Conditional grantDecided 29 May 2025Carlow County Council

2560022: To construct a dwelling house, domestic garage, waste water treatment system, percolation area, new bored well, new splayed entrance and associated site work

Cloghna, Milford, Carlow
DecisionConditional grant
Decided29 May 2025
Application typePERMISSION
Source documents6

Site

What is on file

0refusal reasons15conditions8nearby records

Decision details

Core application dates and identifiers from the public planning record.

Planning analysis

Refusal reasons and planning conditions extracted from the public decision file.

Refusal reasons

No refusal reason

No refusal reason is on record for this application yet.

Conditions

  • 1Development must be carried out in accordance with plans received 05/02/2025, as amended by FI received 08/05/2025.Compliance
  • 2Permission authorises only the development described in public notices and application plans.Compliance
  • 3Dwelling must be first occupied as permanent residence by applicants and immediate family, remaining so for 7 years. Section 47 agreement required prior to commencement. Statement of first occupation due within 2 months.Occupancy
  • 4External finishes for dwelling and garage (render, doors, rainwater goods, natural stone only) must match approved elevational drawings.Design Materials
  • 5Landscaping and boundary treatments retained per approved plan. New planting in first season, protected from damage, failures replaced within 5 years.Landscaping Boundary
  • 6Sight lines at entrance per approved layout plan and DMRB. Road opening licence required prior to commencement.Traffic Access
  • 7Height of site entrance wing walls and piers shall not exceed 1.2m.Other
  • 8Do not impair existing drainage. No surface water to public road or adjoining properties. All surface water collected and disposed to soakaways per BS 8301:1985 and BRE Digest 365. Only clean surface water diverted.Wastewater Drainage
  • 9Sign connection/self-lay agreement with Uisce Éireann prior to commencement. Comply with CDS Technical Documentation. Written approval for diversions. Adhere to separation distances per Codes of Practice.Water Services
  • 10WWT system and percolation area designed, constructed, operated and maintained per EPA Code of Practice (2021). Certificate of Compliance with as-constructed drawings required prior to occupation. Septic tank tested per I.S. EN 12566/S.R 66. Max 6 distribution pipes, liquid levelling device, foul air carbon vent filter, no surface water infiltration, grease trap installed.Wastewater Drainage
  • 11Provide off-carriageway parking for construction traffic. No parking on public road. Keep vehicles clean. Maintain litter-free site. Control noise/dust. No materials on public road without consent.Construction Management
  • 12Construction hours restricted to Mon-Fri 08.00-18.00 and Sat 08.00-13.00. No work on Sundays or Bank Holidays without prior written approval.Construction Management