  1. © OpenStreetMap
    2350892Granted

    DERRYKILLEW, CORLEA CASHELARD, DOOBALLY KNADER & TOWNPARKS BALLYSHANNON

    (1) A 38KV UNDERGROUND CABLE GRID CONNECTION APPROXIMATELY 9KM IN LENGTH FROM THE CONSENTED DERRYKILLEW COMMUNITY WIND FARM (AN BORD PLEANÁLA REF. NO. 307520, DONEGAL COUNTY COUNCIL REF. NO. 19/51750) TO LANDS AT TOWNPARKS, NORTH OF THE EXISTING CATHALEEN'S FALL 110KV SUBSTATION IN BALLYSHANNON, (2) A PARTIAL SECTION OF A 38KV OVERHEAD LINE GRID CONNECTION CROSSING 130M OVER THE RIVER ERNE AT CATHALEEN'S FALL, BALLYSHANNON, AND (3) THE DERRYKILLEW COMMUNITY WIND FARM 38KV SUBSTATION AND A BATTERY ENERGY STORAGE SYSTEM. AN ENVIRONMENTAL IMPACT ASSESSMENT REPORT (EIAR) ACCOMPANIES THIS APPLICATIONDecision record indexed
    Decision21 March 2024View record
  2. © OpenStreetMap
    1951750Refused

    DERRYKILLEW, CORLEA, BALLYSHANNON

    ALTERATIONS TO (A) INCREASE IN TIP HEIGHT OF THE FIVE PERMITTED TURBINES, FROM 136 METRES TO UP TO 150 METRES (B) AMENDMENTS TO LOCATIONS OF PERMITTED TURBINES NO.'S 1 AND 3; (C) INCREASE IN SIZE OF PERMITTED HARDSTANDING AREAS; (D) UPGRADING OF EXISTING ACCESS TRACKS AND PROVISION OF NEW SITE ACCESS ROADS; (E) ALL ASSOCIATED UNDERGROUND ELECTRICAL AND COMMUNICATIONS CABLING CONNECTING THE TURBINES TO THE ONSITE SUBSTATION; (F) ALL ASSOCIATED SITE DEVELOPMENT WORKS (INCLUDING TREE FELLING). THE PROPOSED DEVELOPMENT WILL HAVE AN OPERATIONAL LIFE OF 30 YEARS FROM THE DATE OF COMMISSIONING OF THE DEVELOPMENT AND THE APPLICATION SEEKS A TEN YEAR PLANNING PERMISSION. AN ENVIRONMENTAL IMPACT AWARENESS REPORT AND A NATURA IMPACT STATEMENT ACCOMPANY THIS APPLICATIONGrounds not yet categorised
    Decision11 June 2020View record