19869: For the erection of a permanent health and safety sign including all ancillary site works, at the entrance to Glenmore Wind Farm
Boolynaknockaun, Kilmaley, Co Clare
DecisionConditional grant
Decided16 December 2019
Application typePERMISSION
Source documents5
Site
What is on file
0refusal reasons0conditions8nearby records
Decision details
Core application dates and identifiers from the public planning record.Planning analysis
Refusal reasons and planning conditions extracted from the public decision file.Refusal reasons
No refusal reason on record
Documents are indexed. Reason extraction for Clare has not started yet.
Conditions
No conditions
No conditions are on record for this application yet.
Source documents
Original council portal records and source PDFs where available.- Application fileApplication file on www.eplanning.ieSource portal
- Chief Executives OrderSource: clarecoco.eplanning.ie / 673399.PDF / Document 474676Source PDF
- Final GrantSource: clarecoco.eplanning.ie / 674058.PDF / Document 481610Source PDF
- Planners ReportSource: clarecoco.eplanning.ie / 673400.PDF / Document 474678Source PDF
- Planners ReportSource: clarecoco.eplanning.ie / 673401.PDF / Document 474682Source PDF
Nearby precedent
Similar nearby applications linked to this planning decision.- 2360414For development which will consist of a 10 year planning permission for the construction and operation of battery arrays (240 number units, each 1.87m2 by c. 2.32m tall), a control building with gross floor area 140m2 by 6.40m tall, 3 number 12MVA transformers (c. 3.5m tall), 1 number 2.5MVA transformer (c. 2.5m tall) and inverters (24 number units, each 1.85m2 by c. 2.22m tall. The development will include for ancillary infrastructure including security fencing, lighting, CCTV, internal access roads and drainage. The development will have a 35 year operational lifetime. The overall development site is ca. 1.42 hectares (ha) / 1.0 km away / 23 November 2023Granted
- 18555For development which will consist of the installation of battery arrays located within container units (18 number units, each 30m2 by c. 2.6m tall) a control building (c 160.5m2 by c.6.4m tall) and transformer (c. 5m tall). The development will include for ancillary infrastructure including security fencing, lighting, CCTV, Internal access roads & drainage. The overall development site is c.1.4Ha. / 1.0 km away / 30 August 2018Granted
- 23328Is sought for the continued operation of the existing Booltiagh Wind Farm as permitted by An Bord Pleanala Ref: 03.120616 (Clare County Council Pl. Ref: 00/567) for a further period of 10 years from the date of the expiry of the current planning permission (30th September 2025) per Condition no. 2 of the consent issued and for the decommissioning of the wind farm at the end of that further period. The proposed development development does not comprise any modifications to the existing operational wind farm. The proposed development comprises: a) 12 no. existing GE Energy 1.5 Megawatt (MW) wind turbines with a maximum overall blade tip height of 90 metres (m) including hardstands; b) Existing site access tracks and car parking spaces; c) all existing associated underground electrical and communications cabling connecting the turbines to onsite substation (onsite substation consented under ABP 03.120616, amended and made permanent under Pl. Ref: 11/34, and amended under ABP 03.245273; d) Existing gated site entrance from Creegh - Kilmaley local road; e) Existing site drainage; f) All existing ancillary infrastructure, associated site fencing and signage; and g) Implementation of a decommissioning plan. All elements of the wind farm are pre-existing and it is not proposed to make any alterations to the current site layout, wind turbines or associated infrastructure as part of this application. an Environmental Impact Assessment Report (EIAR) accompanies the planning application / 1.4 km away / 10 July 2024Granted
- 2273Of alterations and changes to dwelling house and septic tank, as constructed, from grant of permission reference P8/26445 / 2.3 km away / 29 March 2022Granted
- 23290For development at lands at Crossmore County Clare in the townlands of Furroor, Illaunatoo or Sorrelisand, Boolynakockaun and Booltiagh. The development will consist of: 1. Amendment to item (1) of Permitted Development Pl. Ref: 21/1057 to install a 38kV electrical connection over a total length of approximately 11km, from the permitted Crossmore Wind Farm (Pl. Ref: 09/123, as extended under Pl. Ref: 19/388 and altered by Pl. Ref: 20/284) to the entrance to the existing Booltiagh 110kV electrical substation. This amended connection will consist of: a. Revision to site boundaries as permitted under Pl. Ref: 21/1057; b. Removal of permitted overhead line from permitted polesets north of Local Road L2084 (previously numbered polesets 1-40 consented under Pl. Ref: 21/1057) for a distance of circa 4km and its replacement with c. 6.5km of underground electrical cabling along unnamed Local Roads. c. Relocation of permitted poleset number 40 (consented under Pl. Ref: 21/1057) 7m (meters) south. Redesign of poleset number 40 from double (as permitted under Pl. Ref: 21/1057) to triple (termination) poleset. The entirety of the grid connection from Crossmore Wind Farm to the existing Booltiagh 110kV electrical substation will therefore comprise c. 5.5km of overhead line (poleset numbers 41-93 conscented under Pl. Ref: 21/1057) c. 6.5km of underground cable (proposed under subject application) 2. Site Drainage 3. All associated site development and ancillary works. The application will be accompanied by a Natura Impact Statement (NIS) / 2.7 km away / 11 July 2023Granted
- 18517For development which will consist of: carry out extensions and alterations to existing habitable dwelling house including (a) RETAIN rear part of existing house and removed remaining structure (b) construct extension and alterations to remaining part of existing dwelling house (c) new connected garage (d) remove existing out buildings as shown (e) connect to existing services and associated site works. / 2.8 km away / 18 December 2018Granted
- 19299For the construction of a battery storage compound adjacent to an existing electricity substation, with new palisade fencing, bunded concrete plinths, up to 4 No. storage units and associated equipment, transformers and all ancillary site works. A Natura Impact Statement ( NIS ) has been prepared and included as part of this application / 2.9 km away / 09 September 2019Granted
- 19868For the erection of a permanent health and safety sign including all ancillary site works at the entrance to Glenmore Wind Farm / 3.0 km away / 16 December 2019Granted