and (b) a single storey extension to the rear of dwelling house, which is connected to mains services and all associated works
The brief summarizes the pattern across all 460 matched decisions within 5 km and includes up to 80 detailed comparables (40 nearest refusals and 40 nearest grants), with extracted reasons, quotes, and available source links. €29 incl. VAT.
Source match
Matched from public planning record 19601159The site brief adds up to 80 nearest detailed grants and refusals, extracted source evidence, document links, and a shareable risk summary.