NATIONAL OIL RESERVES AGENCY, TARBERT OIL STORAGE PLAN, TARBERT ISLAND TARBERT CO KERRY
Planning application 25115
DecisionConditional grant
Decided16 October 2025
Application typePERMISSION
Source documents1
Site
What is on file
0refusal reasons0conditions8nearby records
Proposed development
Application description published by Kerry County Council.Decision details
Core application dates and identifiers from the public planning record.Planning analysis
Refusal reasons and planning conditions extracted from the public decision file.Refusal reasons
No refusal reason on record
Documents are indexed. Reason extraction for Kerry has not started yet.
Conditions
No conditions
No conditions are on record for this application yet.
Planning a project near NATIONAL OIL RESERVES AGENCY, TARBERT OIL STORAGE PLAN, TARBERT ISLAND TARBERT CO KERRY?
Get a site risk brief with the local decision pattern and up to 80 detailed nearby comparables (40 refusals and 40 grants), including extracted reasons and source links. €49 incl. VAT, PDF by email.Source documents
Original council portal records and source PDFs where available.- Application fileApplication file on www.eplanning.ieSource portal
Nearby precedent
Similar nearby applications linked to this planning decision.- 18392CONSTRUCT A BATTERY STORAGE FACILITY WITHIN A TOTAL SITE AREA OF UP TO 2.278HA, TO INCLUDE 50 NO. SELF CONTAINED BATTERY CONTAINER UNITS WITH ASSOCIATED HVAC COOLING UNITS, 13 CONVERTER AND 13 STEP UP TRANSFORMER CONTAINER UNITS, ASSOCIATED COMPOUND CABLING AND DUCTING, A GRID TRANSFORMER, A SINGLE STOREY SUBSTATION / CONTROL BUILDING WITH WELFARE FACILITIES, A CABLE ROUTE GRID CONNECTION TO THE EXISTING ESB SUBSTATION BUILDING, MAINTENANCE LIGHTING, SECURITY FENCING, A CCTV MONITORING SYSTEM,AND ALL ASSOCIATED ANCILLARY INFRASTRUCTURE ON LANDS WITHIN THE TARBERT GENERATING FACILITY. A TEN YEAR PLANNING PERMISSION IS BEING SOUGHT TO CONSTRUCT THE DEVELOPMENT / 0.4 km away / 15 January 2019Granted
- 23350THE PROPOSED DEVELOPMENT WILL COMPRISE OF THE FOLLOWING ON A SITE MEASURING APPROXIMATELY 6.9 HECTARES: (1) REMOVAL OF EXISTING CABLE JOINT, BAY WITHIN TARBERT GENERATING STATION, 220kV SWITCHGEAR WITHIN THE EXISTING TARBERT SUBSTATION COMPOUND AND ASSOCIATED 220kV CABLING; (2) TWO NO. NEW LENGTHS OF 220kV UNDERGROUND CABLING MEASURING APPROXIMATELY 340M EACH, RUNNING BETWEEN TWO NO. NEW UNDERGROUND CABLE JOINT BASE IN TARBERT GENERATING STATION AND THE CONNCETION POINT AT TARBERT SUBSTATION; (3) THE NEW 220kV SWITCHGEAR BAY WITHIN THE EXISTING TARBERT SUBSTATION COMPOUND COMPRISING ASSOCIATED ELECTRICAL EQUIPMENT, INCLUDING CABLE SEALING ENDS, INSULATORS, OVER HEAD CONDUCTORS, SURGE ARRESTORS, LIGHTNING MASTS AND LIGHTING POLES; AND (4) ALL ANCILLARY SITE DEVELOPMENT WORKS INCLUDING TEMPORARY CONSTRUCTION COMPUND AND LAYOUT AREAS, SITE PREPARATION WORKS AND GROUND LEVELING AS REQUIRED TO FACILITATE THE WORKS. TARBERT GENERATING STATION IS LICENSED BY THE ENVIRONMENT PROTECTION AGENCY (EPA) UNDER THE INDUSTRIAL EMISSIONS (IE) LICENSE (REF: P0607-02). THE PROPOSED DEVELOPMENT INCLUDES WORKS LOCATED WITHIN THE IE LICENSE BOUNDARY OF TARBERT GENERATING STATION WHICH IS AN UPPER TIER ESTABLISHMENT TO WHICH THE CHEMICALS ACT (CONTROL OF MAJOR ACCIDENTS HAZARDS INVOLVING DANGEROUS SUBSTANCES) REGULATIONS 2015 (THE COMAH REGULATIONS) APPLY. THIS PLANNING IS ACCOMPANIED BY A NATURA IMPACT STATEMENT (NIS). AMENDMENTS TO THE NIS HAVE BEEN MADE IN RESPONSE TO THE FURTHER INFORMATION REQUEST / 0.7 km away / 06 December 2023Granted
- 19115THE DEVELOPMENT WILL CONSIST OF A GRID STABILISATION FACILITY COMPRISING OF: THE CONSTRUCTION UP TO 4 NO. ROTATING STABILISERS, 5 NO. BATTERY STORAGE CONTAINERS, 1 NO. CONTROL ROOM, 2 TRANSORMERS AND ANCILLARY EQUIPMENT WITHIN A SITE AREA OF APPROX. 1.46 HECTARES. IT IS PROPOSED TO CONNECT THE PROPOSED DEVELOPMENT TO THE ADJACENT EIRGRID SUBSTATION BY UNDERGROUND CABLE WHICH WILL TRAVERSE THE PERMITTED AND UNDER CONSTRUCTION PEAKING PLANT. THE ROTATING STABILISERS WILL BE SUPPORTED BY 10 NO. ELECTRICAL EQUIPMENT ROOMS WHICH WILL CONTAIN ANCILLARY POWER SUPPLY PRODUCTS INCLUDING A STATIC FREQUENCY CONVERT (SFC), MV SWITCHGEAR, EXCITERS AND LV DISTRIBUTION, AND STEP-UP / DOWN TRANSFORMERS. A HEATING VENTILATION AND AIR CONDITIONING SYSTEM (HVAC) WILL BE ATTACHED TO EACH ROTATING STABILISER, 4 NO. AUXILIARY TRANSFORMERS ARE ALSO PROPOSED. THE BATTERY CONTAINERS WILL HOUSE INDIVIDUAL BATTERY COMPONENTS WITH 2 NO. FITTED EXTERNAL HVAC SYSTEM FOR EACH. 13 NO. INVERTER STATIONS AND 14 AUXILIARY TRANSFORMERS ARE PROPOSED FOR THE BATTERY CONTAINERS. THE ENTIRE SITE WILL CONSIST OF VARIOUS UNDERGROUND CABLES AND DUCTS, BOUNDARY SECURING FENCE, COMPOUND LIGHTING AND PALISADE GATES AND FENCING, NEW INTERNAL ACCESS TRACK, SECURITY LIGHTING, CCTV, HARDSTANDING AREAS AND ALL NECESSARY FOUNDATION WORKS. PERMISSION IS ALSO SOUGHT FOR 2 ELECTRICAL TRANSFORMERS (UP TO 220KV), ASSOCIATED HV EQUIPMENT AND UNDERGROUND ELECTRICAL GRID CONNECTION CABLING AND DUCTING CONNECTING THE DEVELOPMENT TO THE NATIONAL GRID AT THE ADJACENT ESB/EIRGRID SUBSTATION. PLANNING PERMISSION IS SOUGHT FOR A PERIOD OF 10 YEARS. A NATURA IMPACT STATEMENT (NIS) ACCOMPANIES THIS APPLICATION / 1.4 km away / 07 February 2020Granted
- 21549(A) A HIGH INTERTIA SYNCHRONOUS COMPENSATOR (HISC) COMPOUND CONTAINING 1 NO. HISC UNIT ENCLOSED WITHIN A STEEL CLAD FRAMED STYLE STRUCTURE (12.1M MAX HEIGHT) AND SUPPPORTED BY 8 NO. ELECTRICAL EQUIPMENT CONTAINERS (CONTAINING ANCILLARY POWER SUPPLY PRODUCTS INCLUDING A STATIC FEQUENCY CONVERTS, MV SWITCHGEAR, EXCITERS, LV DISTRIBUTION, CONTROL ROOM, WELFARE AND OFFICE), MAIN AUXILIARY AND START-UP ELECTRICAL TRANSFORMERS, GENERATOR CIRCUIT BREAKER, SWITCHGEAR EQUIPMENT, EXTERNAL COOLER UNITS AND 1 NO. BACK UP DIESEL GENERATOR AND ASSOCIATED DIESEL STORAGE TANK; (B) A 220KV HIGH VOLTAGE GAS INSULTATED SWITCHGEAR (GIS) SUBSTATION COMPOUND CONTAINING A GIS SUBSTATION BUILDING WITH ALL CONTROL AND HV EQUIPMENT WITHIN A SINGLE STOREY BUILDING (13.2M MAX HEIGHT). THE BUILDING WILL BE SURROUNDED BY A COMPOUND ROAD AND CONTAINED WITHIN A 2.6M HIGH GALVANISED STEEL PALISADE FENCE; (C) A BATTERY STORAGE COMPOUND CONTAINING 5 NO. BATTERY STORAGE CONTAINERS, ENCLOSED IN STEEL CONTAINERS OF DIMENSIONS APPROXIMATELY 13M BY 2.5M BY 3M, HOUSING INDIVIDUAL BATTERY COMPONENTS WITH 2 NO FITTED EXTERNAL HVAC SYSTEMS FOR EACH UNIT AND SUPPORTED BY 13 NO. INVERTER STATIONS, 14 NO. AUXILIARY TRANSFORMERS AND CONTROL CONTAINER; (D) 220KV UNDERGROUND CABLE TO THE EXISTING ADJOINING EIRGRID SUBSTATION; (E) ASSOCIATED ELEMENTS COMPRISING VARIOUS UNDERGROUND CABLES AND DUCTS, EQUIPMENT PLINTHS, BOUNDARY SECURITY FENCE, COMPOUND LIGHTING AND PALISADE GATES AND FENCING, SECUIRTY LIGHTING, CCTV, INTERNAL ACCESS ROADS, HARDSTANDING AREAS AND ALL NECESSARY FOUNDATIONS WORKS FOR THE ABOVE COMPOUNDS. THE PLANNING APPLICATION IS ON LANDS WHERE GRID STABILISATION FACILITY WAS PREVIOUSLY PERMITTED UNDER PLANNING REGISTER NO 19/115. PLANNING PERMISSION TO CONSTRUCT THE DEVELOPMENT IS SOUGHT FOR A PERIOD OF 10 YEARS. A NATURA IMPACT STATMENT (NIS) HAS BEEN PREPARED IN RESPECT OF THE PROPOSED DEVELOPMENT AND ACCOMPANIES THE APPLICATION / 1.4 km away / 19 July 2021Granted
- 20850FOR CHANGES TO THE PREVIOUSLY PERMITTED PEAKER POWER PLANT DEVELOPMENT (PLANNING REF. 13/138). IT IS PROPOSED TO CHANGE THE ENERGY SOURCE FOR THE CHARGING OF THE BATTERY ENERGY STORAGE SYSTEM (BESS) CONTAINERS FROM DIESEL TO CHARGING OFF THE NATIONAL GRID AND TO CHANGE THE PERMITTED LAYOUT FOR ELECTRICAL EQUIPMENT BASED ON THE CONSEQUENCE OF THE PROPOSED CHANGE IN ENERGY SOURCE AT AN AREA LOCATED WITHIN THE PERMITTED DEVELOPMENT. IT IS ALSO PROPOSED TO INCLUDE A SMALL METERING ENCLOSURE ADJACENT TO THE CONSTRUCTED SUBSTATION BUILDING WITHIN THE PERMITTED DEVELOPMENT. A FIVE YEAR PLANNING PERMISSION IS BEING SOUGHT FOR THE PROPOSED DEVELOPMENT / 1.4 km away / 12 November 2020Granted
- 2460615Change of use for a business unit to residential at no 5. / 1.4 km away / 18 October 2024Granted
- 2460616Change of use for a business unit to residential at no 6 / 1.4 km away / 22 October 2024Granted
- 21305RETAIN AN EXISTING TELECOMMUNICATIONS SUPPORT STRUCTURE (PREVIOUSLY GRANTED UNDER LOCAL AUTHORITY REF NO. 11/969) (AN BORD PLEANALA REFERENCE PL 08.240232) TOGETHER WITH ASSOCIATED GROUND EQUIPMENT, SECURITY FENCE, AND ACCESS TRACK / 1.4 km away / 18 May 2021Granted