Conditional grantDecided 05 June 2020Carlow County Council

2067: The erection of a slatted cattle shed, unroofed silage pit, cattle handling area, concrete yards and ancillary work.

Tomard Upper, Co. Carlow
DecisionConditional grant
Decided05 June 2020
Application typePERMISSION
Source documents3

Site

What is on file

0refusal reasons14conditions8nearby records

Decision details

Core application dates and identifiers from the public planning record.

Planning analysis

Refusal reasons and planning conditions extracted from the public decision file.

Refusal reasons

No refusal reason

No refusal reason is on record for this application yet.

Conditions

  • 1Development must be carried out in accordance with plans received on 27/02/20.Compliance
  • 2Permission limited to development detailed in submitted plans; no other development authorised.Compliance
  • 3External concrete walls neutral finish; roof/side panels dark green matt finish.Design Materials
  • 4Agricultural purposes only; no commercial use other than incidental to farming.Occupancy
  • 5Existing mature trees and hedgerows on/bounding site must be retained and maintained.Environment Ecology
  • 6Lines of sight at road entrance per DMRB. Road opening works require Road Opening Licence per Guidelines (2007) submitted for written agreement prior to commencement.Traffic Access
  • 7Only clean water to soak pits/drains per BS8301/BRE Digest 365. Design/construction/operation per S.I. 1605/2017. Noise/vibration per BS 5228 standards.Wastewater Drainage
  • 8Do not impair existing drainage without Municipal District Engineer agreement. No surface water runoff to public road/adjoining properties. All surface water to soakways/system per B.S. 8301:1985 and BRE Digest 365.Wastewater Drainage
  • 9Only clean surface water to soakpits/system. Only foul/soiled water to wastewater treatment system.Wastewater Drainage
  • 10Connect to Irish Water network requires signed connection/self-lay agreement prior to commencement. Comply with CDS Technical Documentation. New agreement if impact significant. Connections subject to Irish Water Capital Investment Programme.Water Services
  • 11Adequate off-carriageway parking during construction, no road parking. Prevent debris on public road, keep vehicles clean. Maintain neat site. Noise/dust emissions must not impair amenities beyond site boundary.Construction Management
  • 12Construction hours Mon-Fri 08.00-18.00, Sat 08.00-13.00. No Sundays/Bank Holidays. Deviation requires prior written approval.Construction Management

Source documents

Original council portal records and source PDFs where available.

Nearby precedent

Similar nearby applications linked to this planning decision.