FW24A/0400E: Intend to apply for Permission for A Battery Energy Storage System facility to include up to 85 no. containerised battery storage modules on concrete bases, 20 no. transformer and power conditioning units, cable racks, and associated lighting. 2) Associated development including internal access roads, security gates, palisade perimeter security fencing, acoustic barrier, site drainage and all other works required to facilitate the development. AI Rcvd 30/04/2025
Huntstown Power Station, In the townlands of Hunstown and Johnstown, C
DecisionGrant permission
Decided26 May 2025
Application typePermission
Source documents16
Site
What is on file
0refusal reasons0conditions8nearby records
Decision details
Core application dates and identifiers from the public planning record.Planning analysis
Refusal reasons and planning conditions extracted from the public decision file.Refusal reasons
No refusal reason on record
Documents are indexed. Reason extraction for Fingal is in progress.
Conditions
No conditions
No conditions are on record for this application yet.
Planning a project near Huntstown Power Station, In the townlands of Hunstown and Johnstown, C?
Get the precedent report for this site: every grant and refusal within 5 km, and the planners' reasons. €49 incl. VAT, PDF by email.Source documents
Original council portal records and source PDFs where available.- Application fileApplication file on planning.agileapplications.ieSource portal
- Notification Of DecisionSource: planningapi.agileapplications.ie / FW24A.0400E_D.pdf / Document 1069231Source PDF
- Notification Of DecisionSource: planningapi.agileapplications.ie / FW24A.0400E_D.pdf / Document 1108661Source PDF
- Chief Executives OrderSource: planningapi.agileapplications.ie / FW24A.0400E_CE.pdf / Document 1069230Source PDF
- Chief Executives OrderSource: planningapi.agileapplications.ie / FW24A.0400E_ce_.pdf / Document 1108660Source PDF
- Final GrantSource: planningapi.agileapplications.ie / FW24A_0400E.pdf / Document 1117168Source PDF
- ReportsSource: planningapi.agileapplications.ie / FW24A-0400E_-_Uisce_Eireann.pdf / Document 1061859Source PDF
- ReportsSource: planningapi.agileapplications.ie / FW24A0400E_Environment_Reponse_to_Planning.pdf / Document 1062130Source PDF
- ReportsSource: planningapi.agileapplications.ie / FW24A-0400E_-_DAA.pdf / Document 1065125Source PDF
- ReportsSource: planningapi.agileapplications.ie / FW24A_0400E.docx / Document 1065238Source PDF
- ReportsSource: planningapi.agileapplications.ie / FW24A-0400E.docx / Document 1067414Source PDF
- ReportsSource: planningapi.agileapplications.ie / FW24A_0400E.docx / Document 1067475Source PDF
- ReportsSource: planningapi.agileapplications.ie / FW24A-0400E_-HSA.pdf / Document 1067838Source PDF
- ReportsSource: planningapi.agileapplications.ie / FW24A0400E.docx / Document 1106456Source PDF
- ReportsSource: planningapi.agileapplications.ie / FW24A_0400E-_Health_and_Safety_Authority.pdf / Document 1107896Source PDF
- ReportsSource: planningapi.agileapplications.ie / FW24A.0400E_Air_and_Noise_Report_AI.pdf / Document 1107955Source PDF
Nearby precedent
Similar nearby applications linked to this planning decision.- FW25A/0086EThe replacement of approx. 251 m of existing 2.4 m high chainlink perimeter fencing and associated access / emergency gates with new 2.4 m high security fencing, gates and all associated site works. / 0.1 km away / 28 April 2025Granted
- FW19A/0015The development will consist of a Battery Energy Storage System (BESS) / 0.2 km away / 21 March 2019Granted
- FW18A/0082The development is a wastewater treatment plant comprising a 3m high b / 0.3 km away / 26 July 2018Granted
- FW24A/0082The development will consist of upgrade works and alterations to an existing renewable bioenergy plant as granted permission under planning reference FW13A/0089 (as extended under extension of duration FW13A/0089/E1) and as granted permission for an increase in the volume of waste imported under planning reference FW18A/0159. The proposed works consist of: (i) Provision of a Biomethane Upgrader, comprising a biogas scrubber and a compression unit; (ii) Provision of a Biomethane Nework Entry Facility (BNEF) with associated proane tanks and perimeter fencing; (iii) Amendment to operating hours with removal of condition 5 of permission FW13A/0089 to permit waste being accepted into the facility 24 hours per day and outputs also being removed from the site 24 hours per day to facilitate operations; (iv) Ancillary site development works. Access will be through existing permitted vehicular accesses onto the R135 Regional Road. The application relates to development which comprises or is for the purpose of an activity requiring an industrial emissions licence issued by the Enviromental Protection Agency. / 0.3 km away / 25 April 2024Granted
- FW13A/0018Extension to and modifications of the Dogs Trust Rehoming Centre previ / 0.3 km away / 24 April 2013Granted
- FW13A/0143Planning Permission and Retention Permission for development at this s / 0.3 km away / 17 February 2014Granted
- FW23A/0276Planning Permission to erect 1,795.23 m2 or 371.68 Kwp of photovoltaic panels on the roof of our existing Huntstown Power Station plant with all associated site works at Huntstown Bioenergy Limited, Johnstown, Dublin, D11 N28R, site that currently operates under an Industrial Emissions (IE) License (P0993-02). / 0.3 km away / 01 November 2023Granted
- FW18A/0159Planning Permission is sought for an increase in the annual volume of / 0.3 km away / 13 December 2018Granted