19621: To Retain and Maintain and, Continue to use established, temporary ancillary car parking areas associated with the development and operation of the Westpark Business Campus.
Westpark Business Campus, Shannon, Co. Clare
DecisionConditional grant
Decided23 September 2019
Application typePERMISSION
Source documents5
Site
What is on file
0refusal reasons0conditions8nearby records
Decision details
Core application dates and identifiers from the public planning record.Planning analysis
Refusal reasons and planning conditions extracted from the public decision file.Refusal reasons
No refusal reason
No refusal reason is on record for this application yet.
Conditions
No conditions
No conditions are on record for this application yet.
Source documents
Original council portal records and source PDFs where available.- Application fileApplication file on www.eplanning.ieSource portal
- Chief Executives OrderSource: clarecoco.eplanning.ie / 8b4a1d9a-c72d-40db-a53f-3f5e63c14c6e.PDF / Document 460451Source PDF
- Final GrantSource: clarecoco.eplanning.ie / 672767.PDF / Document 464936Source PDF
- Planners ReportSource: clarecoco.eplanning.ie / 1b29100a-aa7d-4123-8d54-98782514faa9.PDF / Document 460453Source PDF
- Planners ReportSource: clarecoco.eplanning.ie / Bf7e4475-d516-493e-8506-0511a57d07bb.PDF / Document 460454Source PDF
Nearby precedent
Similar nearby applications linked to this planning decision.- 19226For the further completion of construction of Westpark Business Campus with the construction of Block 6000 ( immediately south of existing Block 7000), for a building of five storeys ( with an additional area for mechanical plant on the roof area ) on the western portion of the proposed building facing into the centre of the Campus with a further two basement storeys linking into a proposed, ancillary, multi-deck car park ( MDCP) to the east of the site. Block 6000 will have a total gross floor area of 10,800 sqms for office use. The office building includes ancillary services including, secure internal, cycle parking with staff toilets and shower facilities. The ESB sub station and mechanical plant areas are contained within the office building. The proposed development will use existing drainage services in place within the overall Campus and the existing road network. The development includes all other ancillary site development works as required to complete the block / 0.1 km away / 21 May 2019Conditional grant
- 17583For the further completion of construction of Westpark Business Campus with the construction of Block 6000, ( immediately south of existing Block 7000), a mixed use, multi-storey block, similar to that granted under parent planning permission under Clare County Council PA Ref: P01-1066 and APB Ref: PL03.130244. Block 6000 will have a total gross internal area of 12,045 sqms with offices at upper floors 300-500 and data centre/light industrial / storage/ Research and Development uses at lower levels 100-200. The construction of an ancillary, multi-deck carpark (MDCP) located to the South of Block 4000 within the Campus. The MDCP will accommodate 580 spaces and will replace the existing, 101 at grade, split level, car park located to the South of Block 4000. The car park will also replace the 500 space MDCP located to the South of the Campus, granted by Clare County Council under Ref: P01-1066 and APB Ref PL.03-130244. The proposed development will use existing drainage services in place within the overall campus and the existing road network. The development includes, landscaping, ancillary parking adjacent to Block 6000, ESB Substation, service areas for goods vehicles. The application includes all other ancillary site development works as required to complete the block. / 0.2 km away / 20 September 2017Conditional grant
- 2560673For the following development on the site, consisting of; construction of a new 47 m2 bunded modular extension including an underground bund, A new external covered solvent storage area and bund, New concrete yard, New access landing, ramp, steps & railings, Removal of an existing LPG tank, and All ancillary site development works and services to facilitate the development including drainage, and utility connections. The proposed development site is controlled by an Industrial Emissions Licence (No. IEL P0020-03) authorised by the Environmental Protection Agency / 0.2 km away / 22 December 2025Conditional grant
- 2560279For amendments to previously granted planning permission (Planning Reference: P24/60414) at Ballymurtagh, Shannon Free Zone West, Shannon, Co. Clare. The amendments include: 1. Realignment of the northern site boundary to the north of permitted Building 01; 2. Repositioning and reduction in the floor area of Building 01 (from 3,905 m² to 3677 m²); 3. Increase in the floor area of Building 02 (from 6,010 m² to 6509m²). 4. Reduction in car parking spaces from previously permitted 286 spaces to 285 spaces. 5. Associated site works required to facilitate the above amendments, including adjustments to parking and landscaping, as necessary. The permitted development consists of the construction of two light industrial buildings with ancillary office space, yard areas, refuse stores, car parking, bicycle parking, ESB substations, a switch room, and associated site works. Permission is also sought to retain flexibility in the subdivision of the buildings as follows: Building 01 (Floor area amended from previously granted 3905m² to reduced area of 3,677 m²). Option A: (Amended floor area 3677m²) One unit with ancillary yard and refuse/plant store. Option B: (Amended Unit 01 floor area 1834.5m²), (Amended Unit 02 floor area 1842.5m²), Two units with individual yards and refuse/plant stores. Building 02 (Floor area amended from previously granted 6010m² to increased area of 6,509 m²) Option A: (Amended floor area 6509m²) One unit with ancillary yard and refuse store. Option B: (Amended Unit 01 floor area 4318.5m²), (Amended Unit 02 floor area 2190.5 m²), Two units with individual yards and refuse stores. Option C: (Amended Unit 01 floor area 2176m²), (Amended Unit 02 floor area 2142.4 m²) & (Amended Unit 03 floor area 2190.6 m²), Three units with individual yards and refuse stores. / 0.3 km away / 10 July 2025Conditional grant
- 2460414For development which consists of the construction of two light industrial facilities with ancillary office space, yard spaces, refuse stores with carparking, bicycle parking, ESB substations, switch room and associated site works. Permission is sought for Building 01 the industrial and office facility to have the flexibility to be subdivided as follows: Option A: One No. Unit (Area: 3905m²) with Ancillary Yard and Refuse/Plant Store. Option B: Two No. Units (Units 01 Area: 1953 m²) (Unit 02 Area: 1952m²) with Ancillary Yards and Two No. Refuse/Plant Stores. Permission is sought for Building 02 the industrial and office facility to have the flexibility to be subdivided as follows: Option A: One No. Unit (Area: 6010m²) with Ancillary Yard and Refuse Store. Option B: Two No. Units (Units 01 Area: 3985m²) (Unit 02 Area: 2025m²) with Two No. Ancillary Yards and Two No. Refuse Stores. Option C: Three No. Units (Area Unit 01: 2025m² / Area Unit 02: 1960m² / Area Unit 03: 2025m²) with Three No. Ancillary Yards and Three No. Refuse Stores. Other works include the provision of 286 No. carparking spaces which include accessible spaces, EV charging areas and set-down areas with vehicular and HGV access points to the perimeter of site. Secure bicycle parking spaces, refuse stores with roof level and site level external service areas, roof and ground mounted photo voltaic panels, building signage with all ancillary landscaping and associated site works and services. The planning application is accompanied by a Natura Impact Statement. / 0.3 km away / 27 March 2025Conditional grant
- 21738For the following: (1) Demolition of an existing bungalow (2) Construct a new ESB Substation and (3) Construct mixed use industrial units with office accommodation for industrial, light industrial, storage, warehouse and logistic usage including ancillary siteworks / 0.3 km away / 01 April 2022Conditional grant
- 24337To make amendments to a previous granted planning Ref No. P21-738 which included (1) Demolition of an existing bungalow (2) Construct a new ESB Substation and (3) Construct mixed use industrial units with office accommodation for industrial, light industrial, storage, warehouse and logistic usage including ancillary siteworks all at Western Business Park, Caherteige and Drumgeely Shannon, Co Clare. The amendments to the previous granted planning include the following: (a) relocating the ESB substation from the eastern elevation of Unit 7 to the western elevation of Unit 6, (b) revising the internal layout and elevation of Unit 6 and raising the height of Unit 6 from 16.4m OD to 18.4m / 0.3 km away / 17 April 2025Conditional grant
- 17125To construct an industrial unit with office accommodation for industrial, warehouse and logistic usage, including ancillary site development works / 0.3 km away / 16 June 2017Conditional grant