D19A/0457/E: Permission for development. The proposal consists of the construction of 3 no. office buildings ('N1'; 'N2' and 'N3') ranging in height from 6 to 8 storeys, over lower ground floor and basement level. The total GFA of office floorspace proposed is c.47,216 sq.m. The proposal includes plant areas at basement, lower ground and roof level. The proposal includes a wellness pavilion building (GFA of c. 148 sq.m), public open space, sunken gardens, shared entrance plaza, upper level / roof terraces to buildings and all associated works. The proposal includes 474 no. car parking spaces at basement and lower ground floor level. 474 no. cycle parking spaces are proposed at lower ground and surface level. The associated site and infrastructural works include site access and internal roads, entrance ramp to car park, cycle path, footpaths, 4 no. ESB substations, bin stores, plant rooms, foul water drainage, surface water drainage including attenuation tank watermains including water storage tank, utilities, hard and soft landscaping, public lighting, boundary treatments and all ancillary works on an application site area of c. 1.97 hectares.
Central Park (Block N Site), Leopardstown Road, Dublin 18
DecisionGrant extension of duration of perm.
Decided17 July 2025
Application typeExtension Of Duration Of Permission
Source documents3
Site
What is on file
0refusal reasons0conditions8nearby records
Decision details
Core application dates and identifiers from the public planning record.Planning analysis
Refusal reasons and planning conditions extracted from the public decision file.Refusal reasons
No refusal reason on record
Documents are indexed. Reason extraction for Dún Laoghaire–Rathdown is in progress.
Conditions
No conditions
No conditions are on record for this application yet.
Planning a project near Central Park (Block N Site), Leopardstown Road, Dublin 18?
Get the precedent report for this site: every grant and refusal within 5 km, and the planners' reasons. €49 incl. VAT, PDF by email.Source documents
Original council portal records and source PDFs where available.- Planners ReportSource: planningapi.agileapplications.ie / Report D19A0457E.pdf / Document 5503188Source PDF
- ReportsSource: planningapi.agileapplications.ie / 250530082450-1004.pdf / Document 5494946Source PDF
- ReportsSource: planningapi.agileapplications.ie / 250530082450-1006.pdf / Document 5494948Source PDF
Nearby precedent
Similar nearby applications linked to this planning decision.- D19A/0457Permission for development. The proposal consists of the construction of 3 no. office buildings ('N1'; 'N2' and 'N3') ranging in height from 6 to 8 storeys, over lower ground floor and basement level. The total GFA of office floorspace proposed is c.47,216 sq.m. The proposal includes plant areas at basement, lower ground and roof level. The proposal includes a wellness pavilion building (GFA of c. 148 sq.m), public open space, sunken gardens, shared entrance plaza, upper level / roof terraces to buildings and all associated works. The proposal includes 474 no. car parking spaces at basement and lower ground floor level. 474 no. cycle parking spaces are proposed at lower ground and surface level. The associated site and infrastructural works include site access and internal roads, entrance ramp to car park, cycle path, footpaths, 4 no. ESB substations, bin stores, plant rooms, foul water drainage, surface water drainage including attenuation tank watermains including water storage tank, utilities, hard and soft landscaping, public lighting, boundary treatments and all ancillary works on an application site area of c. 1.97 hectares. / 0.0 km away / 21 January 2020Granted
- D07A/1626Transfer of the existing 150 sq.m. temporary creche building to a new site withi / 0.1 km away / 30 January 2008Granted
- D05A/1137110 kV electrical transformer station / 0.1 km away / 26 October 2005Granted
- D16A/0159Permission: Block 1 as permitted under Reg. Ref. D98A/0886 is a 7,639 sqm / 0.1 km away / 14 October 2016Granted
- D08A/0421The renewal of planning permission for a two storey portacabin building for use / 0.1 km away / 06 June 2008Granted
- D09A/0398Planning permission sought for development which will consist of the installatio / 0.1 km away / 16 September 2009Granted
- D15A/0370Permission: Block K was permitted under Reg. Ref. D04A/0994. The proposed / 0.1 km away / 24 July 2015Granted
- D15A/0369Permission: Block K was permitted under Reg. Ref. D04A/0994. The proposed / 0.1 km away / 23 July 2015Granted