FW24A/0474: Permission for retention of an attic conversion including two dormer windows to the front elevation and roof extension with windows to the rear elevation of the original bungalow and two single storey extensions to the rear, with a total additional area of 143 sq.m to the Dormer Bungalow.
Hollystown, Mulhuddart, Co. Dublin
DecisionGrant permission for retention
Decided06 January 2025
Application typeRetention
Source documents5
Site
What is on file
0refusal reasons0conditions8nearby records
Decision details
Core application dates and identifiers from the public planning record.Planning analysis
Refusal reasons and planning conditions extracted from the public decision file.Refusal reasons
No refusal reason on record
Documents are indexed. Reason extraction for Fingal is in progress.
Conditions
No conditions
No conditions are on record for this application yet.
Planning a project near Hollystown, Mulhuddart, Co. Dublin?
Get the precedent report for this site: every grant and refusal within 5 km, and the planners' reasons. €49 incl. VAT, PDF by email.Source documents
Original council portal records and source PDFs where available.- Application fileApplication file on planning.agileapplications.ieSource portal
- Notification Of DecisionSource: planningapi.agileapplications.ie / Fw24A.0474_D.pdf / Document 1077212Source PDF
- Chief Executives OrderSource: planningapi.agileapplications.ie / Fw24A.0474_ce.pdf / Document 1077211Source PDF
- Final GrantSource: planningapi.agileapplications.ie / FW24A_0474.pdf / Document 1083468Source PDF
- ReportsSource: planningapi.agileapplications.ie / FW24A-0474_-DAA.pdf / Document 1073932Source PDF
Nearby precedent
Similar nearby applications linked to this planning decision.- FW25A/0156The development will consist of an increase in the maximum number of children to be accommodated in the existing Creche from 50 at any one time ( as conditioned within Condition No. 4 of the Grant of Planning Permission made under Planning Register Reference Number F07A/1454) to 77 Children and, the construction of a bicycle shelter to accommodate ten bicycles. Additional information received 10/11/25 Significant Additional Information received 28/11/2025 / 0.1 km away / 16 December 2025Granted
- FW20B/0029Retention Planning Permission for a single storey side extension with alterations to existing building. / 0.1 km away / 09 June 2020Granted
- FW17B/0058The development will consist of first floor extension and single store / 0.2 km away / 15 August 2017Granted
- FW25A/0472EThe development consists of amendments to permitted Reg Ref W24A/0471E. The amendments consist of, 1) revised design of detached two storey creche with a new floor area of 196.6sq.m (previously 341sq.m) and associated internal layout, play area, elevational, parking, bicycle layout and bin store updates. 2) the addition of 2no. three storey houses, Type C1 adjacent to the creche. 3) Change of house type from a C2, three storey house to a C1, three storey house. 4) Road layout revision at Hollywood Close to create a homezone with associated car parking updates and all ancillary site development works. Additional Information Received 17/02/2026 Significant Additional Information Received 27/02/2026 / 0.2 km away / 26 March 2026Granted
- FW22A/0034The development will consist of of 4 No. ground floor shops, a remote work hub, a stand-alone café with outdoor seated dining area and 17 No. residential units across 4 individual blocks ranging from one to three storeys on a site measuring circa 0.53 Hectares and comprising; (i) Block A: 2 storey block of 2 No. two bed and 3 No. 1 bed apartments over 4 No. ground floor shops, (ii) Block B: 3 storey block of 4 No. 2-storey 3-bedroom duplex units over a ground floor remote work hub, (iii) Block C: 3 storey block of 4 No. 2-storey 3-bedroom duplex units over 4 No. ground level 2 bedroom apartments, (iv) Block D: single storey standalone pavilion style café with outdoor seated dining area, (v) Ancillary bicycle storage, refuse storage and ESB substation in 3 individual single storey buildings, (vi) provision of 46 No. car parking spaces, 82 No. bicycle parking spaces and 2 No. motorcycle parking spaces, (vii) an area of public open space, including a children’s play area, (viii) relocation of an existing vehicular and pedestrian entrance off the Ratoath Road to the Northern end of the site frontage (ix) alterations to the existing boundaries and all associated site development works including hard and soft landscaping, service connections and drainage works including connections to the existing public foul and surface water systems in the Ratoath Road. AI received 17/6/2022 / 0.2 km away / 13 July 2022Granted
- FW22B/00841) Single storey domestic garage to gable end and rear of house. 2) Single storey extension to rear of house as addition to existing single storey extension. / 0.2 km away / 29 August 2022Granted
- FW20B/0141The development will consist of 1. Construction of a new single storey flat roof side and rear extension to consist of a living room and study. 2. General remodel and upgrade of the main dwelling to suit the proposed layouts. 3. All drainage, structural and associated site works to be implemented. / 0.2 km away / 15 December 2020Granted
- FW22A/0098A 10 Year PERMISSION for development of a site of c 9.3ha in the townlands of Hollystown and Yellow Walls on part of the former Hollystown Golf Course lands, Ratoath Road, Hollystown, Dublin 15, D15 C6258. The development will consist of a GAA Cluster Facility including: a) 4 no. floodlit GAA pitches (Pitches No’s 1 to 4) comprising; 1 x synthetic all weather pitch (Pitch No. 2) (145m x 90m with floodlights with a lux level of 350 mounted on 8 no. 20 metre high columns); 2 x sand-based grass pitches (Pitch No’s 3 and 4) (145m x 90m with floodlights with a lux level of 350 mounted on 8 no. 20 metre high columns per pitch);1 x sand-based grass pitch (Pitch No. 1) (145m x 90m with floodlights with a lux level of 500 mounted on 8 no. 30 metre high columns). All pitches will have GAA goal posts and ball stop netting (12m in height and 30m in length) to rear of same, scoreboards and 2 dugouts each, a railing around the perimeter of each of the sand-based pitches and 2.5m sports fencing around the perimeter of the all-weather pitch. The development will also consist of b) the renovation and alteration of the former 2 storey clubhouse (existing area: 678m2) with the alteration of the existing bar area to 2 no. team changing rooms and alteration of existing changing room layouts with new external door access, officials changing room, showers and toilets on the ground floor, retention of existing kitchen facilities, re-purposing of first floor to offices, storage space and team meeting space/multi-purpose room, including removal of external stairs. c) Development of new two-storey extension (area:1,276m2, height: 10.06m) to provide 6 no. team changing rooms, showers and toilets, baths and physio rooms, plant room and toilets for spectators, all on ground floor. Gymnasium, storerooms, office and physio space and team meeting space/multi-purpose room on first floor. New access stairs and lift as well as terrace and green roof and pv solar roof panels. d) the provision of a separate Indoor Training Facility (area: 820m2, height: 7.25m) including a 30m x 20m pitch, team tactics space, toilets, plant room and store for equipment. e) the construction of a Spectator Stand to the east of Pitch No.1 (area: 296m2, height: 7m) to accommodate 500 spectators with partial roof/cover and undercroft equipment store. f) Hurling wall (9m x 9.5m and 5m in height) with fenced in floodlit astro-turf hurling practice area. g) Maintenance and storage building (area: 128m2, height: 4.3m). h) Demolition of existing driving range and pro-shop shed (area: 72m2). In addition the development will include i) a walking/jogging trail with outdoor exercise equipment around perimeter of site, an outdoor training area (30m x 20m) and 100m long speed training area, a new access roadway and pedestrian entrance onto Ratoath Road, 3 no. pedestrian/cycle access gates to adjacent lands to south-east. Car Parking for 54 no. standard car parking spaces, 9 no. universal access spaces and 100 no. overflow spaces for intermittent use with a grasscrete finish, 2 no. coach spaces and bicycle stands for the parking of 100 no. bicycles. j) Earthworks drainage infrastructure and attenuation, an ESB substation (area: 42m2) and switch room, retaining structures, signage, landscaping and all other associated site development works above and below ground level. AI Received 24/10/2022 / 0.2 km away / 17 November 2022Granted