F20A/0668: A proposed development comprising the taking of a ‘relevant action’ only within the meaning of Section 34C of the Planning and Development Act 2000, as amended, at Dublin Airport, Co. Dublin, in the townlands of Collinstown, Toberbunny, Commons, Cloghran, Corballis, Coultry, Portmellick, Harristown, Shanganhill, Sandyhill, Huntstown, Pickardstown, Dunbro, Millhead, Kingstown, Barberstown, Forrest Great, Forrest Little and Rock on a site of c. 580 ha. The proposed relevant action relates to the night-time use of the runway system at Dublin Airport. It involves the amendment of the operating restriction set out in condition no. 3(d) and the replacement of the operating restriction in condition no. 5 of the North Runway Planning Permission (Fingal County Council Reg. Ref. No. F04A/1755; ABP Ref. No. PL06F.217429 as amended by Fingal County Council F19A/0023, ABP Ref. No. ABP-305289-19), as well as proposing new noise mitigation measures. Conditions no. 3(d) and 5 have not yet come into effect or operation, as the construction of the North Runway on foot of the North Runway Planning Permission is ongoing. The proposed relevant action, if permitted, would be to remove the numerical cap on the number of flights permitted between the hours of 11pm and 7am daily that is due to come into effect in accordance with the North Runway Planning Permission and to replace it with an annual night-time noise quota between the hours of 11.30pm and 6am and also to allow flights to take off from and/or land on the North Runway (Runway 10L 28R) for an additional 2 hours i.e. 2300 hrs to 2400hrs and 0600 hrs to 0700 hrs. Overall, this would allow for an increase in the number of flights taking off and/or landing at Dublin Airport between 2300 hrs and 0700 hrs over and above the number stipulated in condition no. 5 of the North Runway Planning Permission, in accordance with the annual night time noise quota. The relevant action pursuant to Section 34C (1) (a) is: To amend condition no. 3(d) of the North Runway Planning Permission (Fingal County Council Reg. Ref. No. F04A/1755; ABP Ref. No.: PL06F.217429 as amended by Fingal County Council F19A/0023, ABP Ref. No. ABP-305289-19). Condition 3(d) and the exceptions at the end of Condition 3 state the following: ‘3(d). Runway 10L-28R shall not be used for take-off or landing between 2300 hours and 0700 hours except in cases of safety, maintenance considerations, exceptional air traffic conditions, adverse weather, technical faults in air traffic control systems or declared emergencies at other airports.’ Permission is being sought to amend the above condition so that it reads: ‘Runway 10L-28R shall not be used for take-off or landing between 0000 hours and 0559 hours except in cases of safety, maintenance considerations, exceptional air traffic conditions, adverse weather, technical faults in air traffic control systems or declared emergencies at other airports or where Runway 10L-28R length is required for a specific aircraft type.’ The net effect of the proposed change, if permitted, would change the normal operating hours of the North Runway from the 0700hrs to 2300 hrs to 0600 hrs to 0000 hrs. The relevant action also is: To replace condition no. 5 of the North Runway Planning Permission (Fingal County Council Reg. Ref. No. F04A/1755; ABP Ref. No.: PL06F.217429 as amended by Fingal County Council F19A/0023, ABP Ref. No. ABP-305289-19) which provides as follows: 5. On completion of construction of the runway hereby permitted, the average number of night time aircraft movements at the airport shall not exceed 65/night (between 2300 hours and 0700 hours) when measured over the 92 day modelling period as set out in the reply to the further information request received by An Bord Pleanála on the 5th day of March, 2007. Reason: To control the frequency of night flights at the airport so as to protect residential amenity having regard to the information submitted concerning future night time use of the existing parallel runway'. With the following: A noise quota system is proposed for night time noise at the airport. The airport shall be subject to an annual noise quota of 7990 between the hours of 2330hrs and 0600hrs. In addition to the proposed night time noise quota, the relevant action also proposes the following noise mitigation measures: - A noise insulation grant scheme for eligible dwellings within specific night noise contours; - A detailed Noise Monitoring Framework to monitor the noise performance with results to be reported annually to the Aircraft Noise Competent Authority (ANCA), in compliance with the Aircraft Noise (Dublin Airport) Regulation Act 2019. The proposed relevant action does not seek any amendment of conditions of the North Runway Planning Permission governing the general operation of the runway system (i.e., conditions which are not specific to nighttime use, namely conditions no. 3 (a), 3(b), 3(c) and 4 of the North Runway Planning Permission) or any amendment of permitted annual passenger capacity of the Terminals at Dublin Airport. Condition no. 3 of the Terminal 2 Planning Permission (Fingal County Council Reg. Ref. No. F04A/1755; ABP Ref. No. PL06F.220670) and condition no. 2 of the Terminal 1 Extension Planning Permission (Fingal County Council Reg. Ref. No. F06A/1843; ABP Ref. No. PL06F.223469) provide that the combined capacity of Terminal 1 and Terminal 2 together shall not exceed 32 million passengers per annum. The planning application will be subject to an assessment by the Aircraft Noise Competent Authority in accordance with the Aircraft Noise (Dublin Airport) Regulations Act 2019 and Regulation (EU) No 598/2014. The planning application is accompanied by information provided for the purposes of such assessment. An Environmental Impact Assessment Report will be submitted with the planning application. The planning application and Environmental Impact Assessment Report may be inspected or purchased at a fee not exceeding the reasonable cost of making a copy, at the offices of the Planning Authority during its public opening hours of 9.30 - 16.30 (Monday – Friday) at Fingal County Council, Fingal County Hall, Main Street, Swords, Fingal, Co. Dublin. AI received 13/09/21 AI deemed significant Revised public notices(SAI) received 21/09/21
Dublin Airport, Co. Dublin.
DecisionGrant permission
Decided08 August 2022
Application typePermission
Source documents252
Site
What is on file
0refusal reasons0conditions8nearby records
Decision details
Core application dates and identifiers from the public planning record.Planning analysis
Refusal reasons and planning conditions extracted from the public decision file.Refusal reasons
No refusal reason on record
Documents are indexed. Reason extraction for Fingal has not started yet.
Conditions
No conditions
No conditions are on record for this application yet.
Source documents
Original council portal records and source PDFs where available.- Application fileApplication file on planning.agileapplications.ieSource portal
- Notification Of DecisionSource: planningapi.agileapplications.ie / 05907B5D658F11EB8624005056926D4A.docx / Document 700744Source PDF
- Notification Of DecisionSource: planningapi.agileapplications.ie / 2AE5B832729E11EBBF2F3464A927EB6F.tif / Document 706067Source PDF
- Notification Of DecisionSource: planningapi.agileapplications.ie / 6B9947FB750111EBA1E74EEBBDB391AD.docx / Document 713196Source PDF
- Notification Of DecisionSource: planningapi.agileapplications.ie / 938F48C8658F11EB8624005056926D4A.docx / Document 719634Source PDF
- Notification Of DecisionSource: planningapi.agileapplications.ie / C6F0C6D4659111EB8624005056926D4A.docx / Document 724686Source PDF
- Notification Of DecisionSource: planningapi.agileapplications.ie / C0FF1EDD624211EB86240050569277E6.docx / Document 725699Source PDF
- Notification Of DecisionSource: planningapi.agileapplications.ie / F8655E7D220A11EC863B005056929533.docx / Document 731156Source PDF
- Notification Of DecisionSource: planningapi.agileapplications.ie / 2BCACF6D659511EB8624005056926D4A.docx / Document 732940Source PDF
- Notification Of DecisionSource: planningapi.agileapplications.ie / 4F4D0966622611EB862400505692F02D.docx / Document 734893Source PDF
- Notification Of DecisionSource: planningapi.agileapplications.ie / 87266C61F14511EBB6053464A927EB6F.tif / Document 737087Source PDF
- Notification Of DecisionSource: planningapi.agileapplications.ie / C7DAE0EF380011EC924784C5A68ABD3E.docx / Document 739654Source PDF
- Notification Of DecisionSource: planningapi.agileapplications.ie / B08E19071E4411ED8674005056925056.docx / Document 763328Source PDF
- Notification Of DecisionSource: planningapi.agileapplications.ie / DAC17B1217CD11EDB7039C7BEFBB54FD.tif / Document 768405Source PDF
- Chief Executives OrderSource: planningapi.agileapplications.ie / F20A_0668_Noting_Order.pdf / Document 1147048Source PDF
- Chief Executives OrderSource: planningapi.agileapplications.ie / 87266C64F14511EBB6053464A927EB6F.tif / Document 716693Source PDF
- Chief Executives OrderSource: planningapi.agileapplications.ie / 2AE5B835729E11EBBF2F3464A927EB6F.tif / Document 732813Source PDF
- Chief Executives OrderSource: planningapi.agileapplications.ie / E6ADE33117EE11EDB7039C7BEFBB54FD.tif / Document 768911Source PDF
- ReportsSource: planningapi.agileapplications.ie / 02FE490A451311EB85F2005056926A5C.pdf / Document 665178Source PDF
- ReportsSource: planningapi.agileapplications.ie / 1745C01E451311EB85F2005056926A5C.pdf / Document 667126Source PDF
- ReportsSource: planningapi.agileapplications.ie / 23FF1973451311EB85F2005056926A5C.pdf / Document 668587Source PDF
- ReportsSource: planningapi.agileapplications.ie / 30F48460451311EB85F2005056926A5C.pdf / Document 669824Source PDF
- ReportsSource: planningapi.agileapplications.ie / 37885B25451311EB85F2005056926A5C.pdf / Document 670515Source PDF
- ReportsSource: planningapi.agileapplications.ie / 3E35F9E3451311EB85F2005056926A5C.pdf / Document 693071Source PDF
- ReportsSource: planningapi.agileapplications.ie / 522BBD5A451311EB85F2005056926A5C.pdf / Document 693698Source PDF
- ReportsSource: planningapi.agileapplications.ie / 01C0201FCCEC11EB80E6D8126595A214.pdf / Document 700175Source PDF
- ReportsSource: planningapi.agileapplications.ie / 01EDCFE4624311EB86240050569277E6.pdf / Document 700187Source PDF
- ReportsSource: planningapi.agileapplications.ie / 0763D05B389A11EC85EF4CEBBDB3918C.pdf / Document 700878Source PDF
- ReportsSource: planningapi.agileapplications.ie / 090D4A50211411EC863B00505692C209.pdf / Document 700999Source PDF
- ReportsSource: planningapi.agileapplications.ie / 0825551DF50311EB863700505692DF5E.pdf / Document 701167Source PDF
- ReportsSource: planningapi.agileapplications.ie / 0825551EF50311EB863700505692DF5E.pdf / Document 701168Source PDF
- ReportsSource: planningapi.agileapplications.ie / 0825551FF50311EB863700505692DF5E.pdf / Document 701169Source PDF
- ReportsSource: planningapi.agileapplications.ie / 08255523F50311EB863700505692DF5E.pdf / Document 701170Source PDF
- ReportsSource: planningapi.agileapplications.ie / 08255524F50311EB863700505692DF5E.pdf / Document 701171Source PDF
- ReportsSource: planningapi.agileapplications.ie / 08255520F50311EB863700505692DF5E.pdf / Document 701280Source PDF
- ReportsSource: planningapi.agileapplications.ie / 08255521F50311EB863700505692DF5E.pdf / Document 701281Source PDF
- ReportsSource: planningapi.agileapplications.ie / 08255522F50311EB863700505692DF5E.pdf / Document 701282Source PDF
- ReportsSource: planningapi.agileapplications.ie / 18419BF61AE211EC863B00505692F3B2.pdf / Document 703087Source PDF
- ReportsSource: planningapi.agileapplications.ie / 01C0201DCCEC11EB80E6D8126595A214.pdf / Document 703571Source PDF
- ReportsSource: planningapi.agileapplications.ie / 01C0201ECCEC11EB80E6D8126595A214.xlsx / Document 703572Source PDF
- ReportsSource: planningapi.agileapplications.ie / 25412458C93811EB862E00505692966A.xlsx / Document 704684Source PDF
- ReportsSource: planningapi.agileapplications.ie / 2B168CDA713F11EB862500505692A2FE.docx / Document 705396Source PDF
- ReportsSource: planningapi.agileapplications.ie / 35B83698220211EC863B005056929533.docx / Document 706905Source PDF
- ReportsSource: planningapi.agileapplications.ie / 3626FD6A7CFC11EB8625005056924457.pdf / Document 706912Source PDF
- ReportsSource: planningapi.agileapplications.ie / 3BAD8A3A1D4211EC863B00505692E046.docx / Document 707811Source PDF
- ReportsSource: planningapi.agileapplications.ie / 460362BD574111EC86104CEBBDB3918C.docx / Document 708736Source PDF
- ReportsSource: planningapi.agileapplications.ie / 082554FEF50311EB863700505692DF5E.pdf / Document 709235Source PDF
- ReportsSource: planningapi.agileapplications.ie / 4C272DAF658A11EB8624005056926D4A.pdf / Document 709529Source PDF
- ReportsSource: planningapi.agileapplications.ie / 4C272DB1658A11EB8624005056926D4A.pdf / Document 709717Source PDF
- ReportsSource: planningapi.agileapplications.ie / 4C272DB0658A11EB8624005056926D4A.pdf / Document 710202Source PDF
- ReportsSource: planningapi.agileapplications.ie / 090D4A4F211411EC863B00505692C209.pdf / Document 710337Source PDF
- ReportsSource: planningapi.agileapplications.ie / 5539F665365311EC864000505692A522.pdf / Document 710569Source PDF
- ReportsSource: planningapi.agileapplications.ie / 60378759206811EC863B0050569277E6.pdf / Document 711971Source PDF
- ReportsSource: planningapi.agileapplications.ie / 62E5254D300311EC8640005056925056.docx / Document 712011Source PDF
- ReportsSource: planningapi.agileapplications.ie / 62E52531300311EC8640005056925056.docx / Document 712274Source PDF
- ReportsSource: planningapi.agileapplications.ie / 637370A56C5311EBA1DB4CEBBDB391AE.pdf / Document 712470Source PDF
- ReportsSource: planningapi.agileapplications.ie / 637370A76C5311EBA1DB4CEBBDB391AE.pdf / Document 712471Source PDF
- ReportsSource: planningapi.agileapplications.ie / 637370AB6C5311EBA1DB4CEBBDB391AE.pdf / Document 712472Source PDF
- ReportsSource: planningapi.agileapplications.ie / 66DD7FD23D5311EC8640005056926BDB.docx / Document 712678Source PDF
- ReportsSource: planningapi.agileapplications.ie / 637370A96C5311EBA1DB4CEBBDB391AE.pdf / Document 713330Source PDF
- ReportsSource: planningapi.agileapplications.ie / 71497C70564811EB861D00505692E046.pdf / Document 713913Source PDF
- ReportsSource: planningapi.agileapplications.ie / 6AF99778502911EB861D00505692E046.docx / Document 714036Source PDF
- ReportsSource: planningapi.agileapplications.ie / 744DFCF9648211EB8624005056923C73.docx / Document 715108Source PDF
- ReportsSource: planningapi.agileapplications.ie / 757A62D8622211EB862400505692F02D.pdf / Document 715389Source PDF
- ReportsSource: planningapi.agileapplications.ie / 7F0931EDDB1B11EB80F6D8126595A214.pdf / Document 716145Source PDF
- ReportsSource: planningapi.agileapplications.ie / 845CB29946DB11ECA3344CEBBDB391AE.pdf / Document 716250Source PDF
- ReportsSource: planningapi.agileapplications.ie / 7F0931ECDB1B11EB80F6D8126595A214.pdf / Document 716480Source PDF
- ReportsSource: planningapi.agileapplications.ie / 8D612528327711EC8640005056929533.pdf / Document 717859Source PDF
- ReportsSource: planningapi.agileapplications.ie / 99C40381280E11EC864000505692F3B2.docx / Document 720477Source PDF
- ReportsSource: planningapi.agileapplications.ie / 18419BF31AE211EC863B00505692F3B2.pdf / Document 721928Source PDF
- ReportsSource: planningapi.agileapplications.ie / B4B04A4D1C6611EC863B00505692BE53.pdf / Document 722994Source PDF
- ReportsSource: planningapi.agileapplications.ie / C365F241777F11EB862500505692A2FE.pdf / Document 724237Source PDF
- ReportsSource: planningapi.agileapplications.ie / C365F23F777F11EB862500505692A2FE.pdf / Document 726038Source PDF
- ReportsSource: planningapi.agileapplications.ie / D6A6C5250A3311EC811BD8126595A214.xlsx / Document 726526Source PDF
- ReportsSource: planningapi.agileapplications.ie / D6A6C5280A3311EC811BD8126595A214.pdf / Document 726527Source PDF
- ReportsSource: planningapi.agileapplications.ie / D6A6C5290A3311EC811BD8126595A214.pdf / Document 726528Source PDF
- ReportsSource: planningapi.agileapplications.ie / D99B812F571E11EB861D00505692B757.docx / Document 728418Source PDF
- ReportsSource: planningapi.agileapplications.ie / E6C779BED37211EB80EDD8126595A214.pdf / Document 728454Source PDF
- ReportsSource: planningapi.agileapplications.ie / D6A6C5260A3311EC811BD8126595A214.pdf / Document 728873Source PDF
- ReportsSource: planningapi.agileapplications.ie / D6A6C5270A3311EC811BD8126595A214.pdf / Document 728874Source PDF
- ReportsSource: planningapi.agileapplications.ie / 25412456C93811EB862E00505692966A.pdf / Document 729307Source PDF
- ReportsSource: planningapi.agileapplications.ie / 25412457C93811EB862E00505692966A.pdf / Document 729308Source PDF
- ReportsSource: planningapi.agileapplications.ie / E6C779BFD37211EB80EDD8126595A214.pdf / Document 731125Source PDF
- ReportsSource: planningapi.agileapplications.ie / 50D0724B54EE11EB861D00505692F3B2.docx / Document 734944Source PDF
- ReportsSource: planningapi.agileapplications.ie / 7F0931EBDB1B11EB80F6D8126595A214.pdf / Document 736726Source PDF
- ReportsSource: planningapi.agileapplications.ie / C290FE3D389911EC85EF4CEBBDB3918C.docx / Document 739456Source PDF
- ReportsSource: planningapi.agileapplications.ie / C2C9F426F03C11EB863700505692BE53.pdf / Document 739461Source PDF
- ReportsSource: planningapi.agileapplications.ie / E6C779BDD37211EB80EDD8126595A214.xlsx / Document 741035Source PDF
- ReportsSource: planningapi.agileapplications.ie / E6C779C0D37211EB80EDD8126595A214.pdf / Document 741036Source PDF
- ReportsSource: planningapi.agileapplications.ie / F34BF932703B11EB85064CEBBDB3918C.docx / Document 741600Source PDF
- ReportsSource: planningapi.agileapplications.ie / FF132C0B4C7811EC8643005056925056.docx / Document 742104Source PDF
- AppealSource: planningapi.agileapplications.ie / F20A_0668_Letter_from_An_Bord_Pleanála.pdf / Document 1026339Source PDF
- AppealSource: planningapi.agileapplications.ie / F20A_0668_Appeal_Response.pdf / Document 1026341Source PDF
- AppealSource: planningapi.agileapplications.ie / ABP_314485_FCC_20A0668_Cover_letter_and_Draft_Decision.pdf / Document 1056324Source PDF
- AppealSource: planningapi.agileapplications.ie / ABP_314485_FCC_20A0668_Report_to_Inspector_Appendix_to_main_report.pdf / Document 1056337Source PDF
- AppealSource: planningapi.agileapplications.ie / ABP_314485_FCC_20A0668_Review_of_EIARs_&_A_I_Noise.pdf / Document 1056340Source PDF
- AppealSource: planningapi.agileapplications.ie / ABP_314485_FCC_20A0668-_Inspectors_Report.pdf / Document 1056343Source PDF
- AppealSource: planningapi.agileapplications.ie / Appendix_5_VanguardiaAddendum_Report.pdf / Document 1056382Source PDF
- AppealSource: planningapi.agileapplications.ie / F20A_0668_Appeal_Decision.pdf / Document 1120254Source PDF
- AppealSource: planningapi.agileapplications.ie / F20A_0668_ACP_Notification_Letter.pdf / Document 1125902Source PDF
- AppealSource: planningapi.agileapplications.ie / 153920FE39B411EDB71C9C7BEFBB54FD.tif / Document 744491Source PDF
- AppealSource: planningapi.agileapplications.ie / 1539210A39B411EDB71C9C7BEFBB54FD.tif / Document 744492Source PDF
- AppealSource: planningapi.agileapplications.ie / 1539210439B411EDB71C9C7BEFBB54FD.tif / Document 744719Source PDF
- AppealSource: planningapi.agileapplications.ie / 35C8E2D339BF11EDB71C9C7BEFBB54FD.tif / Document 748142Source PDF
- AppealSource: planningapi.agileapplications.ie / 35C8E2D939BF11EDB71C9C7BEFBB54FD.tif / Document 748148Source PDF
- AppealSource: planningapi.agileapplications.ie / 35C8E2C939BF11EDB71C9C7BEFBB54FD.tif / Document 748595Source PDF
- AppealSource: planningapi.agileapplications.ie / 35C8E2CF39BF11EDB71C9C7BEFBB54FD.tif / Document 748599Source PDF
- AppealSource: planningapi.agileapplications.ie / 35C8E2D639BF11EDB71C9C7BEFBB54FD.tif / Document 748601Source PDF
- AppealSource: planningapi.agileapplications.ie / D0FA9E353B5B11ED81FA4CEBBD9E6A7E.pdf / Document 766580Source PDF
- AppealSource: planningapi.agileapplications.ie / D0FA9E393B5B11ED81FA4CEBBD9E6A7E.pdf / Document 766582Source PDF
- AppealSource: planningapi.agileapplications.ie / D0FA9E3D3B5B11ED81FA4CEBBD9E6A7E.pdf / Document 766585Source PDF
- AppealSource: planningapi.agileapplications.ie / D0FA9E453B5B11ED81FA4CEBBD9E6A7E.pdf / Document 766589Source PDF
- AppealSource: planningapi.agileapplications.ie / D0FA9E493B5B11ED81FA4CEBBD9E6A7E.pdf / Document 766591Source PDF
- AppealSource: planningapi.agileapplications.ie / D0FA9E4F3B5B11ED81FA4CEBBD9E6A7E.pdf / Document 766593Source PDF
- AppealSource: planningapi.agileapplications.ie / D0FA9E5D3B5B11ED81FA4CEBBD9E6A7E.pdf / Document 766594Source PDF
- AppealSource: planningapi.agileapplications.ie / D0FA9E2D3B5B11ED81FA4CEBBD9E6A7E.pdf / Document 767320Source PDF
- AppealSource: planningapi.agileapplications.ie / D0FA9E2F3B5B11ED81FA4CEBBD9E6A7E.pdf / Document 767323Source PDF
- AppealSource: planningapi.agileapplications.ie / D0FA9E373B5B11ED81FA4CEBBD9E6A7E.pdf / Document 767326Source PDF
- AppealSource: planningapi.agileapplications.ie / D0FA9E433B5B11ED81FA4CEBBD9E6A7E.pdf / Document 767329Source PDF
- AppealSource: planningapi.agileapplications.ie / D0FA9E573B5B11ED81FA4CEBBD9E6A7E.pdf / Document 767337Source PDF
- AppealSource: planningapi.agileapplications.ie / D0FA9E633B5B11ED81FA4CEBBD9E6A7E.pdf / Document 767338Source PDF
- AppealSource: planningapi.agileapplications.ie / D0FA9E313B5B11ED81FA4CEBBD9E6A7E.pdf / Document 767497Source PDF
- AppealSource: planningapi.agileapplications.ie / D0FA9E3B3B5B11ED81FA4CEBBD9E6A7E.pdf / Document 767499Source PDF
- AppealSource: planningapi.agileapplications.ie / D0FA9E3F3B5B11ED81FA4CEBBD9E6A7E.pdf / Document 767502Source PDF
- AppealSource: planningapi.agileapplications.ie / D0FA9E473B5B11ED81FA4CEBBD9E6A7E.pdf / Document 767505Source PDF
- AppealSource: planningapi.agileapplications.ie / D0FA9E4B3B5B11ED81FA4CEBBD9E6A7E.pdf / Document 767508Source PDF
- AppealSource: planningapi.agileapplications.ie / D0FA9E4D3B5B11ED81FA4CEBBD9E6A7E.pdf / Document 767511Source PDF
- AppealSource: planningapi.agileapplications.ie / D0FA9E513B5B11ED81FA4CEBBD9E6A7E.pdf / Document 767514Source PDF
- AppealSource: planningapi.agileapplications.ie / D0FA9E533B5B11ED81FA4CEBBD9E6A7E.pdf / Document 767517Source PDF
- AppealSource: planningapi.agileapplications.ie / D0FA9E5B3B5B11ED81FA4CEBBD9E6A7E.pdf / Document 767520Source PDF
- AppealSource: planningapi.agileapplications.ie / 1539210139B411EDB71C9C7BEFBB54FD.tif / Document 814315Source PDF
- AppealSource: planningapi.agileapplications.ie / 1539210739B411EDB71C9C7BEFBB54FD.tif / Document 814316Source PDF
- AppealSource: planningapi.agileapplications.ie / 35C8E2C639BF11EDB71C9C7BEFBB54FD.tif / Document 815595Source PDF
- AppealSource: planningapi.agileapplications.ie / 35C8E2DD39BF11EDB71C9C7BEFBB54FD.tif / Document 815596Source PDF
- AppealSource: planningapi.agileapplications.ie / 74A8B25829FB11EDB7139C7BEFBB54FD.tif / Document 818205Source PDF
- AppealSource: planningapi.agileapplications.ie / 74E19FDB4E3711ED820C4CEBBD9E6A7E.pdf / Document 818225Source PDF
- AppealSource: planningapi.agileapplications.ie / D0FA9E333B5B11ED81FA4CEBBD9E6A7E.pdf / Document 821841Source PDF
- AppealSource: planningapi.agileapplications.ie / D0FA9E413B5B11ED81FA4CEBBD9E6A7E.pdf / Document 821842Source PDF
- AppealSource: planningapi.agileapplications.ie / D0FA9E553B5B11ED81FA4CEBBD9E6A7E.pdf / Document 821843Source PDF
- AppealSource: planningapi.agileapplications.ie / D0FA9E593B5B11ED81FA4CEBBD9E6A7E.pdf / Document 821844Source PDF
- AppealSource: planningapi.agileapplications.ie / D0FA9E5F3B5B11ED81FA4CEBBD9E6A7E.pdf / Document 821845Source PDF
- AppealSource: planningapi.agileapplications.ie / D0FA9E613B5B11ED81FA4CEBBD9E6A7E.pdf / Document 821846Source PDF
- AppealSource: planningapi.agileapplications.ie / 37EA11B78DC611ED82424CEBBD9E6A7E.pdf / Document 864714Source PDF
- AppealSource: planningapi.agileapplications.ie / 7A57B7F2E8EE11EDB7BF9C7BEFBB54FD.tif / Document 872709Source PDF
- AppealSource: planningapi.agileapplications.ie / 83EDB7ABFF9E11ED94D17066553B9052.pdf / Document 873790Source PDF
- AppealSource: planningapi.agileapplications.ie / C5E89ADCCE2C11EDB7AB9C7BEFBB54FD.tif / Document 881510Source PDF
- AppealSource: planningapi.agileapplications.ie / Scan.pdf / Document 889919Source PDF
- AppealSource: planningapi.agileapplications.ie / PR19-2816_RA_Draft_RFI_Response_13.09.2023_v1.7.pdf / Document 894355Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_23_RP065_1.0_CEA_Noise_Information_Report.pdf / Document 894356Source PDF
- AppealSource: planningapi.agileapplications.ie / An_Bord_Pleanála_-_13_Sep_2023.pdf / Document 894358Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_23_RP060_Noise_Modelling_Report_ABP_RFI_-_Figures.pdf / Document 894359Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_23_RP060_4.0_Noise_Modelling_Report_ABP_RFI_27_Apr_2023.pdf / Document 894363Source PDF
- AppealSource: planningapi.agileapplications.ie / App_1A_-_AA_Screening_Addendum.pdf / Document 894365Source PDF
- AppealSource: planningapi.agileapplications.ie / App_1B_-_Cumulative_Effects_Addendum_-_Appendix.pdf / Document 894367Source PDF
- AppealSource: planningapi.agileapplications.ie / App_1B_-_Cumulative_Effects_Addendum_FINAL.pdf / Document 894368Source PDF
- AppealSource: planningapi.agileapplications.ie / 01_-_Introduction_FINAL.pdf / Document 894369Source PDF
- AppealSource: planningapi.agileapplications.ie / 07_-_Population_and_Human_Health_FINAL.pdf / Document 894370Source PDF
- AppealSource: planningapi.agileapplications.ie / 11_-_Climate_and_Carbon_FINAL.pdf / Document 894371Source PDF
- AppealSource: planningapi.agileapplications.ie / 13_-_Air_Noise_&_Vibration_FINAL.pdf / Document 894372Source PDF
- AppealSource: planningapi.agileapplications.ie / 14_-_Ground_Noise_&_Vibration_FINAL.pdf / Document 894373Source PDF
- AppealSource: planningapi.agileapplications.ie / 22_-_Future_Development_FINAL.pdf / Document 894374Source PDF
- AppealSource: planningapi.agileapplications.ie / EIAR_Supplement_-_Front_Material__FINAL.pdf / Document 894375Source PDF
- AppealSource: planningapi.agileapplications.ie / Appropriate_Assessment_Screening_Report_Addendum.pdf / Document 894377Source PDF
- AppealSource: planningapi.agileapplications.ie / InterVISTAS_OperatingRestrictionsAddendum_6Sep2023.pdf / Document 894378Source PDF
- AppealSource: planningapi.agileapplications.ie / DAA_Op_Restrictions_Report_(ANCA_RFI_v1.3.1)_Addendum_v1.0_20230907-1.pdf / Document 894379Source PDF
- AppealSource: planningapi.agileapplications.ie / Penzel-report-Dublin_FINAL_11.09.23.pdf / Document 894380Source PDF
- AppealSource: planningapi.agileapplications.ie / Daa_CEAResultsUpdate_Report_2023-09-14_FINAL.pdf / Document 894381Source PDF
- AppealSource: planningapi.agileapplications.ie / Scan.pdf / Document 894382Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_23_RP061_2.0_NR_EIAR_Appendix_13B_Air_Noise_Methodology.pdf / Document 894383Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_23_RP062_2.0_NR_EIAR_Appendix_13C_Air_Noise_Modelling_Results_Figures.pdf / Document 894384Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR825_2.0_Figure_13B-1_Air_Noise_Study_Area.pdf / Document 894385Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_23_RP063_1.0_NR_EIAR_Appendix_14B_Ground_Noise_Methodology.pdf / Document 894386Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_23_RP064_1.0_NR_EIAR_Appendix_14C_Ground_Noise_Modelling_Results_Figures.pdf / Document 894387Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_23_DR073_1.0_Figure_13B-2_Modelled_Routes_-_South_Runway.pdf / Document 894389Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_23_DR074_1.0_Figure_13B-3_Modelled_Routes_-_North_Runway.pdf / Document 894390Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_23_DR914_1.0_Figure_14C-1_2018_Lden.pdf / Document 894391Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_23_DR915_1.0_Figure_14C-2_2018_Lnight.pdf / Document 894392Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_23_DR916_1.0_Figure_14C-3_2018_LAeq16h.pdf / Document 894393Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_23_DR917_1.0_Figure_14C-4_2018_LAeq8h.pdf / Document 894394Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_23_DR918_1.0_Figure_14C-5_2025_Con_Lden.pdf / Document 894395Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_23_DR919_1.0_Figure_14C-6_2025_Con_Lnight.pdf / Document 894396Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_23_DR920_1.0_Figure_14C-7_2025_Con_LAeq16h.pdf / Document 894397Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_23_DR921_1.0_Figure_14C-8_2025_Con_LAeq8h.pdf / Document 894398Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_23_DR922_1.0_Figure_14C-9_2025_UnC_Lden.pdf / Document 894399Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_23_DR923_1.0_Figure_14C-10_2025_UnC_Lnight.pdf / Document 894400Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_23_DR924_1.0_Figure_14C-11_2025_UnC_LAeq16h.pdf / Document 894401Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_23_DR925_1.0_Figure_14C-12_2025_UnC_LAeq8h.pdf / Document 894412Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_23_DR926_1.0_Figure_14C-13_2035_Con_Lden.pdf / Document 894413Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_23_DR927_1.0_Figure_14C-14_2035_Con_Lnight.pdf / Document 894414Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_23_DR928_1.0_Figure_14C-15_2035_Con_LAeq16h.pdf / Document 894415Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_23_DR929_1.0_Figure_14C-16_2035_Con_LAeq8h.pdf / Document 894416Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_23_DR930_1.0_Figure_14C-17_2035_UnC_Lden.pdf / Document 894417Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_23_DR931_1.0_Figure_14C-18_2035_UnC_Lnight.pdf / Document 894418Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_23_DR932_1.0_Figure_14C-19_2035_UnC_LAeq16h.pdf / Document 894419Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_23_DR933_1.0_Figure_14C-20_2035_UnC_LAeq8h.pdf / Document 894420Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR017_2.0_Figure_13C-01_2025_Permitted_Lden.pdf / Document 894422Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR018_2.0_Figure_13C-02_2025_Permitted_Lnight.pdf / Document 894424Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR019_2.0_Figure_13C-03_2025_Permitted_LAeq16.pdf / Document 894425Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR020_2.0_Figure_13C-04_2025_Permitted_LAeq8.pdf / Document 894427Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR021_2.0_Figure_13C-05_2025_Permitted_N65.pdf / Document 894430Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR022_3.0_Figure_13C-06_2025_Permitted_N60.pdf / Document 894433Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR023_2.0_Figure_13C-07_2025_Permitted_Lday.pdf / Document 894436Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR024_2.0_Figure_13C-08_2025_Permitted_Leve.pdf / Document 894438Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR025_2.0_Figure_13C-09_2025_Proposed_Lden.pdf / Document 894440Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR026_2.0_Figure_13C-10_2025_Proposed_Lnight.pdf / Document 894442Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR027_2.0_Figure_13C-11_2025_Proposed_LAeq16.pdf / Document 894445Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR028_2.0_Figure_13C-12_2025_Proposed_LAeq8.pdf / Document 894448Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR029_2.0_Figure_13C-13_2025_Proposed_N65.pdf / Document 894449Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR030_3.0_Figure_13C-14_2025_Proposed_N60.pdf / Document 894450Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR031_2.0_Figure_13C-15_2025_Proposed_Lday.pdf / Document 894451Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR032_2.0_Figure_13C-16_2025_Proposed_Leve.pdf / Document 894453Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR033_2.0_Figure_13C-17_2035_Permitted_Lden.pdf / Document 894455Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR034_2.0_Figure_13C-18_2035_Permitted_Lnight.pdf / Document 894456Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR035_2.0_Figure_13C-19_2035_Permitted_LAeq16.pdf / Document 894459Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR036_2.0_Figure_13C-20_2035_Permitted_LAeq8.pdf / Document 894461Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR037_2.0_Figure_13C-21_2035_Permitted_N65.pdf / Document 894462Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR038_3.0_Figure_13C-22_2035_Permitted_N60.pdf / Document 894463Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR039_2.0_Figure_13C-23_2035_Permitted_Lday.pdf / Document 894464Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR040_2.0_Figure_13C-24_2035_Permitted_Leve.pdf / Document 894465Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR041_2.0_Figure_13C-25_2035_Proposed_Lden.pdf / Document 894466Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR042_2.0_Figure_13C-26_2035_Proposed_Lnight.pdf / Document 894467Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR043_2.0_Figure_13C-27_2035_Proposed_LAeq16.pdf / Document 894468Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR044_2.0_Figure_13C-28_2035_Proposed_LAeq8.pdf / Document 894469Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR045_2.0_Figure_13C-29_2035_Proposed_N65.pdf / Document 894470Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR046_3.0_Figure_13C-30_2035_Proposed_N60.pdf / Document 894471Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR047_2.0_Figure_13C-31_2035_Proposed_Lday.pdf / Document 894472Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR048_2.0_Figure_13C-32_2035_Proposed_Leve.pdf / Document 894473Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR049_2.0_Figure_13C-33_2025_Permitted_Lnight_East.pdf / Document 894474Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR050_2.0_Figure_13C-34_2025_Permitted_Lnight_West.pdf / Document 894475Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR051_3.0_Figure_13C-35_2025_Permitted_N60_East.pdf / Document 894476Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR052_3.0_Figure_13C-36_2025_Permitted_N60_West.pdf / Document 894477Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR053_2.0_Figure_13C-37_2025_Proposed_Lnight_East.pdf / Document 894478Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR054_2.0_Figure_13C-38_2025_Proposed_Lnight_West.pdf / Document 894479Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR055_3.0_Figure_13C-39_2025_Proposed_N60_East.pdf / Document 894480Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR056_3.0_Figure_13C-40_2025_Proposed_N60_West.pdf / Document 894481Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR057_2.0_Figure_13C-41_2035_Permitted_Lnight_East.pdf / Document 894483Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR058_2.0_Figure_13C-42_2035_Permitted_Lnight_West.pdf / Document 894485Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR059_3.0_Figure_13C-43_2035_Permitted_N60_East.pdf / Document 894486Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR060_3.0_Figure_13C-44_2035_Permitted_N60_West.pdf / Document 894538Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR061_2.0_Figure_13C-45_2035_Proposed_Lnight_East.pdf / Document 894540Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR062_2.0_Figure_13C-46_2035_Proposed_Lnight_West.pdf / Document 894541Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR063_3.0_Figure_13C-47_2035_Proposed_N60_East.pdf / Document 894542Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_19_DR064_3.0_Figure_13C-48_2035_Proposed_N60_West.pdf / Document 894545Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_23_DR065_1.0_Figure_13C-49_Lmax_A320ceo_R28L_Arrival.pdf / Document 894548Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_23_DR066_1.0_Figure_13C-50_Lmax_A320ceo_R28L_Departure.pdf / Document 894550Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_23_DR067_1.0_Figure_13C-51_Lmax_A320neo_R28L_Arrival.pdf / Document 894553Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_23_DR068_1.0_Figure_13C-52_Lmax_A320neo_R28L_Departure.pdf / Document 894555Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_23_DR069_1.0_Figure_13C-53_Lmax_B738_R28L_Arrival.pdf / Document 894556Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_23_DR070_1.0_Figure_13C-54_Lmax_B738_R28L_Departure.pdf / Document 894558Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_23_DR071_1.0_Figure_13C-55_Lmax_B737MAX8_R28L_Arrival.pdf / Document 894560Source PDF
- AppealSource: planningapi.agileapplications.ie / A11267_23_DR072_1.0_Figure_13C-56_Lmax_B737Max8_R28L_Departure.pdf / Document 894562Source PDF
- AppealSource: planningapi.agileapplications.ie / F20A_0668.pdf / Document 901222Source PDF
Nearby precedent
Similar nearby applications linked to this planning decision.- F19A/0304The construction of 25 no. additional space car park, relocation of ex / 0.1 km away / 05 December 2019Granted
- F16A/0339The construction of: a 30 No. space security restricted car park; 6 N / 0.1 km away / 23 September 2016Granted
- F20A/0137A covered walkway over the existing private IAA footpath, linking the two existing air traffic control centres, solar panels on the roof of the covered walkway, new footpath from the new tower service yard to the front entrance and associated site works. / 0.1 km away / 07 July 2020Granted
- F21A/0008Development of an airside single-storey free-standing General Aviation dispatch hut and Tug Shelter and storage shelter (approx. 10.7m x 9.9m). The application includes all associated site works and services. AI received 20/04/21 / 0.2 km away / 10 May 2021Granted
- F22A/0460We, daa plc intend to seek planning permission for development on 4no. sites located entirely within lands in the ownership of Dublin Airport, including 2no. sites at the Airfield in the townlands of Collinstown, Coultry, and Huntstown, Co. Dublin, 1no. of which incorporates part of Pier 3 and surrounding aircraft stands, aircraft stands to the south of Pier 2, Apron Taxiway 4, Taxiway F-2, Runway 16/34 (the crosswind runway), Taxiway W1 and W2, West Apron; and 1no. of which incorporates an existing airside site compound, south of the West Apron; 1no. area of land to the west of the existing Western Compound, south of the R108, north-west of the Airport, in the townland of Pickardstown, Co. Dublin, also to be known as the Western Compound; and 1no. an area of existing hardstanding to the south-west of the Airport, north of the R108, to be known as the Southern Compound, in the townland of Portmellick, Co. Dublin. The proposed development will consist of the construction of a subterranean Underpass of Runway 16/34, a critical airfield operational safety project, which will comprise: a) A twin-cell enclosed tunnel with 2 no. lanes in each direction, linked to the surface by ramps, portals, and light attenuation screen (1.8m in height above existing ground level at the west ramp and 3.3m in height above existing ground level at the east ramp). The enclosed section will be approximately 0.7 km long, with an overall alignment of approximately 1.1 km in length from top of ramp to top of ramp. It will be approximately 24m in external width, and approximately 5.5m in internal height from road to tunnel ceiling. It will be up to 17.5m below existing ground level; b) Plant room, of approximately 625m2, which will comprise housing for transformers, pumps, controls and communications equipment, located underground at the portal of the east ramp, a parking layby and utilities corridor crossing; c) Demolition (approximately 23,741m2) and reinstatement (approximately 16,216m2) of part of the pavement surfaces of Apron Taxiway 4, Taxiway F-2, Runway 16/34 (the crosswind runway), Taxiway W1 and W2, and the West Apron; d) Access roads to tie in with the existing airside road network at each end of the proposed Underpass (at Pier 3 on the Eastern Campus and the West Apron on the Western campus respectively), and 31no. car parking spaces at surface level at Pier 3; e) Demolition (approximately 97m2) of fixed links (elevated enclosed passenger walkways leading from the Pier to Aircraft Nodes) and Nodes (structures which provide support for the fixed links and internal pedestrian access cores to ground level) serving 3 no. aircraft stands and associated airbridges (passenger boarding bridges) at Level 20 (departure gates) of Pier 3. To the south of Pier 3, an existing airbridge is to be removed and an existing fixed link is to be adjusted to service existing stands in that area; f) Replacement of the demolished fixed links and nodes with 3no. new fixed links, A (approximately 356m2), B (approximately 227m2) and C (approximately 170m2) and of approximately 150m, 95m and 70m in length respectively and approximately 2.2m in width and approximately 3.2m in height, at a maximum height of approximately 7.1m above the surrounding apron; 3no. two-storey Nodes A, B and C, approximately 157m2, 154m2 and 148m2 in area respectively; and 2 no. airbridges (1no. at Node A and 1no. at Node B). g) Modifications to the elevations of Pier 3 at Level 20 to accommodate the links and airbridges, including part replacement of the existing glazing with new glazing/cladding, and a new cladded portal with new doors and access control at each new fixed link location; rearrangement of part of the internal floorspace of Level 20, including a new partition between the entrance/ exits of proposed fixed links A and B; new surface water drainage network; and 31no. car parking spaces at surface level; h) Realignment of stands on the Eastern Campus resulting in the net loss of three Narrow Body Enabled (NBE) stands and net gain of one Wide Body (WB) stand at Pier 3; i) Realignment of aircraft stands in the West Apron (involving rearranging /relocating stands by way of new paint markings on the apron pavement) to accommodate the portal and Underpass access roads (no net change in number of stands); j) Modifications to existing drainage network in the vicinity of the proposed Underpass including replacement of existing attenuation system, and construction of a new drainage network for the proposed Underpass, including sump pit with pumps, interceptors, and new attenuation tank; k) Temporary diversion of the Airfield Trunk Culvert during construction and its reinstatement at the existing alignment and level; I) Construction of a new underground pipe network (6no. new pipes) to allow for future drainage infrastructure/surface water management measures; m) Realignment of stands at Pier 2 on the Eastern Campus (no net change in number of stands); n) All ancillary airport infrastructure including additional apparatus/equipment including jet blast fencing, Fixed Electrical Ground Power (FEGP), Advanced Visual Docking Guidance System (AVDGS), Stand Number Indicator Board (SNIB), Fuel Hydrants, High Mast Lighting (HML), electrical charging facilities, and miscellaneous ground service equipment (GSE) parking and storage areas; o) The proposed development also includes (i) a new Western Compound adjacent to the existing Western Compound located south of the R108, north west of the Airport, with a new access off the R108, to be used for pre-screening for deliveries going airside, and to include an airside pass office, parking for construction staff, as well as storage areas, and general logistics; (ii) the provision of a new Southern Compound to the north of the R108, to the south west of the Airport, to be utilised as a lorry waiting area for HGVs. No works are required at this Southern Compound; and (iii) the use of an existing airside site compound adjacent to the proposed Underpass, south of the West Apron, for concrete crushing, batching plant, the storage of non-hazardous materials and equipment, as well as offices, workshop, welfare facilities, and parking. The proposed development does not propose any increase in passenger, cargo or operational capacity at Dublin Airport. The planning application is accompanied by an Environmental Impact Assessment Report (EIAR) and a Natura lmpact Statement (NIS). The planning application, EIAR and NIS may be inspected or purchased at a fee not exceeding the reasonable cost of making a copy at the offices of the Planning Authority, Fingal County Council, Fingal County Hall, Main Street, Swords, Fingal, Co. Dublin, during its public opening hours of 9.30 - 16.30 Monday - Friday (Cash Office opening hours are 9.30 - 15.30), and a submission or observation may be made to the Planning Authority in writing on payment of the prescribed fee within the period of 5 weeks beginning on the date of receipt by the authority of the application, and such submissions or observations will be considered by the Planning Authority in making a decision on the application. The Planning Authority may grant permission subject to or without conditions, or may refuse to grant permission. AI Received 22/12/2022 / 0.2 km away / 27 February 2023Granted
- F18A/0747The proposed development will comprise a single-storey free-standing s / 0.2 km away / 19 February 2019Granted
- F16A/0338Works to upgrade the existing road junction between Gate 9 and the R10 / 0.2 km away / 23 September 2016Granted
- F16A/0549The construction of a new single storey hangar and attached 2 storey f / 0.3 km away / 02 February 2017Granted