FW25A/0173E: Permission and Retention Permission for proposed development consisting of: 1. Cricket oval (156 m diameter field of play), permanent fixed seating for 4,240 spectators with access from the northeast and southwest, and perimeter fencing. 2. Two storey (12 m high) main pavilion building (4,477 sqm) comprising High Performance Centre (HPC) including 4 lane indoor cricket hall with viewing gallery, hall storage, fitness suite, medical and consulting rooms and HPC offices; Player and Match Official Area (PMOA) comprising 4 no. team changing suites, internal and external viewing areas over the oval, team analysis area, physio room, players and coaches changing facilities and utility room, changing and support accommodation for officials, team and official dining room, and anti-doping suite; and foyer, admin staff area, staff room, toilets, and venue control room. 3. Cricket oval floodlighting via 6 no. columns of maximum height 60 m approximately. 4. The provision of spectator concourse and service zone/route immediately around the cricket oval seating; 2 no. moveable sightscreen frames; maintenance facility; and 2 no. toilet blocks. 5. Arrivals plaza including the provision of 31 no. car parking spaces (including 2 no. EV spaces and 7 no. accessible spaces and 1 no. shared EV/accessible space) and 15 no. bicycle parking spaces for day-to-day and non-event/match day use. 6. Provision to the north of the proposed access road of a permanent cricket facility energy centre, provision of a media/outside broadcasting zone for all event/match days; and (a) provision of 150 no. car parking spaces (of which 15 no. are for permanent use and 135 no. for event/match use up to 4,240 attendance, of which there are 18 no. EV spaces and 2 no. accessible spaces and 1 no. shared EV/accessible space) and 184 no. bicycle parking spaces; (b) provision of an event/match overlay area to accommodate a further 170 no. car parking spaces and further bicycle parking spaces for attendances in excess of 4,240 spectators. 7. Provision of serviced overlay areas to accommodate up to a further approximately 7,760 non-permanent seats required on an occasional basis (to bring the total occasional capacity to 12,000 seats) and for concessions, food and beverage, corporate activities, spectators’ activation zones for use only on match/event days, and provision of permanent utilities and services in the form of water, electricity and waste water. 8. Provision of new outdoor grass surface practice nets providing 16 strips, and retention permission of existing access, landscaping and 26 no. car parking spaces at the existing nets for use on a permanent basis. 9. New access road with new entrance incorporating totem signage, pedestrian crossing, carriageway, cycle lanes, footpaths, bus turning area, bus/taxi drop off area, bus lane reservation, upgrade to 2 no. existing pedestrian and bicycle crossings and junction improvements on Ballycoolin Road. 10. 8 no. bus/coach stops, bus and coach turning area/terminus, 30 no. bicycle parking spaces, upgrade and modification to existing vehicular roads, and widening and resurfacing of existing footpaths/cycleways, new gated pedestrian/cycle entrance to the south of the campus, provision of new cycle routes and footpaths promoting active travel into and within the campus. 11. Provision of temporary haul road to facilitate the construction of strategic drainage infrastructure. 12. Temporary provision of a construction compound for the proposed scheme north of the proposed access road prior to completion of the proposed development. 13. Reprofiling of land, extensive landscaping, necessary services and infrastructure, diversion and undergrounding of existing overhead power lines, 2 no. substation kiosks and transformers, and all associated site works above and below ground including temporary works required to facilitate the efficient and safe ongoing operation of the campus. The planning application is accompanied by an Environmental Impact Assessment Report (EIAR) and a Natura Impact Statement (NIS). The proposed development is located within the historic estate and attendant grounds of Abbotstown House which is a protected structure (RPS No. 0683), and adjacent to protected structures Abbotstown Gate Lodge (RPS No. 939), Irish Institute of Sport (RPS No. 0940) and St. Coemhin’s Church (in ruins) and Graveyard (RPS No: 0684). Additional information received 01/08/25 Significant Additional Information received 08/08/2025
Sport Ireland National Sports Campus, Snugborough Road, Blanchardstown
DecisionGrant permission & grant retention
Decided02 October 2025
Application typePermission and Retention
Source documents30
Site
What is on file
0refusal reasons0conditions8nearby records
Decision details
Core application dates and identifiers from the public planning record.Planning analysis
Refusal reasons and planning conditions extracted from the public decision file.Refusal reasons
No refusal reason on record
Documents are indexed. Reason extraction for Fingal is in progress.
Conditions
No conditions
No conditions are on record for this application yet.
Planning a project near Sport Ireland National Sports Campus, Snugborough Road, Blanchardstown?
Get the precedent report for this site: every grant and refusal within 5 km, and the planners' reasons. €49 incl. VAT, PDF by email.Source documents
Original council portal records and source PDFs where available.- Application fileApplication file on planning.agileapplications.ieSource portal
- Notification Of DecisionSource: planningapi.agileapplications.ie / FW25A.0173E_D.pdf / Document 1114370Source PDF
- Notification Of DecisionSource: planningapi.agileapplications.ie / FW25A.0173E_D.pdf / Document 1137031Source PDF
- Chief Executives OrderSource: planningapi.agileapplications.ie / FW25A.0173E_ce.pdf / Document 1114369Source PDF
- Chief Executives OrderSource: planningapi.agileapplications.ie / FW25A.0173E_CE.pdf / Document 1137030Source PDF
- Final GrantSource: planningapi.agileapplications.ie / FW25A-0173E.pdf / Document 1145545Source PDF
- ReportsSource: planningapi.agileapplications.ie / 20250402_c468.21_si_campus_fetmp_v1.9_w_app.pdf / Document 1096863Source PDF
- ReportsSource: planningapi.agileapplications.ie / 20250423_c468.14_si_cricket_tta_v1.10_w_apps_2_of_2.pdf / Document 1096878Source PDF
- ReportsSource: planningapi.agileapplications.ie / 20250423_c468.14_si_cricket_tta_v1.10_w_apps_1_of_2.pdf / Document 1096880Source PDF
- ReportsSource: planningapi.agileapplications.ie / Arch_Report_FW25A0173E_Sports.docx / Document 1104297Source PDF
- ReportsSource: planningapi.agileapplications.ie / FW25A0173E_Environment_Reponse_to_Planning.pdf / Document 1106126Source PDF
- ReportsSource: planningapi.agileapplications.ie / FW25A-0173E_-_Department_of_Defence.pdf / Document 1106734Source PDF
- ReportsSource: planningapi.agileapplications.ie / FW25A_0173E_-_DAA.pdf / Document 1108275Source PDF
- ReportsSource: planningapi.agileapplications.ie / FW25A_0173E_-_NTA.pdf / Document 1109181Source PDF
- ReportsSource: planningapi.agileapplications.ie / FW25A0173E.docx / Document 1109798Source PDF
- ReportsSource: planningapi.agileapplications.ie / FW25A_0173E_-_Uisce_Eireann.pdf / Document 1109902Source PDF
- ReportsSource: planningapi.agileapplications.ie / FW25A_0173E_-_TII.pdf / Document 1110143Source PDF
- ReportsSource: planningapi.agileapplications.ie / FW25A.0173E_Air_and_Noise_Report.pdf / Document 1110867Source PDF
- ReportsSource: planningapi.agileapplications.ie / FW25A_0173E_-_Dept_Hsg_Local_Govt_&_Heritage.pdf / Document 1110915Source PDF
- ReportsSource: planningapi.agileapplications.ie / F25A_0173E_National_Cricket_Centre.docx / Document 1111206Source PDF
- ReportsSource: planningapi.agileapplications.ie / FW25A0173E_Sports_Ireland_National_Sports_Campus_(Cricket_Stadium).docx / Document 1111574Source PDF
- ReportsSource: planningapi.agileapplications.ie / Arch_Report_FW25A0173E_Sports.docx / Document 1112150Source PDF
- ReportsSource: planningapi.agileapplications.ie / FW25A-0173E_-_Transport_Infrastructure_Ireland.pdf / Document 1127906Source PDF
- ReportsSource: planningapi.agileapplications.ie / Arch_report_FW25A0173E_Sports_Ireland_AI.docx / Document 1128023Source PDF
- ReportsSource: planningapi.agileapplications.ie / FW25A_-_0175E_AI_Dept._of_Defence / Document 1128733Source PDF
- ReportsSource: planningapi.agileapplications.ie / FW25A__0173E_SAI.docx / Document 1133633Source PDF
- ReportsSource: planningapi.agileapplications.ie / FW25A-0173E-AI.docx / Document 1133634Source PDF
- ReportsSource: planningapi.agileapplications.ie / FW25A.0173E_AI_Air_and_Noise_Report.pdf / Document 1134471Source PDF
- ReportsSource: planningapi.agileapplications.ie / FW25A0173EAI_Sports_Ireland_National_Sports_Campus_(Cricket_Stadium).docx / Document 1134526Source PDF
- ReportsSource: planningapi.agileapplications.ie / FW25A-0173E_-_Sport_Ireland_National_Sports_Campus_-_Public_Lighting_Report_22092025.docx / Document 1134830Source PDF
Nearby precedent
Similar nearby applications linked to this planning decision.- FW17A/0060High performance centre / 0.2 km away / 09 June 2017Granted
- FW14A/0135Permission for development at this site. The development will consist / 0.2 km away / 11 March 2015Granted
- FW23A/0051For permission/retention permission / 0.3 km away / 27 April 2023Granted
- FW22A/0060The development will consist of: A temporary single storey office development (753m2) for a period not greater than 7 years. The works will comprise a number of individually accessible office units with common toilet and welfare facilities around a central landscaped space; The provision of a permanent extension to the existing car park to provide 25no. additional spaces, 14 No. bicycle parking spaces; set down areas; and all associated site development, har/soft landscaping, site lighting and excavation works above and below ground. / 0.3 km away / 26 May 2022Granted
- FW14A/0125Permission for development that will consist of the demolition ofthe O / 0.3 km away / 18 November 2014Granted
- FW14A/0018Permission for development at this site. The development consists of:- / 0.3 km away / 03 April 2014Granted
- FW20A/0185A single storey temporary modular structure extension (122m²) to the side of the Irish Institute of Sport (IIS) building (A Protected Structure), (formerly the Central Meat Control laboratory) for a period not greater than 7 years. The work will comprise: open plan/cellular office and meeting spaces (115m²); an interlink corridor (7m²) and all associated site development, hard and soft landscaping and excavation works above and below ground. / 0.3 km away / 17 December 2020Granted
- FW12A/0118Permission for development at this site. This development will consist / 0.4 km away / 14 January 2013Granted