GrantedDecided 02 November 2023Dublin City Council

Lands within the Poolbeg Generating Station complex, Pigeon House Road, Dublin 4, D04 XD82

Planning application 3137/23
DecisionGrant permission
Decided02 November 2023
Application typePermission
Source documentsPending

Site

What is on file

0refusal reasons0conditions8nearby records

Proposed development

Application description published by Dublin City Council.
The proposed development will consist of: 1. Demolition of the existing Babcock Store building; 1 No. Hydrogen Tank; the temporary Control Building; 1 No. Water Tank within the National Oil Reserves Agency (NORA) Bunded Area 2. Construction/ installation of an OCGT generating unit and associated plant and equipment, comprising the following main components: - An exhaust stack approx. 40m in height (approx. 8m diameter and 40m H) - Gas Turbine Air Intake (approx. 24m L x 18m W x 26m H) - Generator Enclosure (approx. 24m L x 18m W x 14.5m H) - Gas turbine enclosure including Gas Turbine auxiliaries and loading / rotor turning area (approx. 53m L x 15mW x 26m H) - Exhaust Diffuser (approx. 14.5m L x 10.4m W x 10.5m H) - Gas Turbine Power Control and Electrical Control & Instrumentation (C&I) Module (approx. 24m L x 18m W x 10m H) - 9No. Fin Fan Coolers (approx.27m L x 19m W x 8m H) - Main Transformer (approx. 12.2m L x 7.5m W x 9.3m H), including - 17.5m x 18m bund; and -3No 12m high Blast Walls - Auxiliary Transformer (approx.4.9m L x4.7m W x 6.9m H) - 6.8m x 7.5m bund; and - 2No 12m high Blast Walls - Demineralised Water Treatment Plant (approx.20m L x 10m W x 5.4m H) - Demineralised Water Tank (approx.22.3m diameter and 14.6m H) - Raw/Fire Water Tank (approx.15.2m diameter and 14.6m H) - 8,000m3 Distillate Fuel (Secondary Oil Tank (approx.27.2m diameter and 17.6m H) - Including 8No 1.7m high Baffle Walls surrounding the tank - Fuel Oil Forwarding Pump (approx.8.9m L x 7.8m W x 2.2m H) - Fire Fighting Pumphouse (approx. 12m L x 7m W x 5.4m H) - 1 No. <1 MW thermal output emergency diesel generator 250KWe (approx. 10m L x 4m W x 5m H) - Generator Circuit Breaker (approx.8.8m L x5.1m W x 4m H) - 2 No. Water (replacement) Firewater Tanks for NORA (approx.13m diameter and 14.6m H) - 3-Bay 220kV Indoor Switchgear Building (approx.30m L x 18m W x 18m H) and 3 No. bolted connections (approx.12.5m L x 15m W x 15m H) - Gas Conditioning Compound (approx. 42.2m L x 11.4m W x 3.6m H) which includes: - Gas Compressor and Auxiliaries Building (approx. 24m L x 7.5m W x 5m H) - Gas Compressor Reducing Building (approx. 8m L x 6m W x 6m H); and - Gas Compressor Cooler (approx. 7m L x 4m W x 5m H) - Hydrogen Storage Compound (approx. 6m L x 3.5m W x 3m H) - Continuous Emissions Monitoring System (CEMS) (approx. 3.5m L x 2.5m W x 5m H) - CCGT Stores Building (approx. 15m Lx 14m W x 10m H) - Workshop, Stores and Administration Building (approx. 23m L x 22m W x 15m H) 3. Connection to the existing gas Above Ground Installation (AGI); 4. Connection to the National Grid via the existing 220kV Poolbeg Substation; and 5. All associated works to facilitate the development (e.g. temporary construction compound, perimeter fencing, blast and baffle walls, above-ground pipe racks, underground cables, a new lighting arrangement, lightning and telecommunication masts, parking and surface water drainage network including a new stormwater outfall. All works will take place within the grounds of the ESB Poolbeg Generating station complex. The development consists of an activity for which an Industrial Emissions Licence is required. An Environmental Impact Assessment Report (EIAR) which compiles with the European Union (Planning and Development) (Environmental Impact Assessment) Regulations 2018 (S.I 296 of 2018 and a Natura Impact Statement (NIS) will be submitted to the Planning Authority with the application.

Application and appeal history

Structured appeal stages, outcomes and source documents currently tied to this application.

No indexed appeal history

No structured appeal case is tied to this application. This means no appeal is indexed, not that an appeal is impossible.

Decision details

Core application dates and identifiers from the public planning record.

Planning analysis

Refusal reasons and planning conditions extracted from the public decision file.

Refusal reasons

No refusal reason on record

Documents are indexed. Reason extraction for Dublin City is in progress.

Conditions

No conditions

No conditions are on record for this application yet.

Planning a project near Lands within the Poolbeg Generating Station complex, Pigeon House Road, Dublin 4, D04 XD82?

Get a site risk brief with the local decision pattern and up to 80 detailed nearby comparables (40 refusals and 40 grants), including extracted reasons and source links. €39 incl. VAT, PDF by email.Searching the records is free. A one-off brief for this site is €39, and Pro at €19/month adds full document access and the planning AI for people tracking more than one site.

Source documents

Original council portal records and source PDFs where available.

Source link pending

This application was published at source, but the document inventory has not been bound yet.

Nearby precedent

Similar nearby applications linked to this planning decision.
Get up to 80 detailed nearby comparables in a site risk brief →