2560155: A 10 year permission for a Battery Energy Storage system. The proposed development will comprise of the following; A Battery Energy Storage System with associated infrastructure including a new internal access road, approximately 50 metres in length to the permitted Garreenleen Solar Farm (Planning Ref. 22163); An approximately 90 metre 33kV double circuit underground cable grid connection to the permitted Bendinstown 110kV Substation (Planning Ref. ABP–313139), to be installed in an excavated trench including underground ducting; Modular office and welfare buildings; Six steel storage containers and all associated site development and reinstatement works. A Natura Impact Statement (NIS) has been prepared and is included with this planning application.
Within the townlands of Gilbertstown and Bendinstown, Co. Carlow, Ireland
DecisionRefused
Decided25 February 2026
Application typePERMISSION
Source documents5
Site
What is on file
0refusal reasons35conditions8nearby records
Decision details
Core application dates and identifiers from the public planning record.Planning analysis
Refusal reasons and planning conditions extracted from the public decision file.Refusal reasons
No refusal reason
No refusal reason is on record for this application yet.
Conditions
- 1Clean water diverted to suitably designed soakaways within site boundary.Wastewater Drainage
- 2Soakaways designed and installed per BRE Digest 365.Wastewater Drainage
- 3Dirty water treated in settlement ponds; no discharge to groundwater or Garreenleen Stream.Wastewater Drainage
- 4Dirty water from settlement/bioretention ponds diverted to soakaway.Wastewater Drainage
- 5Hydrocarbon interceptor installed on internal storm waterline prior to bioretention pond.Wastewater Drainage
- 6No surface water dispersed onto public roadway.Wastewater Drainage
- 710m riparian zone/buffer between site boundary and river bank.Environment Ecology
- 8Water quality monitoring schedule (pH, suspended solids, metals, nitrates, phosphates) during construction and 10-year operational phase.Environment Ecology
- 9Yearly water quality report submitted to Environment Dept for written agreement.Environment Ecology
- 10Measures implemented to prevent spread of Alien Invasive Species per NRA guidelines.Environment Ecology
- 11Construction managed per CEMP and RWMP, available for inspection on site.Construction Management
- 12Noise/vibration limited to BS 5228-1/2 standards.Construction Management
Source documents
Original council portal records and source PDFs where available.- Application fileApplication file on www.eplanning.ieSource portal
- Notification Of DecisionSource: carlowcoco.eplanning.ie / F0751e39-6430-448d-9a97-2abe5f2b5fc6.pdf / Document 147193Source PDF
- Chief Executives OrderSource: carlowcoco.eplanning.ie / 0195c32f-f2f2-441e-8667-89e97422e652.pdf / Document 147192Source PDF
- Planners ReportSource: carlowcoco.eplanning.ie / 2789a122-3a46-4a5f-bd51-2760e3399fd2.pdf / Document 149963Source PDF
- F I Request LetterSource: carlowcoco.eplanning.ie / 4ef85c18-ce70-4edb-afe1-3ecf6c43d3ca.pdf / Document 137285Source PDF
Nearby precedent
Similar nearby applications linked to this planning decision.- 20143A 10 year Planning Permission for a solar farm which will connect to the national grid on lands with a total area of circa 127 hectares, consisting of solar panels on ground mounted frames, 28 No. single storey electrical inverter/transformer stations and associated equipment container, security fencing, satellite communications pole, CCTV, upgrading to existing access tracks and new access tracks, temporary construction compounds, landscaping and all associated ancillary development works. Construction and operational access will be via entrances from the L-7111 and L-7112. The operational lifespan of the solar farm will be 35 years. A Natura Impact Statement (NIS) has been prepared and will be submitted to the Planning Authority with the application. / 0.5 km away / 16 July 2020Refused
- 2034For a single storey / part storey & half dwelling, septic tank and percolation area, new vehicular entrance, bored well and all associated site works / 0.7 km away / 23 March 2020Refused
- 2560255To construct a single storey dwelling house, domestic garage, new site entrance, proprietary treatment system and associated percolation area, to connect to public water main, all ancillary site works and services / 1.3 km away / 21 October 2025Refused
- 19486Development which consists of the construction of a new two storey detached dwelling, a new single storey detached garage, a new site entrance, a new wastewater treatment system and all ancillary site works / 1.9 km away / 17 February 2020Refused
- 23129PL18-296 for the restoration, part demolition and extension to the rear of an existing house, along with the installation of a new sewage treatment sewage, percolation area and all associated site and landscaping works / 2.0 km away / 14 September 2023Refused
- 2560301A temporary community training facility for a period of 5 years to include training pitches, parking facilities, new site entrance and exit system. Temporary portacabin type structures to provide, canteen, changing, w.c. facilities, referee and storage rooms. A self contained waste water treatment system, plus all associated site works and site enclosures to facilitate the development / 2.0 km away / 24 November 2025Refused
- 18349A) Planning permission to construct new agricultural shed, with associated holding tanks, yards and aprons. B) Permission to construct new dwelling house, domestic garage, install ETU with percolation area, and form new entrance with all associated site works / 2.1 km away / 24 October 2018Refused
- 2510Extension of duration for PL20/161 Construction of a two-storey dwelling, appropriate wastewater treatment system and percolation area, bored well, new entrance with splayed wing walls, single storey domestic garage and all ancillary site works and landscaping / 2.3 km away / 28 April 2025Refused