GrantedDecided 23 September 2025Carlow County Council

Bendinstown, (townland), Co Carlow

Planning application 2560220
DecisionConditional grant
Decided23 September 2025
Application typePERMISSION
Source documents5

Site

What is on file

0refusal reasons7conditions8nearby records

Proposed development

Application description published by Carlow County Council.
A 5-year permission for temporary development at Bendinstown (townland) in County Carlow. The development will consist of the installation of 3 no. single storey porta cabin units for use as office (2 no.) and storage space (1 no.), 6 no. car parking spaces and all associated site development works. The proposed development will serve the Garreenleen Solar Farm Development (as permitted under Carlow County Council Reference 20/143 / An Bord Pleanála Reference ABP-307891-20). The proposed operational development will be accessed via the L7112 local road via the entrance permitted under An Bord Pleanála Reference ABP-313139-22

Application and appeal history

Structured appeal stages, outcomes and source documents currently tied to this application.

No indexed appeal history

No structured appeal case is tied to this application. This means no appeal is indexed, not that an appeal is impossible.

Decision details

Core application dates and identifiers from the public planning record.

Planning analysis

Refusal reasons and planning conditions extracted from the public decision file.

Refusal reasons

No refusal reason on record

No refusal reason is on record for this application yet.

Conditions

  • 1Development must accord with plans received 31/07/2025, except where amended by conditions.Compliance
  • 2Permission valid for 5 years. Structures and carparking must be removed unless retention permission is granted beforehand. Permission limited to described development.Occupancy
  • 3External finish must be dark grey or green after weathering, or as agreed in writing.Design Materials
  • 4All works must comply with the final CEMP for the permitted 110kV substation/grid connection development (Ref: 313139-22).Construction Management
  • 5No impairment of existing drainage. No surface water discharge to public road or adjoining properties. All surface water to be collected and disposed of to on-site soakways/system per BRE Digest 365.Wastewater Drainage
  • 6Within 4 weeks of grant, consult Chief Fire Officer and strictly comply with recommendations.Traffic Access
  • 7€1,150 development contribution payable prior to commencement, with 5% p.a. interest from grant date (first 90 days discounted).Development Contribution

Planning a project near Bendinstown, (townland), Co Carlow?

Get a site risk brief with the local decision pattern and up to 80 detailed nearby comparables (40 refusals and 40 grants), including extracted reasons and source links. €29 incl. VAT, PDF by email.

Source documents

Original council portal records and source PDFs where available.

Nearby precedent

Similar nearby applications linked to this planning decision.